Handover date

When is the Diamondz by Danube handover date?

Updated 1 October 2026 Diamondz by Danube

Short answer

The Diamondz by Danube handover date is November 2027, the date on Danube's own project page since the May 2024 launch; the Dubai Land Department (DLD) register has no completion date filed for the tower. The DLD site inspection of 20 July 2026 put construction at 16.32% complete, while Danube's own update put it at 30% on 31 August 2026. The two progress figures differ widely, and the November 2027 date rests on Danube's word rather than a registered date.

Registered completion date (DLD)

Not filed

DLD register, project 3017, via Mitchells, accessed 1 Oct 2026

Latest construction progress

16.32%

DLD site inspection, 20 Jul 2026. Danube reported 30% on 31 Aug 2026

Developer's stated date

Nov 2027

Danube project page, accessed 1 Oct 2026

Date change since launch

None recorded

Propsearch, updated 17 Sep 2026

Diamondz by Danube handover date: the latest position

Diamondz by Danube is due for handover in November 2027. That is the date on Danube’s own project page, and Propsearch records the same date from the May 2024 launch to its latest update on 17 September 2026. The Dubai Land Department (DLD) register, project number 3017, holds no completion date for the tower, so November 2027 is Danube’s date rather than a registered one. More on prices and unit sizes is on the Diamondz by Danube page.

Progress figures differ by source. The DLD site inspection of 20 July 2026 recorded 16.32% complete, up from 11.51% on 1 April 2026. Danube’s own update of 31 August 2026 put the tower at 30%, with foundations finished, the Wing A podium 3 slab and Wing B podium 1 slab cast, and all major subcontractors appointed. To finish by November 2027 from the July inspection, the remaining 83.68% would need to be built in about 16 months. Between April and July 2026 the DLD figure rose by 4.81 points.

Diamondz by Danube handover date by building

Diamondz is one 65 storey tower with two wings on a shared podium, so one date covers every unit. The DLD register lists 1,225 units; Danube’s page gives 1,219 apartments plus shops.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Diamondz by Danube (Wings A and B) 16.32%, 20 Jul 2026 Not filed Danube: November 2027. Propsearch: November 2027 (17 Sep 2026). Bayut: Q4 2027

Danube’s 30% and the DLD’s 16.32% are six weeks apart, but the gap is larger than that time alone would explain. The DLD figure comes from its own inspector.

How the Diamondz by Danube handover date has changed

The published date has not moved since launch.

Date What happened Source
May 2024 Launched from AED 1.1 million, with handover in November 2027. Propsearch; Danube
1 Sep 2024 DLD registered construction start. DLD register, via Mitchells
1 Apr 2026 11.51% at the DLD site inspection. DLD register, via Continental Club
20 Jul 2026 16.32% at the DLD site inspection. No completion date filed. DLD register, via Mitchells
31 Aug 2026 Danube reports 30% complete. Danube construction page
Sep 2026 Propsearch and Danube still show November 2027. Continental Club lists Q4 2027 as the developer’s date. Propsearch, 17 Sep 2026; Continental Club, 29 Sep 2026

What the Diamondz by Danube handover date means for payments

Bayut’s building guide gives 10% at booking, 50% during construction across instalments 2 to 36, 10% on handover and 30% over the 30 months after handover at 1% a month. Propsearch describes the same plan as 10%, 60% and 30% after handover, folding the handover payment into construction. On the AED 1.1 million studio launch price, the handover payment under Bayut’s version is AED 110,000, followed by AED 11,000 a month for 30 months. Because 30% is tied to the months after handover, a later handover also pushes back the end of the payment schedule.

What to check before relying on the Diamondz by Danube date

  1. The completion date written into your SPA, since the DLD register has no completion date filed to fall back on.
  2. The DLD progress for project 3017, through DLD’s project status enquiry service, since it ran about 14 points below Danube’s own figure in mid-2026.
  3. Whether your schedule matches Bayut’s 10% handover payment or Propsearch’s version, since Danube’s own page describes only a 0.5% monthly plan.
  4. Which wing your unit is in. At the end of August 2026 Danube reported the podium 3 slab cast in Wing A against podium 1 in Wing B, though it gives one date for both.

Questions buyers also ask

What is the Diamondz by Danube completion date?

November 2027, per Danube's own project page and Propsearch (updated 17 Sep 2026). Continental Club lists the same Q4 2027 as a developer supplied date. The DLD register has no completion date filed for project 3017.

Is Diamondz by Danube finished?

No. The DLD site inspection of 20 July 2026 recorded 16.32% complete. Danube's own update of 31 August 2026 gave 30%, with foundations finished and podium slabs cast in both wings.

When will Diamondz by Danube be ready?

Danube says November 2027. Its 31 August 2026 construction page did not repeat the date, and the DLD has no registered date to compare against.

Has the Diamondz by Danube handover date been delayed?

No change has been published. Propsearch records November 2027 from the May 2024 launch through its 17 September 2026 update, and Danube's own page still shows November 2027.

How much is due at the Diamondz by Danube handover?

Bayut lists 10% on handover, with a further 30% paid over 30 months after handover at 1% a month. Propsearch describes the plan as 10% at booking, 60% during construction and 30% after handover.

Sources

  1. Danube Properties, Diamondz portfolio page (opens in a new tab)danubeproperties.com · accessed 1 Oct 2026
  2. Continental Club, Diamondz by Danube (DLD register) (opens in a new tab)continentalclub.ae · registry updated 29 Sep 2026
  3. Propsearch, Diamondz by Danube (opens in a new tab)propsearch.ae · updated 17 Sep 2026