When is the Bliss Tower handover date?
Short answer
Bliss Tower's registered completion date is 15 December 2026, and Property Finder and the developer give the same date and quarter. The Dubai Land Department (DLD) inspection of 17 September 2026 recorded the tower 92.52% complete. Handover follows the building completion certificate, so keys can come some weeks after construction reaches 100%.
Registered completion date (DLD)
15 Dec 2026
DLD project 3545, via Mitchell's and Continental Club
Latest construction progress (DLD)
92.52%
DLD inspection, 17 Sep 2026
Developer's stated date
Q4 2026
Pure Bliss Development, via Continental Club
Progress four months earlier
About 64.8%
DLD inspection, 19 May 2026, via Continental Club
Bliss Tower handover date: the latest position
Bliss Tower is registered for completion on 15 December 2026 at the Dubai Land Department (DLD), and Property Finder lists the same date. Pure Bliss Development markets Q4 2026. In the register the project appears as Bliss Tower, project 3545, in Wadi Al Safa 5, part of Dubailand Residence Complex. Prices, sizes and the plan: Bliss Tower.
The DLD inspection of 17 September 2026 recorded 92.52% progress. The structure topped out in December 2025, so the remaining work is mainly interior and building systems. The tower was over 90% sold by then (Khaleej Times, 25 December 2025), so most of its 131 owners are waiting on the same handover notice.
Bliss Tower handover date by building
Bliss Tower is a single building of ground, two podium levels, 12 floors and a roof.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Bliss Tower (131 homes) | 92.52%, 17 Sep 2026 | 15 Dec 2026 | Q4 2026 (developer); 15 Dec 2026 (Property Finder) |
How the Bliss Tower handover date has changed
| Date | What was recorded | Source |
|---|---|---|
| 15 Aug 2024 | Sales open and registered start; expected completion 15 Dec 2026 | Property Finder; DLD register |
| 12 Nov 2025 | First registered off-plan sale in the Mitchell’s dataset | DLD sales register, via Mitchell’s |
| 25 Dec 2025 | Topping out announced, over 90% of units sold | Khaleej Times |
| 19 May 2026 | About 64.8% complete | DLD inspection, via Continental Club |
| 17 Sep 2026 | 92.52% complete | DLD inspection, via Continental Club |
| 4 Oct 2026 | Registered completion still 15 Dec 2026 | DLD register, via Continental Club |
The date has not changed since launch. The pace between the last two inspections, about seven points a month, is in line with what is needed to reach 100% before 15 December 2026.
What the Bliss Tower handover date means for payments
Bliss Tower was sold on 20% at booking and 80% on handover, with nothing due during construction (Property Finder). That puts most of the price at the end. On the 1 bedroom median of about AED 1.02 million (Continental Club, sales since 2025), the handover payment is about AED 816,000. On a 2 bedroom at the median of about AED 1.41 million, it is about AED 1.13 million. Buyers using a mortgage need the bank’s valuation and offer ready when the developer issues the handover notice, which follows the building completion certificate.
What to check before relying on the Bliss Tower date
- The handover notice date in writing. The 80% payment is due against that notice, not against the DLD percentage.
- The building completion certificate. A tower at 92.52% can still wait weeks for authority approvals and utility connections.
- The SPA grace period, in case the December date slips into early 2027.
- The snagging window the developer allows after handover for a tower finished in about 28 months.
Questions buyers also ask
Is Bliss Tower finished?
Not yet. The DLD inspection of 17 September 2026 recorded 92.52% progress. The structure topped out in December 2025 and interior works were under way (Khaleej Times, 25 Dec 2025).
What is the Bliss Tower completion date?
15 December 2026 on the DLD register, the same date Property Finder lists as expected completion. The developer markets Q4 2026.
Has the Bliss Tower handover date been delayed?
No. The date at launch in August 2024 was December 2026, and the register still showed 15 December 2026 as at October 2026 (Property Finder; Continental Club).
How much is paid at the Bliss Tower handover?
80% of the price under the 20/80 plan, with 20% paid at booking and nothing during construction (Property Finder).