When is the Baystar by Vida handover date?
Short answer
Baystar by Vida has a registered completion date of 31 December 2029 on the Dubai Land Department (DLD) register, and Emaar gives Q4 2029. The DLD inspection of 16 June 2026 recorded 6.30% progress, six months after construction started. The date has not changed since launch, though sources disagree on how many buildings the project has.
Registered completion date (DLD)
31 Dec 2029
DLD register via Continental Club, updated 4 Oct 2026
Latest construction progress
6.30%
DLD inspection, 16 Jun 2026
Developer's stated date
Q4 2029
Developer-supplied, Continental Club
Portal date
31 Dec 2029
Property Finder, accessed 11 Oct 2026
Baystar by Vida handover date: the latest position
Baystar by Vida, DLD project 4002 at Rashid Yachts and Marina, has a registered completion date of 31 December 2029. Emaar’s developer-supplied date is Q4 2029, and Property Finder lists 31 December 2029. Prices, sizes and the payment plan are on the Baystar by Vida page.
The DLD inspection of 16 June 2026 recorded 6.30% progress (Continental Club, registry updated 4 October 2026). It is the latest inspection on record, almost four months old by October 2026. Dates for the other towers in the community are on the Rashid Yachts and Marina page.
Baystar by Vida handover date by building
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Baystar by Vida (328 units, one DLD project) | 6.30%, 16 Jun 2026 | 31 Dec 2029 | Q4 2029 (Emaar); 31 Dec 2029 (Property Finder) |
The DLD register carries one project record and one date for all 328 units. Continental Club’s status panel shows three buildings while its text describes two residential towers, Engel and Volkers refers to twin towers, and Property Finder lists one building of 105 units. A single registered date applies whichever count is right.
How the Baystar by Vida handover date has changed
| Date | Event | Source |
|---|---|---|
| 24 Dec 2025 | Bookings open; construction registered as starting; completion set for 31 December 2029 | Property Finder; DLD register via Continental Club |
| 19 Feb 2026 | First DLD inspection after start | DLD register via Continental Club |
| 16 Jun 2026 | DLD inspection: 6.30%, up 5.88 points since February | DLD register via Continental Club |
| 4 Oct 2026 | Register still shows 31 December 2029 | Continental Club |
The date has not moved. Progress between February and June 2026 averaged about 1.5 points a month. The project needs about 2.2 points a month from June 2026 to finish by 31 December 2029, so the gap between the recorded and the needed pace is under one point a month.
What the Baystar by Vida handover date means for payments
Both published plans put 20% on handover. On Emaar’s 10/70/20 plan, the 70% construction share is paid in seven instalments, so 80% of the price is paid before completion. On a 1 bedroom at the DLD median of AED 2,185,888, the handover payment is about AED 437,200, and the construction instalments total about AED 1.53 million.
What to check before relying on the Baystar by Vida date
- Whether the seven construction instalments follow dates or progress. At 6.30% built in June 2026, a date-based schedule can collect much of the 70% well before the structure is finished.
- Which building the unit is in, given the one, two or three building descriptions, and whether the SPA gives that building a separate date.
- The grace period in the SPA beyond 31 December 2029.
Questions buyers also ask
When will Baystar by Vida be completed?
The registered completion date is 31 December 2029 and Emaar gives Q4 2029. The project was 6.30% complete on 16 June 2026 (DLD register via Continental Club).
Is Baystar by Vida finished?
No. Construction started on 24 December 2025 and was 6.30% complete at the DLD inspection of 16 June 2026.
Has the Baystar by Vida handover date been delayed?
No. The date set at launch in December 2025, 31 December 2029, is unchanged on the DLD register and on Property Finder.
How much is paid at Baystar by Vida handover?
20% of the price on both published plans: 10% down and 70% during construction, or 20% down and 60% during construction (Property Finder).