Handover date

When is the Beach Walk by Imtiaz handover date?

Updated 11 October 2026 Beach Walk by Imtiaz

Short answer

Beach Walk by Imtiaz has no single handover date. The first building was handed over in March 2026 and Beach Walk 2 was recorded 100% complete in August 2026. Beach Walk 3 passed its registered completion date of 14 June 2026 while 82.01% built (DLD inspection, 20 July 2026), and Beach Walk 4 is registered for 20 April 2027, at 42.87% on 13 August 2026. The building the unit sits in decides which date applies.

Beach Walk 4 registered completion date (DLD)

20 Apr 2027

DLD register via Continental Club, updated 6 Oct 2026

Beach Walk 4 construction progress

42.87%

DLD inspection, 13 Aug 2026

Beach Walk 3 progress, past its 14 Jun 2026 date

82.01%

DLD inspection, 20 Jul 2026

First building handed over

Mar 2026

Gulf News, 10 Mar 2026; groundbreaking target was Q4 2025

Beach Walk by Imtiaz handover date: the latest position

Beach Walk by Imtiaz is a series of buildings on Dubai Islands, each a separate DLD project with its own date. Two are complete. Imtiaz handed over the first in March 2026, the first residential handover on the islands (Gulf News, 10 March 2026), and the DLD register recorded Beach Walk 2 at 100% with a status date of 6 August 2026. Prices, sizes and the payment plan are on the Beach Walk by Imtiaz page.

Two are still being built. Beach Walk 3 passed its registered completion date of 14 June 2026 and was 82.01% complete on 20 July 2026. Beach Walk 4 is registered for 20 April 2027 and was 42.87% complete on 13 August 2026 (DLD register via Continental Club, updated 4 to 6 October 2026).

Beach Walk by Imtiaz handover date by building

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Beach Walk Residences 1 (DLD 3162, 164 units) 100%, finished 19 May 2026 (completion recorded) First series handover Mar 2026, building not named (Gulf News)
Beach Walk 2 (DLD 3224, 63 units) 100%, 6 Aug 2026 10 Aug 2026 Q2 2026 (developer-supplied)
Beach Walk 3 (DLD 3285, 82 units) 82.01%, 20 Jul 2026 14 Jun 2026, passed Q2 2026 (developer-supplied)
Beach Walk 4 (DLD 3707, 70 units) 42.87%, 13 Aug 2026 20 Apr 2027 Q2 2027 (Imtiaz); Apr 2027 (Property Finder)
Beach Walk Grand (DLD 3367, 112 units) 53.22%, 10 Aug 2026 25 Dec 2026 Q4 2026 (developer-supplied)

Sources: DLD register via Continental Club and, for Beach Walk Residences 1, Real Estate Club Dubai. Beach Walk Grand is registered to a separate Imtiaz company and sold as part of the same series. Gulf News described the first building handed over as 80 homes, fewer than the 164 units the register lists for Beach Walk Residences 1.

How the Beach Walk by Imtiaz handover date has changed

Date Event Source
Jun 2024 Beach Walk Residences 1 construction starts Real Estate Club Dubai
25 Jul 2024 Groundbreaking of Beach Walk Residence; completion target Q4 2025 Gulf News
Aug to Sep 2024 Beach Walk 2 and 3 start; registered for 10 August 2026 and 14 June 2026 DLD register via Continental Club
20 Apr 2025 Beach Walk 4 sales and construction start; registered for 20 April 2027 Property Finder; DLD register
9 to 10 Mar 2026 First building handed over GCC Business News; Gulf News
19 May 2026 Completion recorded for Beach Walk Residences 1 Real Estate Club Dubai
14 Jun 2026 Beach Walk 3 registered date passes DLD register via Continental Club
6 Aug 2026 Beach Walk 2 recorded at 100% DLD register via Continental Club
13 Aug 2026 Beach Walk 4 at 42.87% DLD register via Continental Club

The first building arrived about a quarter after the Q4 2025 target given at its groundbreaking. Beach Walk 3 is the one now running late: it needed about 18 more points after 20 July 2026, at a recent pace of about 5 points a month. Beach Walk 4 needs about 57 points in eight months to meet 20 April 2027, or about 7 points a month, against about 3.6 points a month between June and August 2026. Imtiaz’s own June 2027 date for Beach Walk 4 gives it two more months.

What the Beach Walk by Imtiaz handover date means for payments

All buildings sold on 20% down payment, 40% during construction and 40% on handover. For Beach Walk 3 and Beach Walk 4 buyers, the 40% falls on the handover notice, so a later finish moves the largest payment later. On a Beach Walk 4 1 bedroom at the launch price of AED 1,942,000, that is about AED 776,800.

What to check before relying on the Beach Walk by Imtiaz date

  1. The DLD project number on the SPA, since Beach Walk 1 to 4 and Beach Walk Grand each have a different date and status.
  2. For Beach Walk 3, a written revised date from Imtiaz, as the registered date passed in June 2026 with no new date published.
  3. For Beach Walk 4, which date the SPA uses, 20 April 2027 on the register or June 2027 in Imtiaz’s FAQ.

Questions buyers also ask

Is Beach Walk by Imtiaz finished?

Partly. The first building was handed over in March 2026 and Beach Walk 2 was recorded 100% complete in August 2026. Beach Walk 3 was 82.01% built on 20 July 2026 and Beach Walk 4 was 42.87% built on 13 August 2026.

When will Beach Walk 4 be completed?

The DLD registered completion date is 20 April 2027. Imtiaz gives Q2 2027 and says June 2027 in its FAQ. Property Finder lists April 2027.

Has the Beach Walk 3 handover date been delayed?

Yes, against the register. Its registered completion date of 14 June 2026 passed with the building at 82.01% on 20 July 2026 (DLD register via Continental Club). No revised date had been published by 11 October 2026.

When was Beach Walk 1 handed over?

Imtiaz handed over the first Beach Walk building in March 2026, the first residential handover on Dubai Islands (Gulf News, 10 Mar 2026). The report did not number the building. The DLD register records Beach Walk Residences 1 as finished, with completion recorded on 19 May 2026 (Real Estate Club Dubai).

Sources

  1. Continental Club, Beach Walk 2 (DLD registry) (opens in a new tab)continentalclub.ae · registry updated 4 Oct 2026
  2. Continental Club, Beach Walk 3 (DLD registry) (opens in a new tab)continentalclub.ae · registry updated 4 Oct 2026
  3. Continental Club, Beach Walk 4 (DLD registry) (opens in a new tab)continentalclub.ae · registry updated 6 Oct 2026
  4. Continental Club, Beach Walk Grand (DLD registry) (opens in a new tab)continentalclub.ae · registry updated 5 Oct 2026