Handover date

When is the Divine Al Barari handover date?

Updated 11 October 2026 Divine Al Barari

Short answer

Divine Al Barari has a registered completion date of 31 March 2028, and Takmeel Developments gives a Q2 2028 handover. The tower was 12.28% complete at a Dubai Land Department inspection on 19 May 2026, about six months after construction started. The registered date sits at the end of Q1 2028, slightly ahead of the developer's own quarter.

Registered completion date

31 Mar 2028

DLD project register via Continental Club

Latest construction progress

12.28%

DLD inspection, 19 May 2026

Takmeel's stated handover

Q2 2028

Zawya, 2 Oct 2025 and 24 Jan 2026

Change since launch

None

Q2 2028 at launch in Oct 2025

Divine Al Barari handover date: the latest position

Divine Al Barari is registered with the Dubai Land Department (DLD) for completion on 31 March 2028. Takmeel Developments has said Q2 2028 since it launched the tower on 2 October 2025, and repeated that date at the groundbreaking in January 2026. The registered date falls one day before Q2 2028 begins. Prices, sizes and the payment plan are on the project page: Divine Al Barari.

The latest DLD inspection, on 19 May 2026, recorded 12.28% complete. That reading came about six and a half months after the registered construction start of 1 November 2025.

Divine Al Barari handover date by building

Divine Al Barari is one building of 291 units (DLD project number 3759), with a ground floor, two podium levels, 17 residential floors and a roof.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Divine Al Barari (291 units) 12.28% (19 May 2026) 31 Mar 2028 Q2 2028 (Takmeel); June 2028 (Impala Real Estate); March 2028 (Projectory)

The previous DLD inspection, on 21 May 2025 before construction began, recorded 0% (DLD project register via Continental Club, updated 29 September 2026). No inspection after May 2026 had been published by that update.

How the Divine Al Barari handover date has changed

Date Event Source
21 May 2025 DLD inspection before construction: 0% DLD via Continental Club
2 Oct 2025 Launched at AED 400 million, handover Q2 2028, studios from AED 717,000 Zawya
1 Nov 2025 Construction start recorded. Registered completion 31 March 2028 DLD via Continental Club
24 Jan 2026 Groundbreaking announced, handover still Q2 2028 Zawya
19 May 2026 DLD inspection: 12.28% DLD via Continental Club
23 Sep 2026 Broker feed lists June 2028 as scheduled end of construction Impala Real Estate

The developer’s date has held since launch. The only spread is between sources: end of March 2028 on the register, Q2 2028 from Takmeel and June 2028 in one broker feed.

What the Divine Al Barari handover date means for payments

Takmeel’s factsheet plan is 40/60. Buyers pay 10% on reservation, 10% a month later and 5% at 6, 12, 18 and 24 months, for 40% in total, then 60% on handover (Seven Century). The 24 month instalment falls before the registered completion date, so on this plan nothing is due between that instalment and handover. If handover moves, only the 60% payment moves with it. Buyers on a post-handover plan, such as 10% on booking, 40% during construction, 10% on handover and 40% over 36 months (Katalystor), would see the 36 month schedule start from the actual handover date.

What to check before relying on the Divine Al Barari date

  1. The completion date and grace period in the SPA, since three sources give three slightly different months.
  2. How the 60% handover payment will be funded, and whether a mortgage valuation at completion could fall short of it.
  3. The next DLD inspection. The 12.28% figure dates from 19 May 2026, and a newer reading will show whether the pace supports a March 2028 completion.

Questions buyers also ask

When will Divine Al Barari be completed?

The DLD register records a completion date of 31 March 2028. Takmeel has given Q2 2028 since launch, and one broker feed lists June 2028 as the scheduled end of construction (Impala Real Estate, Sep 2026).

Is Divine Al Barari under construction?

Yes. The DLD register records a construction start on 1 November 2025, Takmeel announced its groundbreaking on 24 January 2026, and the tower was 12.28% complete on 19 May 2026.

Has the Divine Al Barari handover date been delayed?

No. Takmeel's Q2 2028 date has not changed since the October 2025 launch, and the registered completion date of 31 March 2028 is slightly earlier.

How much is due on handover at Divine Al Barari?

On Takmeel's factsheet plan, 60% of the price is due on handover, after 40% paid over the first 24 months (Seven Century). For a studio at the launch price of AED 717,000, that is AED 430,200.

Sources

  1. DLD project register via Continental Club, Divine Al Barari (opens in a new tab)continentalclub.ae · inspection 19 May 2026, registry updated 29 Sep 2026