Handover date

When is the Baccarat Hotel & Residences Dubai handover date?

Updated 11 October 2026 Baccarat Hotel & Residences Dubai

Short answer

Baccarat Hotel & Residences Dubai has a registered completion date of 29 December 2026 in the Dubai Land Department project register, but the DLD inspection of 3 September 2026 recorded only 21.16% complete. The developer-supplied date is Q2 2027, and Property Finder lists December 2027 for the Phase 2 tower. At that inspection about 79% of the work remained for the last four months of 2026.

Registered completion date (DLD)

29 Dec 2026

DLD project register via Continental Club, registry updated 7 Oct 2026

Latest construction progress

21.16%

DLD inspection, 3 Sep 2026

Developer's stated date

Q2 2027

Developer supplied, via Continental Club

Phase 2 tower, portal date

Q4 2027

Property Finder, accessed 11 Oct 2026

Baccarat Hotel & Residences Dubai handover date: the latest position

Baccarat Hotel & Residences Dubai has a registered completion date of 29 December 2026 in the Dubai Land Department (DLD) project register. The DLD inspection of 3 September 2026 recorded 21.16% complete, so close to four fifths of the work remained less than four months before that date. Full project details are on the Baccarat Hotel & Residences Dubai page.

The later dates in circulation are Q2 2027, supplied by the developer to Continental Club, and December 2027, which Property Finder lists for the Phase 2 tower. Shamal Holding has not published a revised opening date for the hotel.

Baccarat Hotel & Residences Dubai handover date by building

The DLD register holds one project with two buildings and one registered date. Portals split the sales into two phases.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Whole project, 2 buildings (98 units) 21.16% (3 Sep 2026) 29 Dec 2026 Q2 2027 (developer, via Continental Club)
Tower one: hotel and first 49 residences Not reported separately 29 Dec 2026 Q4 2026 in the 2024 payment plan (Off Plan Bazaar)
Phase 2 tower Not reported separately 29 Dec 2026 December 2027 (Property Finder)

DLD figures via Continental Club, registry updated 7 October 2026. The 2023 announcement placed the 144-room hotel and 49 residences in tower one.

How the Baccarat Hotel & Residences Dubai handover date has changed

Date What was stated Source
7 Feb 2023 Project announced, slated to open in 2026 Shamal Holding via PR Newswire
20 Mar 2023 Registered construction start; completion date 29 December 2026 DLD register via Continental Club
5 Feb 2024 Groundbreaking; still set to open in 2026 Shamal Holding via Hotel Executive
27 Dec 2024 Payment plan lists 40% on completion in Q4 2026 Off Plan Bazaar
31 Dec 2024 Hotel expected to open in 2026 or 2027 Business Traveller
29 Jan 2026 DLD inspection at 12.92% DLD register via Continental Club
12 Feb 2026 Shamal describes the hotel as set to open this year Construction Business News Middle East
3 Sep 2026 DLD inspection at 21.16%; registered date unchanged DLD register via Continental Club
Oct 2026 Developer date Q2 2027; Phase 2 December 2027 Continental Club; Property Finder

What the Baccarat Hotel & Residences Dubai handover date means for payments

The plan is 5% on booking, 15% on the SPA, four instalments of 10% at 6, 12, 18 and 24 months after the SPA, and 40% on completion (Off Plan Bazaar). The four 10% instalments run on the calendar, so most buyers reach 60% paid well before completion. The 40% balance, about AED 9.6 million on a 3 bedroom at the AED 23.9 million registered median, falls due only when the building is completed.

What to check before relying on the Baccarat Hotel & Residences Dubai date

  1. Which phase the SPA refers to. Phase 1 material quoted Q4 2026; Property Finder gives Q4 2027 for Phase 2.
  2. The SPA completion date and grace period, since the registered 29 December 2026 date will pass with the project far from finished.
  3. The construction pace. Continental Club measures about 1.11 points a month over the past year; reaching completion by December 2027 would need about 5 points a month.

Questions buyers also ask

What is the Baccarat Residences Dubai completion date?

The DLD register records 29 December 2026 for project 2724, Baccarat Hotel & Residences Dubai, which covers two buildings and 98 units (via Continental Club).

Has the Baccarat Hotel & Residences Dubai handover date been delayed?

In practice, yes. Shamal Holding announced a 2026 opening in February 2023 and repeated it in February 2026, but the project was 21.16% complete in September 2026. The developer-supplied date is now Q2 2027, and Property Finder gives Q4 2027 for Phase 2.

Is Baccarat Hotel & Residences Dubai finished?

No. It was 21.16% complete at the DLD inspection of 3 September 2026, up from 12.92% on 29 January 2026.

When will Baccarat Residences Phase 2 be ready?

Property Finder lists Phase 2 with an expected completion of 1 December 2027. The DLD register gives a single date, 29 December 2026, for both buildings.

Sources