When is the Binghatti Circle handover date?
Short answer
The Binghatti Circle handover date is 31 May 2027, the registered completion date on the DLD register, and Binghatti gives the same Q2 2027. The last published DLD inspection, on 30 April 2026, recorded 10.33% complete, ten months after construction started. The date has not changed since launch, but almost 90% of the work remained with 13 months to go at that inspection.
Registered completion date (DLD)
31 May 2027
DLD project 3819, via Continental Club
Latest construction progress
10.33%
DLD inspection, 30 Apr 2026
Developer's stated date
Q2 2027
Binghatti, accessed 11 Oct 2026
Date change since launch
None published
Property Finder, DLD register, accessed 11 Oct 2026
Binghatti Circle handover date: the latest position
Binghatti Circle is due for completion on 31 May 2027. That is the registered completion date the Dubai Land Department holds for project 3819, and Binghatti and Property Finder give the same Q2 2027. More on prices and sizes is on the Binghatti Circle page.
The last published DLD inspection, on 30 April 2026, recorded 10.33% complete. Construction was registered as starting on 1 June 2025, so that figure took ten months. With 13 months left to the registered date, almost 90% of the build remained. No newer inspection had been published by 11 October 2026, and Binghatti has not changed the date.
Binghatti Circle handover date by building
Circle is a single tower in JVC District 13, so one date covers its 776 apartments, 31 offices and 15 shops.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Binghatti Circle (822 units) | 10.33%, 30 Apr 2026 | 31 May 2027 | Q2 2027 (Binghatti); 31 May 2027 (Property Finder) |
Binghatti describes two basements, four parking levels, 58 residential floors, three mechanical floors and a roof, which Propsearch counts as 69 storeys. Most of the homes are studios (250) and 1 bedrooms (504), per the DLD register via Continental Club. Buyer payments are held in an escrow account at Dubai Islamic Bank.
How the Binghatti Circle handover date has changed
| Date | What happened | Source |
|---|---|---|
| 1 Jun 2025 | Booking opened and the DLD registered construction start. Expected completion 31 May 2027. | Property Finder; DLD register |
| 20 Jun 2025 | Launch coverage of the tower. | Prelaunch.ae |
| 23 Jun 2025 | First DLD inspection on record. | DLD register, via Continental Club |
| 22 Jul 2025 | Project registered with the DLD. | Dubricks |
| 30 Apr 2026 | DLD inspection records 10.33% complete. | DLD register, via Continental Club |
| 11 Oct 2026 | Binghatti still gives Q2 2027; registered date unchanged; no newer inspection published. | Binghatti; Continental Club |
What the Binghatti Circle handover date means for payments
Two plans were sold. On the 20/50/30 plan on Binghatti’s page, 30% is due on completion. On the 10/40/50 option listed by Property Finder, 50% is due on handover. On a studio at the AED 675,000 launch price, that is AED 202,500 or AED 337,500. On a 1 bedroom at the AED 1,184,167 DLD median, it is about AED 355,250 or AED 592,080 (Continental Club). If completion moves past May 2027, the final payment moves with it.
What to check before relying on the Binghatti Circle date
- The completion date and grace period in the SPA, given the pace recorded up to April 2026.
- The next DLD inspection for project 3819, through the DLD project status enquiry service.
- Which payment plan the SPA uses, because it decides whether 30% or 50% waits for handover.
Questions buyers also ask
What is the Binghatti Circle completion date?
31 May 2027 on the DLD register for project 3819. Binghatti gives Q2 2027 and Property Finder 31 May 2027.
Is Binghatti Circle finished?
No. The last published DLD inspection, on 30 April 2026, recorded 10.33% complete.
Has the Binghatti Circle handover date been delayed?
Not officially. The registered date and Binghatti's Q2 2027 have not changed since the June 2025 launch. At the April 2026 inspection, 10.33% of the work had been done in ten months, with 13 months left.
How much is due at the Binghatti Circle handover?
30% on the 20/50/30 plan or 50% on the 10/40/50 plan. On a studio at the AED 675,000 launch price, that is AED 202,500 or AED 337,500.