Handover date

When is the Dubai Lagoon handover date?

Updated 6 October 2026 Dubai Lagoon

Short answer

Dubai Lagoon has no handover date: Schon Properties promised handover in 2008, and no building has been delivered since. The DLD record for the Lily zone shows 54.89% construction progress (via Dubricks, inspection date not shown), and the Dubai REST app has listed the project as under cancellation since 22 October 2024 (Khaleej Times). Until that status is resolved, buyers can neither take handover nor receive refunds.

Estimated completion, Lily

Sep 2020

Propsearch, from DLD data; passed

Latest construction progress, Lily

54.89%

DLD project 1564 via Dubricks, inspection date not shown

Developer's original date

2008

Schon Properties at launch, via Khaleej Times

DLD status

Under cancellation

Since 22 Oct 2024; Khaleej Times, 22 Dec 2024

Dubai Lagoon handover date: the latest position

Dubai Lagoon, Schon Properties’ 2005 apartment project in Dubai Investments Park, has no handover date. Handover was first promised for 2008, and in the 18 years since no building has been delivered to buyers. Planned size, prices and the history of the developers are on the Dubai Lagoon page.

The Dubai REST app listed the project as cancelled on 6 October 2024 and changed it to under cancellation on 22 October 2024 (Khaleej Times, 22 December 2024). Data Habibi dates the change to October 2023, so sources differ on the year. A DLD representative told one buyer the project would either be transferred to another developer or buyers refunded, and that refunds cannot start while the status stays under cancellation. Propsearch’s page, updated 1 October 2025, shows no later step.

Dubai Lagoon handover date by building

Zone Construction progress (DLD, date) Registered or estimated completion Developer or portal date
Lily (DLD 1564, 688 units) 54.89% (via Dubricks, date not shown); building D20 reported complete by a buyer, Dec 2024 Sep 2020 (Propsearch) 2020 (Xanadu, 2018); first building pending Civil Defence approval, Mar 2022
Lotus (8 buildings) 90% (Schon, Aug 2019) Not published June 2020 (Schon, Aug 2019); Q3 2007 at launch (Data Habibi)
Rowan, Winterberry (10 buildings) Not published Not published 2020 (Schon and Xanadu, Feb 2017)
Whole project (54 buildings) Under cancellation, 22 Oct 2024 Passed 2008 at launch

The Lily percentage carries no inspection date on the copy of the DLD record available, so its age is unknown. Lily’s unit count also differs: 880 apartments in Schon’s 2017 transfer, 688 on the DLD record.

How the Dubai Lagoon handover date has changed

Date What happened Source
2005 to Mar 2006 Launch; first phase sold out in 54 days, handover promised for 2008 Khaleej Times
24 Feb 2014 Zone 1 handover set for H2 2014, whole project by 2016 Construction Week
29 Nov 2016 200 units said complete; first residents Q1 2017; all by 2019 or 2020 The National
28 Feb 2017 Lily, Rowan and Winterberry transferred to Xanadu; completion by 2020 The National
Aug 2018 DLD moves to seize Schon’s property, plots and funds Propsearch, citing The National
8 Aug 2019 Lotus said 90% complete, handover June 2020 The News
Mar 2022 First Lily building said to await Civil Defence approval Gulf News
6 and 22 Oct 2024 Status changed to cancelled, then under cancellation Khaleej Times

What the Dubai Lagoon handover date means for payments

There is no handover payment to plan for while the project is under cancellation. Many buyers have already paid most of the price: Khaleej Times reported buyers who had paid 75%, 90% and 100%, including one who paid a final 10% in 2018 on a promise of completion by 2020. Any refund or transfer will turn on what each buyer has paid and can document.

What to check before relying on the Dubai Lagoon date

  1. The DLD status of the specific zone, Lily or Lotus, on the Dubai REST app, since only a change from under cancellation unlocks transfer or refund.
  2. Whether the unit is blocked by a court order, as Dubai Courts blocked units held under Schon Properties.
  3. Which developer holds the unit, Schon or Xanadu, after the 2017 split.
  4. Proof of every payment, since some buyers paid Schon and others paid Xanadu or a transferring developer.

Questions buyers also ask

Has Dubai Lagoon been handed over?

No. None of the 54 planned buildings has been handed over. A Lily investor told Khaleej Times in December 2024 that building D20 was complete but not handed over.

Is Dubai Lagoon cancelled?

It is under cancellation. The Dubai REST app showed cancelled on 6 October 2024 and under cancellation from 22 October 2024 (Khaleej Times). Data Habibi dates this to October 2023, so sources differ on the year.

Has the Dubai Lagoon handover date been delayed?

Repeatedly. Handover was promised for 2008, then H2 2014 for Zone 1 and 2016 for the whole project, then 2017, 2019 to 2020 and June 2020 for Lotus. Each date passed without a handover.

What happens to Dubai Lagoon buyers now?

A DLD representative told one buyer the outcome would be a transfer to another developer or refunds, and that refunds cannot proceed while the project stays under cancellation (Khaleej Times, 22 Dec 2024).

Sources

  1. Propsearch, Dubai Lagoon (opens in a new tab)propsearch.ae · updated 1 Oct 2025
  2. Propsearch, Dubai Lagoon Lily (opens in a new tab)propsearch.ae · updated 7 May 2025
  3. Data Habibi, Dubai Lagoon Lotus (opens in a new tab)datahabibi.ae · accessed 6 Oct 2026