Illustration: construction cranes on a residential tower at dusk
Handover date

When is the Binghatti Aquarise handover date?

Updated 11 October 2026 Binghatti Aquarise

Short answer

Binghatti gives Q1 2027 as the completion date for Binghatti Aquarise, while the DLD register holds a registered completion date of 31 October 2026. The last DLD inspection, on 14 May 2026, recorded the project 21.04% complete. That leaves the October 2026 date out of reach, and Data Habibi already lists a later target of Q2 2027.

Registered completion date (DLD)

31 Oct 2026

DLD register, project 3585

Latest construction progress

21.04%

DLD inspection, 14 May 2026

Developer's stated date

Q1 2027

Binghatti, accessed 11 Oct 2026

Portal estimate

Q2 2027

Data Habibi, three months after the original Q1 2027

Binghatti Aquarise handover date: the latest position

Binghatti says Binghatti Aquarise is expected to be completed in Q1 2027. The DLD register holds an earlier registered completion date of 31 October 2026 for the Business Bay project, covered in full on the Binghatti Aquarise page.

The last DLD inspection, on 14 May 2026, recorded 21.04% complete. Daily snapshots of the register from August to 10 October 2026 show no newer inspection and no change to the October date (Dubai Handover). With about four fifths of the work outstanding in May, neither the October 2026 date nor, on the progress published so far, an early 2027 finish is assured.

Binghatti Aquarise handover date by building

The DLD register files Aquarise as one project with five buildings and 1,592 units. It gives one date and one progress figure for all of them.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Binghatti Aquarise, all buildings (DLD project 3585) 21.04%, 14 May 2026 31 Oct 2026 Q1 2027 (Binghatti); Q2 2027 (Data Habibi)
Tower A, Tower B, Tower C (names on DLD sales records) Not reported separately Not reported separately Not published separately

How the Binghatti Aquarise handover date has changed

Date What was published Source
6 Mar 2025 First DLD inspection, 0% DLD register via Continental Club
15 Mar 2025 Registered construction start DLD register
16 Apr 2025 Project registered with DLD, completion date 31 Oct 2026 Dubai Handover
17 Apr 2025 Sales open by expression of interest Real Estate Club Dubai
At launch Original developer delivery promise Q1 2027 Data Habibi
14 May 2026 21.04% complete at DLD inspection DLD register via Continental Club
Oct 2026 Binghatti still gives Q1 2027; Data Habibi lists Q2 2027 Binghatti; Data Habibi

The DLD date has stayed at 31 October 2026 since registration. Binghatti’s own date has stayed at Q1 2027, while Data Habibi has moved its target by one quarter.

What the Binghatti Aquarise handover date means for payments

Binghatti’s plan is 20% on booking, 50% during construction and 30% on completion. The 30% balance is the payment tied to the handover date. On a 1 bedroom at AED 2,000,000, that is AED 600,000. If completion moves from Q1 to Q2 2027 or later, that payment moves with it, and so does the start of any rental income.

What to check before relying on the Binghatti Aquarise date

  1. The completion date in the SPA, since three dates are in circulation: 31 October 2026, Q1 2027 and Q2 2027.
  2. The next DLD inspection for project 3585. Progress has not been updated since 14 May 2026.
  3. Whether the SPA ties instalments to construction milestones or calendar dates, which decides how the 50% construction share falls.
  4. The tower letter on the contract, in case Binghatti hands over the five buildings at different times.

Questions buyers also ask

Is Binghatti Aquarise finished?

No. It was 21.04% complete at the DLD inspection on 14 May 2026, and the register lists it as under construction (Mitchells, 4 October 2026).

What is the Binghatti Aquarise completion date?

The registered completion date on the DLD register is 31 October 2026. Binghatti's own completion date is Q1 2027.

Has the Binghatti Aquarise handover date been delayed?

Binghatti still gives Q1 2027. Data Habibi lists Q2 2027 as the current target, a three month postponement against the original promise. The registered date of 31 October 2026 will pass before the project is finished.

Do all Binghatti Aquarise towers hand over together?

Binghatti has published one date. The DLD register lists five buildings under one project number, and sales records name Tower A, B and C, but no separate dates have been published for them.

Sources

  1. Data Habibi, Binghatti Aquarise (opens in a new tab)datahabibi.ae · accessed 11 Oct 2026
Request a Unit Review