When is the Al Haseen Residences handover date?

Updated 11 October 2026 Al Haseen Residences

Short answer

Al Haseen Residences 3 has a registered completion date of 15 May 2027, with a developer handover of Q2 2027. The last Dubai Land Department inspection, on 14 July 2026, recorded it 10.08% complete. Phase 4 is registered for 30 December 2026 and phase 5 for 3 June 2027, but both were under 12% complete in mid 2026, so all three dates are at risk of moving.

Phase 3 registered completion date

15 May 2027

DLD project register via Continental Club

Phase 3 construction progress

10.08%

DLD inspection, 14 Jul 2026

Phase 3 developer handover

Q2 2027

JRE Dubai, accessed 11 Oct 2026

Phase 4 registered completion

30 Dec 2026

11.76% at DLD inspection, 14 Jul 2026

Al Haseen Residences handover date: the latest position

Al Haseen Residences 3 is registered with the Dubai Land Department (DLD) for completion on 15 May 2027, and JRE gives a developer handover of Q2 2027. The DLD inspection of 14 July 2026 recorded 10.08% complete. Prices, sizes and payment plans for each phase are on the project page: Al Haseen Residences.

The two other buildings under construction are further behind their dates. Phase 4 is registered for 30 December 2026 and was 11.76% complete on 14 July 2026. Phase 5 is registered for 3 June 2027 and was 4.22% complete on 25 June 2026. The first two Al Haseen buildings are completed: phase 1 has a registered completion date of 30 April 2020, and phase 2 is listed as ready.

Al Haseen Residences handover date by building

Building Construction progress (DLD, date) Registered completion date Developer or portal date
Al Haseen Residence (phase 1, 138 units) 100% (11 May 2020) 30 Apr 2020 Completed
Al Haseen Residence 2 Completed Not published Ready (Continental Club)
Al Haseen Residences 3 (180 units) 10.08% (14 Jul 2026) 15 May 2027 Q2 2027 (JRE); 29 Jun 2026 (PropertyStellar, out of date)
Al Haseen Residence 4 (248 units) 11.76% (14 Jul 2026) 30 Dec 2026 Q4 2026 (Continental Club, Property Finder)
Al Haseen Residence 5 (245 units) 4.22% (25 Jun 2026) 3 Jun 2027 Dec 2026 (Property Finder, Jan 2026); Q4 2027 (Ezre)

DLD figures are from the DLD project register via Continental Club, Data Dubai and Mitchells. Phase 3 is DLD project number 3484, phase 4 is 3562 and phase 5 is 4461.

How the Al Haseen Residences handover date has changed

Date Event Source
27 Jan 2025 Phase 3 first DLD inspection: 0% Data Dubai
7 Feb 2025 Phase 3 registered; completion date 15 May 2027 Data Dubai
15 Apr 2025 Phase 3 construction start Data Dubai
29 Jun 2025 Phase 4 bookings open and construction starts; due 30 December 2026 Property Finder; Continental Club
29 Sep 2025 Phase 3 inspection: 0.6% Data Dubai
3 Dec 2025 Phase 5 construction start; due 3 June 2027 Continental Club
25 Feb 2026 Phase 3 at 3.3%; phase 4 at about 2.2% Data Dubai; Continental Club
14 Jul 2026 Phase 3 at 10.08%; phase 4 at 11.76% DLD via Continental Club

None of the registered dates had changed by October 2026. Phase 3 was at 0.6% five and a half months after its start, and moved faster in 2026. At its February to July 2026 pace of about 1.5 points a month, it would not reach 100% by May 2027. The completed phase 1 took three years, from May 2017 to April 2020.

What the Al Haseen Residences handover date means for payments

The plans put much of the price at or after handover, so the date matters most for the timing of those payments. Phase 4 buyers pay 10% at booking, 20% during construction and 70% on handover, so a delay pushes back the largest payment. Phase 3 is sold with a post-handover plan, listed by PropertyStellar as 30% before and 70% after handover, so the handover date starts that schedule. Several phase 5 plans put 60% after handover (Ezre).

What to check before relying on the Al Haseen Residences date

  1. The phase number on the SPA and Oqood. The three buildings have separate DLD registrations and dates, and listings often just say “Al Haseen Residences”.
  2. The next DLD inspection for phase 4, which needed close to 90 points in under six months to meet 30 December 2026.
  3. The SPA grace period for phase 3, since the 2026 pace points past 15 May 2027.

Questions buyers also ask

When will Al Haseen Residences 3 be completed?

The registered completion date is 15 May 2027, and JRE gives Q2 2027. It was 10.08% complete at the DLD inspection of 14 July 2026.

When will Al Haseen Residences 4 be ready?

Phase 4 is registered for 30 December 2026 and listed for Q4 2026, but it was 11.76% complete at the DLD inspection of 14 July 2026 (DLD register via Continental Club).

When will Al Haseen Residences 5 be handed over?

The registered completion date is 3 June 2027 and it was 4.22% complete on 25 June 2026. Sources disagree on the developer date: Property Finder showed December 2026 in January 2026, while Ezre lists Q4 2027.

Has the Al Haseen Residences handover date been delayed?

The registered dates have not changed yet, but progress is well behind them. Phase 4 had about 88% of its work left five and a half months before its December 2026 date.

Sources

  1. Mitchells, Al Haseen Residence (phase 1) DLD registry (opens in a new tab)mitchellscommercialrealty.com · registry 4 Oct 2026
  2. PropertyStellar, Al Haseen Residences 3 (opens in a new tab)propertystellar.com · accessed 11 Oct 2026
  3. Continental Club, Al Haseen Residence 2 (opens in a new tab)continentalclub.ae · accessed 11 Oct 2026
Request a Unit Review