
When is the Casa Vista Residence handover date?
Short answer
Casa Vista Residence by Golden Woods had a registered completion date of 30 June 2026 on the Dubai Land Department (DLD) register, and Golden Woods gave Q2 2026; both have passed. The latest DLD inspection, on 9 June 2026, recorded 90.05% progress, and on 8 October 2026 the register still listed the project as active. One portal describes it as handed over in Q3 2026, but the DLD register does not show a completion.
Registered completion date (DLD)
30 Jun 2026, passed
DLD register via Continental Club, 8 Oct 2026
Latest construction progress
90.05%
DLD inspection, 9 Jun 2026
Developer's stated date
Q2 2026
Golden Woods project page, accessed 11 Oct 2026
Days past the registered date
103
As of 11 Oct 2026
Casa Vista Residence handover date: the latest position
The Dubai Land Department (DLD) register gave Casa Vista Residence by Golden Woods, project number 2998 in Jumeirah Village Circle, a completion date of 30 June 2026. Golden Woods’ own page gives Q2 2026. Both have passed. More on prices and homes is on the Casa Vista Residence by Golden Woods page.
The latest DLD inspection, on 9 June 2026, recorded 90.05%. Daily snapshots of the register by Dubai Handover show the project still active, at 90%, with the 30 June 2026 date unchanged through 8 October 2026. ezre.ae lists the building as handed over in Q3 2026, a claim the register does not yet support.
Casa Vista Residence handover date by building
Casa Vista Residence is one building of 90 units.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Casa Vista Residence By Golden Woods (90 units) | 90.05%, 9 Jun 2026 | 30 Jun 2026, passed | Q2 2026 (Golden Woods); Q3 2026 (ezre.ae) |
Progress and dates are from the DLD register as republished by Continental Club, registry updated 8 October 2026.
How the Casa Vista Residence handover date has changed
| Date | Event | Source |
|---|---|---|
| 1 Mar 2024 | Construction registered as starting; completion date 30 June 2026. | DLD register, via Continental Club |
| 11 Mar 2024 | DLD inspection: 0%. | DLD register, via Continental Club |
| 3 Jun 2024 | Project registered with DLD. | Dubai Handover |
| Q3 2024 | Golden Woods launches sales, with completion given as Q2 2026. | Golden Woods |
| 28 Apr 2025 | DLD inspection: 48.31%. | DLD register, via Continental Club |
| 27 Oct 2025 | DLD inspection: 78.08%. | DLD register, via Continental Club |
| 9 Jun 2026 | DLD inspection: 90.05%. | DLD register, via Continental Club |
| 30 Jun 2026 | Registered completion date passes. | DLD register |
| 8 Oct 2026 | Register still active, 90%, date unchanged. | Dubai Handover |
Portals have shown other dates along the way: Prop971 still lists Q4 2025, and Takween Aldar shows 30 September 2026. The building slowed as it neared the end, adding 11.97 points in the seven months to June 2026 after 29.77 points in the six months before. Continental Club’s estimate puts 100% around 13 December 2026.
What the Casa Vista Residence handover date means for payments
Golden Woods sells the building on post-handover plans. On the 40/10/50 plan listed by ezre.ae, 10% is due on handover and 50% follows over 36 months in quarterly payments. On Takween Aldar’s 10/10/80 plan, 80% is paid over 36 months after handover. On these plans, the later the completion, the later the post-handover schedule begins. A 10% handover payment on a 1 bedroom at the registered sales median of AED 1,044,624 (Continental Club) is about AED 104,500.
What to check before relying on the Casa Vista Residence date
- The grace period in the SPA, since the registered date passed on 30 June 2026.
- A completion certificate and a DLD status change before treating any “handed over” listing as final.
- The start date of the post-handover instalments written into the SPA for the specific plan.
Questions buyers also ask
Is Casa Vista Residence finished?
Not on the DLD register. It was 90.05% complete at the 9 June 2026 inspection and still listed as active on 8 October 2026. ezre.ae describes it as handed over in Q3 2026, which the register does not yet reflect.
What is the Casa Vista Residence completion date?
The registered completion date was 30 June 2026 and has passed. Continental Club's trend estimate from past inspections puts 100% around 13 December 2026, which is not a developer date.
Has the Casa Vista Residence handover been delayed?
Yes, against its registered date. The building was 90.05% built three weeks before 30 June 2026, and by 11 October 2026 it was 103 days past that date without a recorded completion.
When do post-handover payments start at Casa Vista Residence?
On the plans listed by ezre.ae and Takween Aldar, the 36 or 60 month post-handover instalments begin after handover, so a later completion moves the whole schedule later.
