Handover date

When is the Bay Grove Residences handover date?

Updated 1 October 2026 Bay Grove Residences

Short answer

Nakheel said on 17 September 2026 that main works on Bay Grove Residences phases 1 and 3 are due to finish in late 2028, while the DLD register gives registered completion dates of 15 March 2028 for phase 1 and 21 September 2028 for phase 3. The DLD inspection on 21 July 2026 recorded phase 1 at 6.6% and phase 3 at 5.72%. Phases 2 and 4, 617 of the 1,154 homes, had no main contractor as of September 2026, so their dates are less certain.

Registered completion date (DLD), phase 1

15 Mar 2028

DLD project 3293, via Continental Club. Phase 3: 21 Sep 2028

Latest construction progress, phase 1

6.6%

DLD inspection, 21 Jul 2026. Phase 3: 5.72%

Developer's stated date, phases 1 and 3

Late 2028

Main works completion. Nakheel, 17 Sep 2026

Portal estimates

Q1 2028 to Q1 2029

Property Finder, by phase; Propsearch Sep 2028

Bay Grove Residences handover date: the latest position

Nakheel said on 17 September 2026, when it awarded a contract worth more than AED 800 million to Metac General Contracting, that main construction works on phases 1 and 3 of Bay Grove Residences are due to finish in late 2028. Those two phases hold 537 homes in seven buildings. Prices, sizes and the payment plan are on the Bay Grove Residences page.

The Dubai Land Department register gives earlier dates: 15 March 2028 for phase 1 and 21 September 2028 for phase 3. The DLD inspection on 21 July 2026 recorded phase 1 at 6.6% and phase 3 at 5.72%. Phases 2 and 4, the other 617 homes, had no main contractor in September 2026.

Bay Grove Residences handover date by phase

The community will have 1,154 homes in 15 buildings once complete (Nakheel, 17 September 2026). The DLD register holds phases 1 and 3 as separate projects with their own progress figures. No DLD progress figure was found for phases 2 and 4.

Phase Construction progress (DLD, date) Registered completion date Developer or portal date
Phase 1, 4 buildings, 296 homes (DLD 3293) 6.6%, 21 Jul 2026 15 Mar 2028 Late 2028 main works (Nakheel); Q1 2028 (Property Finder); Sep 2028 (Propsearch)
Phase 2 Not published Not found Q4 2028 (broker listing, Aug 2026); no contractor yet
Phase 3, 3 buildings, 241 homes (DLD 3631, “Bay Grove Residences B”) 5.72%, 21 Jul 2026 21 Sep 2028 Late 2028 main works (Nakheel); Mar 2029 (Property Finder)
Phase 4, 257 homes Not published Not found 15 Sep 2028 (portal listing); no contractor yet

Phase 3 moved from about 0.3% to 5.72% between the DLD inspections of 28 April and 21 July 2026, and phase 1 from 3.7% to 6.6%.

How the Bay Grove Residences handover date has changed

Date What happened Source
Oct 2024 Phase 1 launched, 296 homes Propsearch
Dec 2024 Next phase released from about AED 1.85 million Propsearch; Property Finder
15 Feb 2025 Phase 3 sales open, expected completion 1 Mar 2029 Property Finder
17 Jun 2025 Phase 3 registered construction start, completion 21 Sep 2028 on file DLD register, via Continental Club
Jul to Aug 2025 Final phase launched, 257 homes, listed for Sep 2028 Propsearch; portal listing
28 Apr 2026 Phase 1 at 3.7%, phase 3 at about 0.3% DLD inspections
21 Jul 2026 Phase 1 at 6.6%, phase 3 at 5.72% DLD inspections
8 Sep 2026 Propsearch estimate: Sep 2028 Propsearch
17 Sep 2026 Main contract for phases 1 and 3; main works due late 2028. Phases 2 and 4 still to be contracted Nakheel via Dubai Holding

The 15 March 2028 date for phase 1 has not been changed on the register, but Nakheel’s own target is now late 2028.

What the Bay Grove Residences handover date means for payments

The published plan is 20% at booking, 50% during construction and 30% at handover (Property Finder). One phase 2 schedule spreads the 50% over six instalments due 6 to 26 months after booking, with the final 30% due on handover at 100% completion (Sandwater, August 2026). The construction instalments follow the calendar, so a later handover moves only the last 30%. On a 1 bedroom unit at the launch price of AED 1.85 million, that is AED 555,000.

What to check before relying on the Bay Grove Residences date

  1. Which phase the unit is in. Phase 1 and phase 3 have registered dates six months apart, and Property Finder lists phase 3 a year after phase 1.
  2. Whether the phase has a main contractor. Phases 2 and 4 had none on 17 September 2026, so any date quoted for them is not yet backed by a construction contract.
  3. The completion date in the SPA against Nakheel’s late 2028 target. For phase 1 the registered date of 15 March 2028 sits months before the main works target, which brings the SPA grace period into play.
  4. The building number on resale paperwork. DLD transactions are recorded by building (Building 01 to 04 in phase 1), which shows which phase a resale unit belongs to.

Questions buyers also ask

Is Bay Grove Residences finished?

No. The DLD inspection on 21 July 2026 recorded phase 1 at 6.6% and phase 3 at 5.72%, with piling and enabling works under way. Nakheel only awarded the main construction contract for these two phases on 17 September 2026.

When will Bay Grove Residences be ready?

Nakheel expects main works on phases 1 and 3 to finish in late 2028 (17 September 2026). Handover follows completion of those works. Propsearch estimates September 2028 for the project (updated 8 September 2026).

What is the Bay Grove Residences completion date on the DLD register?

Phase 1, DLD project 3293, has a registered completion date of 15 March 2028. Phase 3, registered as Bay Grove Residences B, DLD project 3631, has 21 September 2028 (DLD register, via Continental Club, September 2026).

When will Bay Grove Residences phases 2 and 4 be ready?

No firm date is set. Nakheel said on 17 September 2026 that plans for the 617 homes in phases 2 and 4 are progressing and that construction appointments will be announced later. Portal listings give Q4 2028 for phase 2 and September 2028 for phase 4, but neither phase had a main contractor at that point.

Has the Bay Grove Residences handover date been delayed?

Nakheel has not announced a delay. Its late 2028 target for main works is later than the 15 March 2028 registered completion date for phase 1 and the Q1 2028 date on Property Finder, so phase 1 is unlikely to be handed over by March 2028.

Sources