Handover date

When is the Binghatti Twilight handover date?

Updated 11 October 2026 Binghatti Twilight

Short answer

Binghatti Twilight's registered completion date is 30 April 2026, and Binghatti still gives Q1 2026, but the tower has not been handed over. The latest DLD inspection, on 14 September 2026, recorded it 55.41% complete. Binghatti has not published a revised date, so the date in each buyer's SPA and the next DLD inspection are the figures to follow.

Registered completion date (DLD)

30 Apr 2026

DLD project register via Continental Club

Latest construction progress

55.41%

DLD inspection, 14 Sep 2026

Developer's stated date

Q1 2026

Binghatti project page, accessed 11 Oct 2026

Portal estimate

March 2026

Propsearch, updated 7 May 2026, not revised

Binghatti Twilight handover date: the latest position

Binghatti Twilight has a registered completion date of 30 April 2026 in the DLD project register. Binghatti’s own page gives Q1 2026. Both dates have passed and the tower is not finished. Prices, sizes and the payment plan are on the Binghatti Twilight page.

The latest DLD inspection, on 14 September 2026, recorded the building at 55.41% complete. Binghatti has not announced a revised completion date, and Propsearch’s estimate of March 2026 had not been updated since 7 May 2026.

The tower is one of several Binghatti projects with a Q1 2026 date that has passed, alongside Binghatti Ruby in JVC. Twilight is further ahead than Ruby, at 55.41% against 46.43%, but it started later, in April 2025, and has fewer units, 277 against 628. The status of every Binghatti project is on the Binghatti handover dates page.

Binghatti Twilight handover date by building

Binghatti Twilight is one tower, registered as a single DLD project (project number 3397) with 277 units.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Binghatti Twilight 55.41%, 14 Sep 2026 30 Apr 2026 Q1 2026 (Binghatti); Q2 2026 (developer figure via Continental Club); March 2026 (Propsearch, 7 May 2026)

How the Binghatti Twilight handover date has changed

Date What happened Source
Sep 2024 Binghatti reported to be preparing its Al Jaddaf launch Dubai Housing, 10 Sep 2024
1 Apr 2025 Construction start recorded DLD register
30 Apr 2026 Registered completion date; inspection records 32.01% DLD register
7 May 2026 Propsearch still shows a March 2026 estimate Propsearch
14 Sep 2026 Inspection records 55.41% complete DLD register
11 Oct 2026 Binghatti’s page still says Q1 2026 Binghatti

The published dates have not changed since launch, but the building has fallen behind them. A tower that started work in April 2025 was given about a year to complete; by September 2026 it had been under construction for about 17 months and was just over half built.

What the Binghatti Twilight handover date means for payments

Binghatti’s plan is 20% on signing, 50% during construction and 30% upon completion. The final 30% depends on completion, so it moves with the real handover, not the Q1 2026 date. On a 1 bedroom at the median DLD price of AED 1,355,000, that final payment would be about AED 406,500. No post-handover plan is listed.

What to check before relying on the Binghatti Twilight date

  1. The SPA completion date and grace period for the unit, which the contract enforces regardless of the marketing date.
  2. Residential or office unit. Offices and the two shops are part of the same DLD project, so they follow the same completion date as the homes.
  3. The next DLD inspection result on the DLD project status service, as the 14 September 2026 figure is the latest published.
  4. Any change to the Binghatti project page, which still showed Q1 2026 on 11 October 2026.

Questions buyers also ask

Is Binghatti Twilight finished?

No. The DLD register recorded the tower 55.41% complete at its inspection on 14 September 2026.

What is the Binghatti Twilight completion date?

The DLD project register holds a completion date of 30 April 2026. Binghatti's project page says Q1 2026 and Continental Club records the developer's planned handover as Q2 2026. All have passed, and no revised date has been published.

Has the Binghatti Twilight handover date been delayed?

In practice, yes. The building was 32.01% complete on its registered completion date of 30 April 2026 and 55.41% complete on 14 September 2026 (DLD project register via Continental Club).

When will Binghatti Twilight be ready?

No firm date is published. Progress rose by 23.4 points between 30 April and 14 September 2026. Binghatti has not said when the remaining work will be finished.