When is the Baccarat Hotel & Residences Dubai handover date?
Short answer
Baccarat Hotel & Residences Dubai has a registered completion date of 29 December 2026 in the Dubai Land Department project register, but the DLD inspection of 3 September 2026 recorded only 21.16% complete. The developer-supplied date is Q2 2027, and Property Finder lists December 2027 for the Phase 2 tower. At that inspection about 79% of the work remained for the last four months of 2026.
Registered completion date (DLD)
29 Dec 2026
DLD project register via Continental Club, registry updated 7 Oct 2026
Latest construction progress
21.16%
DLD inspection, 3 Sep 2026
Developer's stated date
Q2 2027
Developer supplied, via Continental Club
Phase 2 tower, portal date
Q4 2027
Property Finder, accessed 11 Oct 2026
Baccarat Hotel & Residences Dubai handover date: the latest position
Baccarat Hotel & Residences Dubai has a registered completion date of 29 December 2026 in the Dubai Land Department (DLD) project register. The DLD inspection of 3 September 2026 recorded 21.16% complete, so close to four fifths of the work remained less than four months before that date. Full project details are on the Baccarat Hotel & Residences Dubai page.
The later dates in circulation are Q2 2027, supplied by the developer to Continental Club, and December 2027, which Property Finder lists for the Phase 2 tower. Shamal Holding has not published a revised opening date for the hotel.
Baccarat Hotel & Residences Dubai handover date by building
The DLD register holds one project with two buildings and one registered date. Portals split the sales into two phases.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Whole project, 2 buildings (98 units) | 21.16% (3 Sep 2026) | 29 Dec 2026 | Q2 2027 (developer, via Continental Club) |
| Tower one: hotel and first 49 residences | Not reported separately | 29 Dec 2026 | Q4 2026 in the 2024 payment plan (Off Plan Bazaar) |
| Phase 2 tower | Not reported separately | 29 Dec 2026 | December 2027 (Property Finder) |
DLD figures via Continental Club, registry updated 7 October 2026. The 2023 announcement placed the 144-room hotel and 49 residences in tower one.
How the Baccarat Hotel & Residences Dubai handover date has changed
| Date | What was stated | Source |
|---|---|---|
| 7 Feb 2023 | Project announced, slated to open in 2026 | Shamal Holding via PR Newswire |
| 20 Mar 2023 | Registered construction start; completion date 29 December 2026 | DLD register via Continental Club |
| 5 Feb 2024 | Groundbreaking; still set to open in 2026 | Shamal Holding via Hotel Executive |
| 27 Dec 2024 | Payment plan lists 40% on completion in Q4 2026 | Off Plan Bazaar |
| 31 Dec 2024 | Hotel expected to open in 2026 or 2027 | Business Traveller |
| 29 Jan 2026 | DLD inspection at 12.92% | DLD register via Continental Club |
| 12 Feb 2026 | Shamal describes the hotel as set to open this year | Construction Business News Middle East |
| 3 Sep 2026 | DLD inspection at 21.16%; registered date unchanged | DLD register via Continental Club |
| Oct 2026 | Developer date Q2 2027; Phase 2 December 2027 | Continental Club; Property Finder |
What the Baccarat Hotel & Residences Dubai handover date means for payments
The plan is 5% on booking, 15% on the SPA, four instalments of 10% at 6, 12, 18 and 24 months after the SPA, and 40% on completion (Off Plan Bazaar). The four 10% instalments run on the calendar, so most buyers reach 60% paid well before completion. The 40% balance, about AED 9.6 million on a 3 bedroom at the AED 23.9 million registered median, falls due only when the building is completed.
What to check before relying on the Baccarat Hotel & Residences Dubai date
- Which phase the SPA refers to. Phase 1 material quoted Q4 2026; Property Finder gives Q4 2027 for Phase 2.
- The SPA completion date and grace period, since the registered 29 December 2026 date will pass with the project far from finished.
- The construction pace. Continental Club measures about 1.11 points a month over the past year; reaching completion by December 2027 would need about 5 points a month.
Questions buyers also ask
What is the Baccarat Residences Dubai completion date?
The DLD register records 29 December 2026 for project 2724, Baccarat Hotel & Residences Dubai, which covers two buildings and 98 units (via Continental Club).
Has the Baccarat Hotel & Residences Dubai handover date been delayed?
In practice, yes. Shamal Holding announced a 2026 opening in February 2023 and repeated it in February 2026, but the project was 21.16% complete in September 2026. The developer-supplied date is now Q2 2027, and Property Finder gives Q4 2027 for Phase 2.
Is Baccarat Hotel & Residences Dubai finished?
No. It was 21.16% complete at the DLD inspection of 3 September 2026, up from 12.92% on 29 January 2026.
When will Baccarat Residences Phase 2 be ready?
Property Finder lists Phase 2 with an expected completion of 1 December 2027. The DLD register gives a single date, 29 December 2026, for both buildings.