Handover date

When is the 11 Hills Park handover date?

Updated 11 October 2026 11 Hills Park

Short answer

11 Hills Park has a registered completion date of 31 March 2027, and TownX gives Q1 2027 for handover. The Dubai Land Department (DLD) recorded the tower 80.05% complete at its inspection of 30 April 2026, up from 41% on 22 October 2025. No newer DLD figure had been published by 7 October 2026, so the remaining 20% of the work is not yet confirmed by an inspection.

Registered completion date (DLD)

31 Mar 2027

DLD register via Continental Club, updated 7 Oct 2026

Latest construction progress

80.05%

DLD inspection, 30 Apr 2026

Developer's stated date

Q1 2027

TownX, accessed 11 Oct 2026

Change since launch

None

Q1 2027 at launch in Nov 2024 and now

11 Hills Park handover date: the latest position

11 Hills Park is due for completion on 31 March 2027, the date on the Dubai Land Department (DLD) register, and TownX gives Q1 2027 for handover. Propsearch’s estimate is March 2027. See the 11 Hills Park project page for prices, sizes and the payment plan.

The latest DLD inspection, on 30 April 2026, recorded the tower 80.05% complete. TownX said it had reached 80% in its May 2026 update and kept publishing monthly updates through August 2026, but those updates do not give a newer percentage, and the register, updated on 7 October 2026, shows no later inspection.

11 Hills Park handover date by building

11 Hills Park is a single 25 storey tower (G+23+R) with 571 registered units.

Building Construction progress (DLD, date) Registered completion date Developer or portal date
11 Hills Park (DLD project 3324) 80.05% (30 Apr 2026) 31 Mar 2027 Q1 2027 (TownX); March 2027 (Propsearch)

The DLD inspection history shows the pace of work:

DLD inspection Progress
22 Jul 2025 26.31%
22 Oct 2025 41.00%
22 Jan 2026 60.52%
30 Apr 2026 80.05%

The January figure is worked back from the 19.53 point rise the register records between the January and April inspections. Continental Club puts the past year’s average at about 5.4% a month. At that pace the structure would have reached 100% in August 2026, well ahead of the March 2027 date, but finishing work, the completion certificate and utility connections usually take longer than the build percentage suggests.

How the 11 Hills Park handover date has changed

Date What happened Source
1 Nov 2024 Construction start recorded on the DLD register DLD register via Dubricks
7 Nov 2024 Project registered with DLD, completion date 31 March 2027 DLD register via Data Dubai and Dubricks
Nov 2024 Sales launch from AED 650,000 Propsearch
17 Sep 2025 TownX says completion expected in Q1 2027 Executive Bulletin
22 Oct 2025 DLD inspection: 41% Continental Club
30 Apr 2026 DLD inspection: 80.05% Continental Club
7 May 2026 TownX reports construction at 80% TownX on LinkedIn
Oct 2026 TownX still lists handover in Q1 2027 TownX

The date has not moved since registration.

What the 11 Hills Park handover date means for payments

The share due at handover depends on the plan. The launch plan put 40% on handover (20% booking, 40% during construction). TownX’s site now lists a 20/80 plan, with 80% on handover, and Bayut shows 40/60. Brokers list further 70/30, 50/50 and 30/70 options. On a studio at TownX’s list price of AED 949,000, an 80% handover payment is about AED 759,200, due around March 2027.

What to check before relying on the 11 Hills Park date

  1. The completion date and grace period in the SPA, since the 31 March 2027 register date is the reference point for any delay claim.
  2. A DLD inspection after April 2026. Until one is published, the last confirmed figure is 80.05%.
  3. The handover payment amount on the specific plan. With up to 80% of the price due at handover, mortgage pre-approval timing matters more than usual.
  4. Snagging and service charge start dates, which begin from handover, not from the completion certificate.

Questions buyers also ask

When will 11 Hills Park be ready?

TownX says Q1 2027, and the DLD register lists 31 March 2027. The tower was 80.05% complete at the DLD inspection of 30 April 2026.

What is the 11 Hills Park completion date?

31 March 2027 is the completion date on the DLD register (project 3324). Propsearch estimates March 2027 and TownX gives Q1 2027.

Has the 11 Hills Park handover date been delayed?

No change has been published. The project was registered with a completion date of 31 March 2027 in November 2024, and TownX was still giving Q1 2027 in September 2025 and October 2026.

How much of 11 Hills Park is built?

80.05% at the DLD inspection of 30 April 2026. Earlier inspections recorded 26.31% on 22 July 2025 and 41% on 22 October 2025 (DLD register via Continental Club).

Sources

  1. DLD project register via Continental Club, 11 Hills Park (opens in a new tab)continentalclub.ae · inspection 30 Apr 2026, register updated 7 Oct 2026
  2. Propsearch, 11 Hills Park (opens in a new tab)propsearch.ae · accessed 11 Oct 2026
  3. TownX, construction updates (opens in a new tab)townx.com · August 2026 update published 10 Sep 2026