When is the Dar Al Aiham One handover date?
Short answer
Dar Al Aiham One is due for handover in Q2 2027, with a registered completion date of 30 June 2027 in the Dubai Land Department project register. The DLD inspection of 3 August 2026 recorded 20.78% complete. The date has not changed, but the building would need to more than double its pace of about 3 points a month to finish on time.
Registered completion date (DLD)
30 Jun 2027
DLD project register via Continental Club, registry updated 5 Oct 2026
Latest construction progress
20.78%
DLD inspection, 3 Aug 2026
Developer's stated date
Q2 2027
Developer supplied, via Continental Club; Property Finder
Change since launch
None
Q2 2027 in listings since early 2026
Dar Al Aiham One handover date: the latest position
Dar Al Aiham One has a registered completion date of 30 June 2027 in the Dubai Land Department (DLD) project register, and the developer gives Q2 2027. The DLD inspection of 3 August 2026 recorded 20.78% complete. Full project details are on the Dar Al Aiham One page.
Unlike many off-plan projects, the developer, the portals and the register all show the same date. The question is pace: about 79% of the building remained with 11 months to go.
Dar Al Aiham One handover date by building
Dar Al Aiham One is a single G+1P+6 building in Warsan Fourth, International City Phase 2.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Dar Al Aiham One (71 units) | 20.78% (3 Aug 2026) | 30 Jun 2027 | Q2 2027 (developer); 30 June 2027 (Property Finder) |
Figures from the DLD register via Continental Club, registry updated 5 October 2026. The developer’s brochure gives 70 units and Data Habibi 59, against 71 in the register.
How the Dar Al Aiham One handover date has changed
| Date | What was stated | Source |
|---|---|---|
| 30 Dec 2025 | Registered construction start; completion date 30 June 2027 | DLD register via Continental Club |
| 8 Jan 2026 | DLD inspection at 0% | DLD register via Continental Club |
| Feb 2026 | Brochure circulated; listings quote Q2 2027 | DXB Off Plan; Buy Dubai Off Plan |
| 3 Aug 2026 | DLD inspection at 20.78%; date unchanged | DLD register via Continental Club |
| Oct 2026 | Q2 2027 still given | Continental Club; Property Finder |
The date has held since the project was registered. No inspection between January and August 2026 has been published, so the shape of progress within that period is not known.
What the Dar Al Aiham One handover date means for payments
The plan is 30% during construction and 70% on handover (Data Habibi; Buy Dubai Off Plan). Seven tenths of the price is tied to completion, so any slip in the date moves the largest payment by the same amount. On the AED 630,000 launch price shown by Property Finder, that is about AED 189,000 during construction and about AED 441,000 on handover. Buy Dubai Off Plan describes the construction payments as linked to milestones such as foundations, structure and finishing, so slower building would also spread those instalments out.
What to check before relying on the Dar Al Aiham One date
- The pace from here. About 7 points a month would be needed to reach 100% by 30 June 2027, against roughly 3 points a month from January to August 2026.
- The SPA date and grace period, which govern what happens if completion runs past June 2027.
- The developer’s record. Dar Al Aiham Properties was founded in 2025, so there are no earlier completions to judge timing by.
Questions buyers also ask
What is the Dar Al Aiham One completion date?
30 June 2027, the completion date for DLD project 4323, Dar Al Aiham One (via Continental Club). Property Finder shows the same date.
Has the Dar Al Aiham One handover date been delayed?
No change has been published. Property Finder, Data Habibi, Buy Dubai Off Plan and the DLD register all give Q2 2027 or 30 June 2027.
Is Dar Al Aiham One finished?
No. It was 20.78% complete at the DLD inspection of 3 August 2026.
When did construction of Dar Al Aiham One start?
The DLD register records a construction start on 30 December 2025, with a 0% inspection on 8 January 2026.