When is the Cove Grand by Imtiaz handover date?
Short answer
Cove Grand by Imtiaz has a registered completion date of 15 December 2027 on the Dubai Land Department (DLD) register, and Imtiaz gives Q4 2027. The DLD inspection of 8 October 2026 recorded 13.40% progress, up from 8.67% on 8 July 2026, and Imtiaz's own tracker shows 13% with the super-structure not yet started. The date has not changed, but the tower needs about 6.1 points a month to meet it, against about 1.6 points a month between July and October 2026.
Registered completion date (DLD)
15 Dec 2027
DLD register via Continental Club, updated 11 Oct 2026
Latest construction progress
13.40%
DLD inspection, 8 Oct 2026
Developer's stated date
Q4 2027
Imtiaz project page, accessed 11 Oct 2026
Developer's own progress figure
13%
Imtiaz tracker, undated, accessed 11 Oct 2026
Cove Grand handover date: the latest position
Cove Grand by Imtiaz, DLD project 3774 in Dubailand Residence Complex, has a registered completion date of 15 December 2027. Imtiaz gives Q4 2027 and Property Finder lists 15 December 2027. Prices, sizes and the payment plans are on the Cove Grand by Imtiaz page.
The DLD inspection of 8 October 2026 recorded 13.40% progress, up from 8.67% on 8 July 2026 (DLD register via Continental Club, updated 11 October 2026). Imtiaz’s own tracker, undated, shows 13% overall, with the sub-structure at 75% and the super-structure at 0%. On the developer’s tracker, the tower had not yet started rising.
Cove Grand handover date by building
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Cove Grand by Imtiaz (538 units) | 13.40%, 8 Oct 2026 | 15 Dec 2027 | Q4 2027 (Imtiaz); 15 Dec 2027 (Property Finder) |
Cove Grand is one tower of basement, ground floor, three podium levels and 17 residential floors. The DLD register names the developer as Imtiaz Cove Real Estate Development. Cove Boulevard nearby is a separate DLD project with a later date of 30 October 2028.
How the Cove Grand handover date has changed
| Date | Event | Source |
|---|---|---|
| 30 May 2025 | Bookings open; construction registered as starting; completion set for 15 December 2027 | Property Finder; DLD register via Continental Club |
| 29 Apr 2026 | DLD inspection: about 6.26% | DLD register via Continental Club |
| 8 Jul 2026 | DLD inspection: 8.67% | DLD register via Continental Club |
| 8 Oct 2026 | DLD inspection: 13.40% | DLD register via Continental Club |
| Oct 2026 | Register still shows 15 December 2027; Imtiaz still gives Q4 2027 | Continental Club; Imtiaz |
The date has not moved since launch. The tower took about 11 months to reach 6.26%, then added 2.41 points in ten weeks to July and 4.73 points in the three months to 8 October 2026. Meeting 15 December 2027 needs about 87 points in just over 14 months from the October inspection, or about 6.1 points a month.
What the Cove Grand handover date means for payments
How much the date matters depends on the plan. On the 20/30/50 plan listed by Property Finder and Continental Club, half the price is due on handover, about AED 362,300 on a studio at the DLD median of AED 724,572. On Property Finder’s second option, 15% is due on handover and 30% after it. On Imtiaz’s 70/30 plan, 30% is paid quarterly over three years after handover, so a later completion also moves the end of the plan.
What to check before relying on the Cove Grand date
- The progress at the next DLD inspection, which will show whether the super-structure has started.
- The plan written into the SPA, as the handover share ranges from 15% to 50% across the three published options.
- The DLD project number on the SPA, 3774 for Cove Grand, as the Cove towers nearby carry different dates.
Questions buyers also ask
When will Cove Grand be completed?
The registered completion date is 15 December 2027 and Imtiaz gives Q4 2027. The tower was 13.40% complete on 8 October 2026 (DLD register via Continental Club).
Is Cove Grand by Imtiaz finished?
No. It was 13.40% complete at the DLD inspection of 8 October 2026. Imtiaz's tracker shows the sub-structure at 75% and the super-structure not yet started.
Has the Cove Grand handover date been delayed?
No. The registered date of 15 December 2027 has not changed since construction was registered in May 2025, and Imtiaz still gives Q4 2027.
How much is paid at Cove Grand handover?
It depends on the plan: 50% on the 20/30/50 plan, 15% plus 30% after handover on the 20/35/15/30 plan (Property Finder), or 50% on completion on Imtiaz's 50/50 plan.