Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Eltiera Views handover date?

Updated 11 October 2026 Eltiera Views

Short answer

The DLD register holds a completion date of 31 December 2029 for Eltiera Views, and Ellington Properties markets Q4 2029. Progress on the register is 0%, from an inspection on 5 December 2025; construction was registered as starting on 16 April 2026. One portal lists December 2028, which is the date reported for Ellington's earlier Eltiera Heights, not this project.

Registered completion date

31 Dec 2029

DLD project register via Data Dubai and Continental Club

Latest DLD construction progress

0%

DLD inspection, 5 Dec 2025; works registered from 16 Apr 2026

Developer's stated date

Q4 2029

Ellington, via brokers' developer price lists, Oct 2026

Date change since launch

None

Q4 2029 quoted since launch; Certified Poor's Dec 2028 does not match the register

Eltiera Views handover date: the latest position

The DLD register holds a completion date of 31 December 2029 for Eltiera Views, and Ellington Properties markets Q4 2029. Full project details are on the Eltiera Views page.

The project is at an early stage. Its only DLD inspection, on 5 December 2025, recorded 0%, and the registered construction start date is 16 April 2026. The register has no newer progress figure, so the 2029 date has not yet been tested against site progress.

Eltiera Views handover date by building

The DLD register treats Eltiera Views as one project of 1,185 units (DLD project 4116), while broker price lists split the stock into Tower 1 and Tower 2.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Eltiera Views (Tower 1 and Tower 2, 1,185 units) 0% (5 Dec 2025) 31 Dec 2029 Q4 2029 (Narva, DirectDXB, Oct 2026); Dec 2028 (Certified Poor)

The December 2028 figure on Certified Poor matches the date reported for Eltiera Heights, Ellington’s earlier and separate project on the same lake. It does not match the DLD record for Eltiera Views.

How the Eltiera Views handover date has changed

Date Event Source
3 to 5 Dec 2025 Ellington announces the “coming soon” campaign Ellington Properties
5 Dec 2025 DLD inspection records 0% DLD register via Continental Club
19 Mar 2026 Ellington announces the launch Gulf Construction Online
16 Apr 2026 Registered construction start DLD register via Data Dubai
6 May 2026 Project registered with DLD; first sales recorded in May Data Dubai
Oct 2026 Completion date on the register still 31 December 2029; brokers quote Q4 2029 Data Dubai, Narva

The date has not moved since launch. The registered construction period, from April 2026 to December 2029, is about 44 months.

What the Eltiera Views handover date means for payments

Ellington’s plan puts 30% of the price on completion. The other 70% is paid before it: 20% on booking, 10% at 60 days, 5% at each of 120, 180, 240 and 360 days, and 5% at each of the 20%, 30%, 40% and 50% construction stages. Because the first 50% is time based, it falls due in the first year whatever the pace on site. The four construction stage payments, and the final 30%, move if the building runs late. On the median 1 bedroom DLD sale of AED 2.04 million, the completion payment is about AED 612,000.

What to check before relying on the Eltiera Views date

  1. Which tower the unit is in, and the date in its SPA. The register shows one date for the project; contracts may set dates by tower.
  2. The first DLD inspection after April 2026. It will show whether work is keeping pace with a December 2029 finish.
  3. That the project is Eltiera Views and not Eltiera Heights. Some portals mix the two names and dates.

Questions buyers also ask

What is the Eltiera Views completion date?

The DLD register holds 31 December 2029 for Eltiera Views (DLD project 4116, 1,185 units), per Data Dubai with data through 29 September 2026. Ellington markets Q4 2029.

Is Eltiera Views the same as Eltiera Heights?

No. Both are Ellington projects beside the Jumeirah Islands lake. Eltiera Heights launched first, sold out, and is reported for December 2028 (HCO Real Estate, July 2026). Eltiera Views is a separate DLD project with a completion date of 31 December 2029.

Do both Eltiera Views towers hand over at the same time?

Brokers quote Q4 2029 for both Tower 1 and Tower 2 (Narva, Oct 2026), and the DLD register holds one completion date, 31 December 2029, for the 1,185 unit project.

How much is due at the Eltiera Views handover?

30% of the price is due on completion under Ellington's plan. On the median 1 bedroom sale of AED 2.04 million, that is about AED 612,000; on the median 2 bedroom sale of AED 3.16 million, about AED 948,000.

Sources

  1. Ellington Properties, Eltiera Views project site and payment plan (opens in a new tab)eltiera-views.ellingtonproperties.ae · accessed 11 Oct 2026
Request a Unit Review