
When is the Binghatti Etherea handover date?
Short answer
The Dubai Land Department (DLD) register holds a completion date of 31 December 2027 for Binghatti Etherea in JVC, while Binghatti's project page says July 2027. The DLD inspection of 15 September 2026 recorded 7.24% construction progress. Reaching July 2027 would mean building more than 90% of the tower in about ten months.
Registered completion date (DLD)
31 Dec 2027
DLD register via Mitchell's, 4 Oct 2026
Latest construction progress
7.24%
DLD inspection, 15 Sep 2026
Developer's stated date
July 2027
Binghatti project page, accessed 11 Oct 2026
Portal estimates
Q3 to Q4 2027
Continental Club, Binayah, Impala, accessed Oct 2026
Binghatti Etherea handover date: the latest position
The Dubai Land Department (DLD) project register holds 31 December 2027 as the completion date for Binghatti Etherea (project number 4303). The DLD inspection of 15 September 2026 recorded 7.24% construction progress. Prices, sizes and the payment plan are on the Binghatti Etherea page.
Binghatti’s project page says July 2027, five months before the registered date. Broker pages are split between Q3 2027 and Q4 2027. Realty Hunting describes the launch as Q1 2026, although the first DLD-registered sale was on 5 November 2025 (Mitchell’s). The registered date is the later of the published dates and the one most consistent with progress so far.
Binghatti Etherea handover date by building
Binghatti Etherea is a single tower of 287 registered units.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Binghatti Etherea | 7.24%, 15 Sep 2026 | 31 Dec 2027 | July 2027 (Binghatti); Q3 2027 (Continental Club, Binayah); Q4 2027 (Impala) |
How the Binghatti Etherea handover date has changed
| Date | Event | Source |
|---|---|---|
| 5 Nov 2025 | First DLD-registered sale | Mitchell’s |
| 17 Dec 2025 | First DLD inspection | Continental Club |
| 1 Jan 2026 | Registered construction start | DLD register via Mitchell’s |
| 15 Sep 2026 | DLD inspection, 7.24% complete | Continental Club |
| Oct 2026 | Binghatti still says July 2027; register holds 31 Dec 2027 | Binghatti; Mitchell’s |
Neither date has moved since sales began. The registered date allows two years from the construction start, while Binghatti’s target allows about 18 months.
From the registered start on 1 January 2026 to the September 2026 inspection, progress averaged under 1 percentage point a month. Finishing by 31 December 2027 would need about 6 points a month for the remaining 15 months. Finishing by the end of July 2027 would need close to 9 points a month. The five month gap between the two dates depends on how fast the next year of work goes.
What the Binghatti Etherea handover date means for payments
The plan is 20% on booking, 50% during construction and 30% on completion. The completion payment is AED 229,500 on the AED 764,999 studio and about AED 360,000 on a 1 bedroom at the AED 1,199,999 list price. Nothing is due after handover. If the tower completes on the registered date rather than in July 2027, the 30% falls due about five months later.
What to check before relying on the Binghatti Etherea date
- Which date the SPA states, July 2027 or 31 December 2027, and the grace period after it.
- How the 50% construction share is scheduled, since progress of 7.24% in September 2026 sets how many milestones have been reached.
- Binghatti’s current delivery pace. It delivered about 1,700 units in the first half of 2026 but cut its expected 2026 handovers from 16 projects to 13 (Binghatti, 27 July 2026).
- The next DLD inspection for project 4303 on the Dubai REST app.
Questions buyers also ask
When will Binghatti Etherea be completed?
The DLD registered completion date is 31 December 2027. Binghatti gives July 2027. The DLD inspection of 15 September 2026 recorded 7.24% progress.
Is Binghatti Etherea on track for July 2027?
It would need a fast build. The tower was 7.24% complete in mid September 2026, about nine months after the registered construction start of 1 January 2026, and July 2027 is about ten months later.
Has the Binghatti Etherea handover date been delayed?
No delay has been announced. Binghatti's page still says July 2027, and the registered date of 31 December 2027 has not changed.
How long does Binghatti usually take to build in JVC?
It varies. Binghatti delivered six JVC projects in December 2024 (Khaleej Times), but Binghatti Amberhall in JVC was 38.03% complete in April 2026, after its registered completion date of 28 February 2026.


