Handover date

When is the At 85 Residences handover date?

Updated 11 October 2026 At 85 Residences

Short answer

At 85 Residences has a registered completion date of 15 March 2028 in the DLD project register, and the developer's date is Q1 2028. The only published DLD inspection, dated 12 January 2026, recorded 0%, just before construction officially started on 15 January 2026. Launch listings said Q2 2028, so sales material and the register differ by a quarter.

Registered completion date (DLD)

15 Mar 2028

DLD project register via Continental Club, accessed 11 Oct 2026

Latest construction progress

0%

DLD inspection, 12 Jan 2026

Developer's stated date

Q1 2028

Developer supplied via Continental Club; Alnair, 15 Apr 2026

Date in launch listings

Q2 2028

Genz Properties, Elevation and Alnair, Feb 2026

At 85 Residences handover date: the latest position

At 85 Residences is registered with the Dubai Land Department for completion on 15 March 2028. Continental Club lists the developer’s date as Q1 2028, matching the register. Full project details are on the At 85 Residences page.

The only published DLD inspection, dated 12 January 2026, recorded 0%. The registered construction start is 15 January 2026, so the register gives about 26 months to build a ground, podium and six floor building with 261 units.

At 85 Residences handover date by building

The DLD register holds At 85 Residences as one project, so one date applies to the apartments, podium villas and townhouses alike. Its 261 units are 30 studios, 87 one bedrooms, 88 two bedrooms and 56 three bedroom homes, and escrow payments go to Ajman Bank.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
At 85 Residences (DLD project 4325, 261 units) 0% (12 Jan 2026) 15 Mar 2028 Q1 2028 (developer via Continental Club; Alnair, Apr 2026); Q2 2028 (Genz, Elevation, Feb 2026)

How the At 85 Residences handover date has changed

Date Event Source
30 Dec 2025 or 12 Jan 2026 DLD inspection records 0% (sources give different days) Dubai Handover; Continental Club
15 Jan 2026 Registered construction start DLD register via Continental Club
12 to 14 Feb 2026 Launch listings give Q2 2028 Alnair, Elevation
17 Feb 2026 Scope Properties unveils the project Scope Properties
15 Apr 2026 Alnair notice gives completion as Q1 2028 Alnair
4 Aug to 9 Oct 2026 Daily register snapshots show 15 Mar 2028 unchanged Dubai Handover

The registered date has not moved. Buyers who booked at launch may still have Q2 2028 in their sales material.

What the At 85 Residences handover date means for payments

The 40/60 plan puts 60% of the price on completion. For a studio at the AED 650,000 launch price, that is AED 390,000 due on handover. The other 40% is paid on fixed dates: 10% on booking, 10% within 30 days, and 5% on each of 1 September 2026, 1 January 2027, 1 May 2027 and 1 September 2027 (Genz Properties).

Because the 40% runs on calendar dates, a later handover does not change those payments. It only moves the 60% balance, and with it the date buyers need cash or a mortgage in place.

What to check before relying on the At 85 Residences date

  1. The date printed in the SPA, Q1 or Q2 2028, and the grace period after it.
  2. A newer DLD reading. The public register shows only the 0% inspection from January 2026, while two fixed instalments have fallen due since; the Dubai REST app shows the current percentage for project 4325.
  3. Mortgage timing for the 60% balance, since bank valuations happen near handover.

Questions buyers also ask

When will At 85 Residences be ready?

The DLD register sets 15 March 2028 as the completion date, and the developer gives Q1 2028. The project was at 0% at the January 2026 inspection, the latest published.

What is the At 85 Residences completion date?

15 March 2028, as filed with DLD under project number 4325 (Continental Club, registry updated 6 Oct 2026; Dubai Handover, 9 Oct 2026).

Has the At 85 Residences handover date changed?

Not in the register. Launch listings in February 2026 said Q2 2028, while the register has shown 15 March 2028 and the developer Q1 2028. Dubai Handover's daily snapshots show no change between August and October 2026.

When does At 85 Residences construction start?

The registered construction start is 15 January 2026. DLD's only published inspection, dated 12 January 2026, recorded 0%.