When is the Augusta Town Square handover date?
Short answer
Augusta Town Square has a registered completion date of 14 January 2028, and Nshama gives Q1 2028. The Dubai Land Department inspection of 10 September 2026 recorded 5.33%, up from 0.49% in February 2026. Meeting the date would need about 6 points of progress a month, far above the pace recorded so far.
Registered completion date
14 Jan 2028
DLD project register via Continental Club and Mitchells
Latest construction progress
5.33%
DLD inspection, 10 Sep 2026
Developer's stated date
Q1 2028
Nshama, via Property Finder and Metropolitan (23 May 2025)
Progress, Feb to Sep 2026
+4.84 points
DLD project register via Continental Club
Augusta Town Square handover date: the latest position
Augusta Town Square is registered with the Dubai Land Department (DLD) for completion on 14 January 2028. Nshama gives Q1 2028, the quarter it announced at launch, and Property Finder shows 14 January 2028. Prices, sizes and the payment plan are on the project page: Augusta Town Square.
The DLD inspection of 10 September 2026 recorded the building 5.33% complete. That leaves about 16 months for the remaining 94.67 points, close to 6 points a month. The register recorded 4.84 points over the seven months from February to September 2026.
Augusta Town Square handover date by building
Augusta is a single 18-storey building (G+2P+14+R) with ground-floor retail, registered as “Augusta Town Square” with 154 units in Al Yelayiss 2, the DLD district for Town Square.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Augusta Town Square (DLD project 3649, 154 units) | 5.33% (10 Sep 2026) | 14 Jan 2028 | Q1 2028 (Nshama); 14 Jan 2028 (Property Finder); January 2028 (launch payment schedule) |
How the Augusta Town Square handover date has changed
| Date | Event | Source |
|---|---|---|
| 9 Apr 2025 | DLD inspection: 0% | DLD register via Continental Club |
| 18 Apr 2025 | Launch listings show final 50% due on handover in January 2028 | Remington Properties |
| 12 May 2025 | First DLD-registered sale | Mitchells |
| 23 May 2025 | Nshama presents Augusta with completion in Q1 2028 | Metropolitan Premium Properties |
| 10 Oct 2025 | Registered construction start; completion registered for 14 Jan 2028 | DLD register via Mitchells |
| 17 Feb 2026 | DLD inspection: 0.49% | DLD register via Continental Club |
| 10 Sep 2026 | DLD inspection: 5.33% | DLD register via Continental Club |
The date has not moved. What has changed is the time left: by September 2026, 11 of the 27 months between the registered construction start and January 2028 had passed, but only about 5% of the work was done.
What the Augusta Town Square handover date means for payments
On the 50/50 plan, buyers pay 10% on booking and four instalments of 10% at about 2, 9, 15 and 21 months after purchase, then 50% on handover (Tanami Properties). Some 40/60 offers leave 60% for completion. For a 2 bedroom at the 2026 registered price of AED 1,594,888, the handover payment is about AED 797,000 on the 50/50 plan. The construction instalments run by date, not progress, so buyers who booked in 2025 will have paid the first 50% well before handover.
What to check before relying on the Augusta Town Square date
- The next DLD inspection. A reading well above 5.33% would be the first sign the building can reach 14 January 2028.
- The SPA completion date and grace period, which govern any delay beyond the registered date.
- Whether the unit is on the 50/50 or 40/60 offer, since the amount due on handover differs by 10% of the price.
Questions buyers also ask
Is Augusta Town Square finished?
No. The DLD inspection of 10 September 2026 recorded 5.33%. Its registered completion date is 14 January 2028.
What is the Augusta Town Square completion date?
14 January 2028 on the DLD register (project 3649). Nshama gives Q1 2028, and Property Finder shows the same 14 January 2028.
Has the Augusta Town Square handover date been delayed?
No new date has been filed. The registered date and Nshama's Q1 2028 have not changed since launch. The risk is pace: the building gained 4.84 points between February and September 2026.
When is the final payment due at Augusta Town Square?
On the 50/50 plan, 50% of the price is due on handover, which the launch schedule placed in January 2028 (Remington Properties, 18 April 2025).