When is the Al Haseen Residences handover date?
Short answer
Al Haseen Residences 3 has a registered completion date of 15 May 2027, with a developer handover of Q2 2027. The last Dubai Land Department inspection, on 14 July 2026, recorded it 10.08% complete. Phase 4 is registered for 30 December 2026 and phase 5 for 3 June 2027, but both were under 12% complete in mid 2026, so all three dates are at risk of moving.
Phase 3 registered completion date
15 May 2027
DLD project register via Continental Club
Phase 3 construction progress
10.08%
DLD inspection, 14 Jul 2026
Phase 3 developer handover
Q2 2027
JRE Dubai, accessed 11 Oct 2026
Phase 4 registered completion
30 Dec 2026
11.76% at DLD inspection, 14 Jul 2026
Al Haseen Residences handover date: the latest position
Al Haseen Residences 3 is registered with the Dubai Land Department (DLD) for completion on 15 May 2027, and JRE gives a developer handover of Q2 2027. The DLD inspection of 14 July 2026 recorded 10.08% complete. Prices, sizes and payment plans for each phase are on the project page: Al Haseen Residences.
The two other buildings under construction are further behind their dates. Phase 4 is registered for 30 December 2026 and was 11.76% complete on 14 July 2026. Phase 5 is registered for 3 June 2027 and was 4.22% complete on 25 June 2026. The first two Al Haseen buildings are completed: phase 1 has a registered completion date of 30 April 2020, and phase 2 is listed as ready.
Al Haseen Residences handover date by building
| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Al Haseen Residence (phase 1, 138 units) | 100% (11 May 2020) | 30 Apr 2020 | Completed |
| Al Haseen Residence 2 | Completed | Not published | Ready (Continental Club) |
| Al Haseen Residences 3 (180 units) | 10.08% (14 Jul 2026) | 15 May 2027 | Q2 2027 (JRE); 29 Jun 2026 (PropertyStellar, out of date) |
| Al Haseen Residence 4 (248 units) | 11.76% (14 Jul 2026) | 30 Dec 2026 | Q4 2026 (Continental Club, Property Finder) |
| Al Haseen Residence 5 (245 units) | 4.22% (25 Jun 2026) | 3 Jun 2027 | Dec 2026 (Property Finder, Jan 2026); Q4 2027 (Ezre) |
DLD figures are from the DLD project register via Continental Club, Data Dubai and Mitchells. Phase 3 is DLD project number 3484, phase 4 is 3562 and phase 5 is 4461.
How the Al Haseen Residences handover date has changed
| Date | Event | Source |
|---|---|---|
| 27 Jan 2025 | Phase 3 first DLD inspection: 0% | Data Dubai |
| 7 Feb 2025 | Phase 3 registered; completion date 15 May 2027 | Data Dubai |
| 15 Apr 2025 | Phase 3 construction start | Data Dubai |
| 29 Jun 2025 | Phase 4 bookings open and construction starts; due 30 December 2026 | Property Finder; Continental Club |
| 29 Sep 2025 | Phase 3 inspection: 0.6% | Data Dubai |
| 3 Dec 2025 | Phase 5 construction start; due 3 June 2027 | Continental Club |
| 25 Feb 2026 | Phase 3 at 3.3%; phase 4 at about 2.2% | Data Dubai; Continental Club |
| 14 Jul 2026 | Phase 3 at 10.08%; phase 4 at 11.76% | DLD via Continental Club |
None of the registered dates had changed by October 2026. Phase 3 was at 0.6% five and a half months after its start, and moved faster in 2026. At its February to July 2026 pace of about 1.5 points a month, it would not reach 100% by May 2027. The completed phase 1 took three years, from May 2017 to April 2020.
What the Al Haseen Residences handover date means for payments
The plans put much of the price at or after handover, so the date matters most for the timing of those payments. Phase 4 buyers pay 10% at booking, 20% during construction and 70% on handover, so a delay pushes back the largest payment. Phase 3 is sold with a post-handover plan, listed by PropertyStellar as 30% before and 70% after handover, so the handover date starts that schedule. Several phase 5 plans put 60% after handover (Ezre).
What to check before relying on the Al Haseen Residences date
- The phase number on the SPA and Oqood. The three buildings have separate DLD registrations and dates, and listings often just say “Al Haseen Residences”.
- The next DLD inspection for phase 4, which needed close to 90 points in under six months to meet 30 December 2026.
- The SPA grace period for phase 3, since the 2026 pace points past 15 May 2027.
Questions buyers also ask
When will Al Haseen Residences 3 be completed?
The registered completion date is 15 May 2027, and JRE gives Q2 2027. It was 10.08% complete at the DLD inspection of 14 July 2026.
When will Al Haseen Residences 4 be ready?
Phase 4 is registered for 30 December 2026 and listed for Q4 2026, but it was 11.76% complete at the DLD inspection of 14 July 2026 (DLD register via Continental Club).
When will Al Haseen Residences 5 be handed over?
The registered completion date is 3 June 2027 and it was 4.22% complete on 25 June 2026. Sources disagree on the developer date: Property Finder showed December 2026 in January 2026, while Ezre lists Q4 2027.
Has the Al Haseen Residences handover date been delayed?
The registered dates have not changed yet, but progress is well behind them. Phase 4 had about 88% of its work left five and a half months before its December 2026 date.