Handover date

When is the District One West handover date?

Updated 4 October 2026 District One West

Short answer

District One West Phase 1 is listed for completion on 3 March 2027 by Property Finder, and Propsearch estimates June 2027; the DLD register data holds no completion date for it. Phase 2 has a registered completion date of 19 November 2027, while Meydan's main contract for it, awarded in January 2025, runs to Q1 2028. DLD inspections recorded Phase 1 at 92.56% on 28 September 2026 and Phase 2 at 40.9% on 14 July 2026, so the phases will hand over at different times.

Registered completion date (DLD), Phase 2

19 Nov 2027

DLD project 3200, via Overit. Phase 1: none on file

Latest construction progress, Phase 1

92.56%

DLD inspection, 28 Sep 2026. Phase 2: 40.9%, 14 Jul 2026

Developer's stated date, Phase 2

Q1 2028

Meydan contract award, 20 Jan 2025

Portal date, Phase 1

Q1 2027

Property Finder 3 Mar 2027; Propsearch Jun 2027

District One West handover date: the latest position

District One West will not hand over in one go. Phase 1 is listed for completion on 3 March 2027 by Property Finder, with Propsearch estimating June 2027, and was 92.56% built at the DLD inspection on 28 September 2026, up from 82.5% on 25 June. Phase 2 has a registered completion date of 19 November 2027 and was 40.9% built on 14 July 2026. Prices, sizes and the payment plan are on the District One West page.

For Phase 2, Meydan’s own date is later than the register. When it awarded the main contract to Ginco General Contracting on 20 January 2025, it said the phase was scheduled for completion in Q1 2028.

District One West handover date by phase

The DLD register holds the two phases as separate projects, both filed by Meydan Group, while Nakheel markets them and publishes the construction updates.

Phase Construction progress (DLD, date) Registered completion date Developer or portal date
Phase 1, 468 villas and mansions (DLD 2696) 92.56%, 28 Sep 2026 Not on file 3 Mar 2027 (Property Finder); Jun 2027 (Propsearch)
Phase 2, 229 villas (DLD 3200) 40.9%, 14 Jul 2026 19 Nov 2027 Q1 2028 (Meydan contract, Jan 2025); Nov 2027 (Propsearch)

Nakheel’s internal inspection on 11 June 2026 gave 83.37% for Phase 1, with superstructure at 98.9%, building work at 77.1%, MEP at 72.4% and infrastructure at 69.4%. For Phase 2 it gave 34.49%, with superstructure at 51.31%. The DLD inspections that followed put Phase 1 at 82.5% on 25 June and 92.56% on 28 September 2026, and Phase 2 at 40.9% on 14 July.

How the District One West handover date has changed

Date What happened Source
21 Jun 2023 Phase 1 registered with DLD DLD register, via HomeSearch
1 Aug 2023 Phase 1 booking opens Property Finder, via Rumavi
Dec 2023 Phase 1 construction begins Propsearch
Feb 2024 Main contracts to Fibrex Contracting and Ginco General Contracting Propsearch
1 Oct 2024 Phase 2 registered with DLD; registered start 20 Nov 2024, completion 19 Nov 2027 DLD register, via HomeSearch and Overit
20 Jan 2025 Phase 2 contract to Ginco, completion Q1 2028 Meydan via Dubai Holding
12 Mar 2026 Phase 1 at 73.31% (RERA) Nakheel
17 Apr 2026 Phase 2 at 31.24% (RERA) Nakheel
25 Jun 2026 Phase 1 at 82.5% DLD inspection
14 Jul 2026 Phase 2 at 40.9% DLD inspection
28 Sep 2026 Phase 1 at 92.56%; still no completion date on the register DLD inspection, via fäm Properties

Neither phase has had a revised date announced. Propsearch’s June 2027 estimate for Phase 1 is three months later than Property Finder’s March 2027 date.

What the District One West handover date means for payments

The plan is 20% at booking, 60% during construction and 20% at handover (Property Finder). On a villa at the lowest listed price of AED 12.5 million, the handover payment is AED 2.5 million. Phase 1 buyers are likely to face that payment during 2027. For Phase 2, the difference between the 19 November 2027 registered date and the Q1 2028 contract date could move it by a few months.

What to check before relying on the District One West date

  1. Which phase the villa is in. HomeSearch lists Phase 1 villas under DLD project 2696 and Phase 2 under 3200; resale paperwork shows which applies.
  2. The completion date in the SPA for Phase 1. The register data shows no completion date for Phase 1, so the SPA date and its grace period are the only contractual reference.
  3. For Phase 2, the SPA date against Q1 2028. The contract date is a few months after the 19 November 2027 registered date.
  4. The developer entity on the SPA. The register names Meydan Group, while Nakheel markets the project and reports progress.

Questions buyers also ask

Is District One West finished?

No. The DLD inspection on 28 September 2026 put Phase 1 at 92.56%, and the inspection on 14 July 2026 put Phase 2 at 40.9%. Nakheel's July 2026 update said Phase 1 was in interior works, exterior finishes and infrastructure, while more Phase 2 villas were still rising.

When will District One West Phase 1 be ready?

Property Finder lists expected completion on 3 March 2027 and Propsearch estimates June 2027. The DLD register data republished by HomeSearch and Rumavi shows no completion date for Phase 1. Nakheel's internal inspection on 11 June 2026 put superstructure at 98.9%, with building work at 77.1% and infrastructure at 69.4%.

When will District One West Phase 2 be ready?

The DLD register gives a completion date of 19 November 2027, and Propsearch estimates November 2027. Meydan's contract award to Ginco General Contracting on 20 January 2025 set completion for Q1 2028.

What is the District One West completion date?

It depends on the phase: Q1 to mid 2027 for Phase 1 on portal estimates, and 19 November 2027 on the register, or Q1 2028 on the contract, for Phase 2.

Has the District One West handover date been delayed?

No revised date has been announced for either phase. Phase 2's contract date of Q1 2028 is later than its registered completion date of 19 November 2027, so the register date may not hold.