When is the Binghatti Wraith handover date?
Short answer
The Binghatti Wraith handover date is 30 December 2027, the registered completion date on the DLD register, and launch listings give the same Q4 2027. The only published DLD inspection, on 20 May 2026, recorded 0%, ahead of the registered construction start of 1 July 2026. That leaves 18 months of construction for a 19 storey tower, and no progress figure since the start had been published by 11 October 2026.
Registered completion date (DLD)
30 Dec 2027
DLD project 4482, via Continental Club and Dubai Handover
Latest construction progress
0%
DLD inspection, 20 May 2026
Date at launch
Q4 2027
Alnair, 9 Jun 2026; Binayah
Date change since launch
None published
DLD register, accessed 11 Oct 2026
Binghatti Wraith handover date: the latest position
Binghatti Wraith is due for completion on 30 December 2027. That is the registered completion date the Dubai Land Department holds for project 4482, and listings at the June 2026 launch gave the same Q4 2027. More on prices and sizes is on the Binghatti Wraith page.
The register sets construction to start on 1 July 2026. The only published inspection, on 20 May 2026, recorded 0%, and no inspection after the start date had been published by 11 October 2026. The date has not changed since launch, but there is no progress figure yet to test it against.
Binghatti Wraith handover date by building
Wraith is one 19 storey tower, so one date applies to all 881 registered units.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Binghatti Wraith (847 apartments, 34 shops) | 0%, 20 May 2026 | 30 Dec 2027 | Q4 2027 (Alnair; Binayah); December 2027 (Property Finder) |
The DLD register lists 196 studios, 563 one bedroom, 86 two bedroom and 2 three bedroom apartments, plus 34 shops (Dubai Handover). Binghatti describes a ground floor, four podium levels, 14 residential floors and a roof, so the residential floors cannot start until the podium is built. Propsearch gives a slightly higher total of 889 units. Buyer payments are held in an escrow account at United Arab Bank (DLD register).
How the Binghatti Wraith handover date has changed
| Date | What happened | Source |
|---|---|---|
| 20 May 2026 | First DLD inspection records 0%. Registered completion 30 December 2027. | DLD register, via Continental Club |
| 1 Jun 2026 | Booking opens. Expected completion December 2027. | Property Finder |
| 8 Jun 2026 | Launch event at the Grand Hyatt Dubai. | 707 Real Estate |
| 9 Jun 2026 | Launch coverage gives Q4 2027 handover. | Alnair |
| 1 Jul 2026 | Registered construction start. | DLD register |
| 3 Sep 2026 | Propsearch still lists the project as planned. | Propsearch |
| 11 Oct 2026 | Registered date unchanged; no newer inspection published. | Continental Club; Dubai Handover |
What the Binghatti Wraith handover date means for payments
Wraith is sold on a 50/50 plan, so half the price falls due at handover. On a studio at AED 799,999 that is about AED 400,000; on a 1 bedroom at the AED 1,275,000 DLD median, about AED 637,500 (Continental Club, DLD data to 3 October 2026). A later handover would push this payment back, while the construction half is paid during the build.
What to check before relying on the Binghatti Wraith date
- The completion date and grace period in the SPA, given that 50% of the price depends on it.
- The first DLD inspection after the 1 July 2026 start, through the DLD project status enquiry service for project 4482.
- How the construction half is scheduled in the SPA, since sources split it as 10/40 or 20/30.
Questions buyers also ask
What is the Binghatti Wraith completion date?
30 December 2027 on the DLD register for project 4482, matching the Q4 2027 given at the June 2026 launch.
Has construction started at Binghatti Wraith?
The DLD register gives a construction start of 1 July 2026. The only published inspection, on 20 May 2026, recorded 0%, and no later figure was public by 11 October 2026.
Has the Binghatti Wraith handover date been delayed?
No. The registered date is still 30 December 2027 and no change had been announced by 11 October 2026.
How much is due at the Binghatti Wraith handover?
50% of the price under the 50/50 plan. On a studio at the AED 799,999 launch price, that is about AED 400,000.