
When is the Ashley Hills handover date?
Short answer
Ashley Hills has a registered completion date of 31 March 2027, and TownX gives Q1 2027. The DLD recorded the project 74.05% complete on 10 June 2026, up from 51.70% in February 2026. At that pace the build could finish ahead of the registered date, but handover follows completion certificates and snagging, so the SPA date remains the reference.
Registered completion date (DLD)
31 Mar 2027
DLD register via Mitchells, 4 Oct 2026
Latest construction progress
74.05%
DLD inspection, 10 Jun 2026
Developer's stated date
Q1 2027
TownX construction update, 6 Apr 2026
Projected 100% at past pace
Around 30 Oct 2026
Continental Club estimate from DLD inspections
Ashley Hills handover date: the latest position
Ashley Hills is registered for completion on 31 March 2027, and TownX gives Q1 2027 for handover. In its construction update of 6 April 2026, TownX said the project was “on track for handover in Q1 2027”. Full project details are on the Ashley Hills page.
The DLD inspection of 10 June 2026 recorded 74.05% progress, the latest published figure. The project gained 22.35 points between February and June 2026. Continental Club estimates that, at the past year’s pace of about 5.6 points a month, construction would reach 100% around 30 October 2026. Handover then depends on the building completion certificate, utility connections and snagging.
Ashley Hills handover date by building
The DLD register files Ashley Hills as one project, DLD project number 3723, with 616 homes in Arjan.
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Ashley Hills (616 units) | 74.05% (10 Jun 2026) | 31 Mar 2027 | Q1 2027 (TownX, 6 Apr 2026); 31 Mar 2027 (Takween Aldar) |
Some broker pages describe the project as two residential blocks. The register gives a single completion date for all 616 units.
How the Ashley Hills handover date has changed
| Date | Event | Source |
|---|---|---|
| 15 Feb 2025 | Registered construction start | DLD register via Mitchells |
| 19 Jul 2025 | TownX opens expressions of interest | TownX on LinkedIn |
| 25 Jul 2025 | Launch, 616 units, 40/60 and 70/30 plans | Rental Living News |
| 18 Aug 2025 | DLD inspection, 20.02% | DLD register via Continental Club |
| 19 Nov 2025 | DLD inspection, 39.01% | DLD register via Continental Club |
| 19 Feb 2026 | DLD inspection, 51.70% | DLD register via Continental Club |
| 6 Apr 2026 | TownX: on track for Q1 2027 | TownX on LinkedIn |
| 10 Jun 2026 | DLD inspection, 74.05% | DLD register via Continental Club |
The Q1 2027 date has not changed since sales began, and the registered 31 March 2027 matches it. Construction started about five months before the public launch, which helps explain the short build time.
What the Ashley Hills handover date means for payments
Under the 40/60 plan, buyers pay 20% down and 20% during construction, then 60% on handover. If the build finishes early, the 60% can fall due earlier than March 2027. On a studio bought at about AED 700,000, that is about AED 420,000. Under the 70/30 plan offered at launch, 70% is paid during construction and 30% at handover. Buyers using a mortgage for the handover payment need a bank valuation near completion.
What to check before relying on the Ashley Hills date
- The SPA completion date and grace period, against the registered 31 March 2027.
- Whether the handover payment can be called early. At 74% in June 2026, completion could come before March 2027, and the 60% under 40/60 falls due at handover.
- The next DLD inspection. The June 2026 figure is four months old; a newer one will confirm whether the pace has held.
- TownX’s record on its other current project, 11 Hills Park, also registered for 31 March 2027.
Questions buyers also ask
When will Ashley Hills be completed?
The registered completion date is 31 March 2027 (DLD register via Mitchells, 4 October 2026). TownX gives Q1 2027. The DLD recorded 74.05% progress on 10 June 2026.
Is Ashley Hills on schedule?
The DLD figures suggest so. Progress rose from 20.02% in August 2025 to 74.05% in June 2026. Continental Club projects 100% around 30 October 2026 at the past year's pace, which is an estimate rather than a TownX date.
Could Ashley Hills be handed over early?
Possibly. TownX completed four of its five previous buildings ahead of their estimated dates, including Luma Park Views in October 2025 against an estimated June 2026 (TownX delivery record). TownX has not announced an early date for Ashley Hills.
What is due at Ashley Hills handover?
Under the 40/60 plan, 60% of the price is due on handover. Under the 70/30 plan offered at launch, 30% is due at handover.

