Updated: 2026-10-11

Golden Woods' 25-storey JVC tower. Registered completion 14 October 2026, 89.05% built in April 2026, 1 bedroom sales near AED 1,800 per sq ft and post-handover plans.

## Key facts

- Registered completion date: 14 Oct 2026 (DLD project register via Continental Club)
- Construction progress: 89.05% (DLD inspection, 25 Apr 2026)
- Units: 161 (DLD register; Propsearch estimates 160)
- 1 bedroom sales, Sep 2026: AED 770,000 to AED 1.23 million (DLD transactions via Data Habibi)

## When will Golden Wood Views 5 be handed over?

The Dubai Land Department (DLD) register records a completion date of 14 October 2026 for Golden Wood Views 5, and the developer's handover target is Q4 2026 (DLD project register via Continental Club). Propsearch also estimates October 2026. The last published DLD inspection, on 25 April 2026, put the building at 89.05% complete. A daily tracker of the register still showed 89% and the same 14 October 2026 date on 10 October 2026 (Dubai Handover), so no newer inspection had been recorded four days before the registered date.

This is later than the first date buyers were given. Data Habibi's record shows a delivery date of Q4 2025, and a broker listing from January 2026 said handover was expected by the end of Q4 2026.

Building-by-building dates and how the date has changed: [Golden Wood Views 5 handover date](/answers/golden-wood-views-handover-date/).

## Golden Wood Views 5 construction update

Construction started on 14 October 2022, so the register allowed four years for the build. Progress was 83.05% at the inspection on 27 October 2025 and 89.05% on 25 April 2026, a gain of six points in six months. The building is in JVC District 14; the DLD registers it in the Al Barsha South Fourth area, and DLD sales records use the building name Golden Woods Views V. It is a single 25-storey tower with ground floor retail, a pool and a gym (Propsearch; Continental Club). The Land Department valued the project at AED 54.2 million, and the escrow account is with ADCB.

## Golden Wood Views 5 homes and sizes

| Home type | Units | Size range |
|---|---|---|
| 1 bedroom | 118 | 561 to 1,131 sq ft |
| 2 bedroom | 34 | 919 to 1,633 sq ft |
| 3 bedroom | 6 | 1,261 to 1,847 sq ft |
| 4 bedroom | 2 | 5,897 to 5,976 sq ft |

Unit counts and sizes are from Data Habibi's record of the building. They total 160, against 161 units in the DLD register. Some 2 bedroom units are duplexes or have a study, and some 1 bedrooms face the FIVE JVC hotel, according to Property Finder listings.

## Golden Wood Views 5 prices and resale

Data Habibi lists launch prices from AED 499,000 for a 1 bedroom, AED 827,000 for a 2 bedroom and AED 1.03 million for a 3 bedroom. Prices in 2026 are much higher. In September 2026, DLD sales included a 561 sq ft 1 bedroom at AED 770,000, a 684 sq ft 1 bedroom at AED 1,229,922 and a 1,110 sq ft 2 bedroom at AED 2,000,000, about AED 1,800 per sq ft for the last two (Data Habibi). Continental Club counts 149 registered sales, about 1% of them resales, with prices up 19% over the past year.

## Golden Wood Views 5 payment plan

Plans have changed between releases. Data Habibi lists 10% on booking, 49% during construction and 1% on handover, leaving 40% for after handover. Property Finder listings in January 2026 offered a 64/36 plan with 36% paid at 1% a month for 36 months after handover, and a plan with 20% on booking and 80% spread over five years after handover. With handover close, buyers on these plans will be paying most of their balance after receiving the keys.

## Golden Wood Views 5 developer and delivery record

Golden Woods, registered as Golden Wood Real Estate Development, has completed two smaller buildings in Jumeirah Village Triangle. Golden Wood Views (60 units) was 100% complete at a DLD inspection on 11 June 2020 and handed over in Q2 2020 (HomeSearch). Golden Wood Views I (55 units) started in January 2019 and was delivered on 13 September 2022 (Data Habibi). Golden Wood Views 5, at 161 units and 25 storeys, is larger than both. The developer is also building Views VII and Golden Woods Albab Views in Dubai South (JRE).

## What to check before buying at Golden Wood Views 5

1. **Whether the completion certificate has been issued.** The registered date is 14 October 2026, but the last DLD reading was 89.05%.
2. **The handover notice and snagging timeline** for the specific unit, once the developer issues it.
3. **The post-handover balance.** On some plans, between 36% and 80% of the price is still owed after handover.
4. **The service charge budget** for the building's first year, which is set once it is completed.

## Sources

- DLD project register via Continental Club, Golden Wood Views 5, inspection 25 Apr 2026: https://continentalclub.ae/project/golden-wood-views-5-jumeirah-village-circle/
- Dubai Handover, Golden Wood Views 5 daily DLD snapshot, snapshot 10 Oct 2026: https://dubaihandover.com/projects/2539-golden-wood-views-5
- Propsearch, Golden Wood Views 5, updated 16 Aug 2026: https://propsearch.ae/dubai/golden-wood-views-5
- Data Habibi, Golden Wood Views 5 prices and DLD transactions, transactions to 17 Sep 2026: https://datahabibi.ae/dubai/golden-wood-views-5-jumeirah-village-circle
- Property Finder, Golden Wood Views 5 listing (64/36 plan), 20 Jan 2026: https://www.propertyfinder.ae/en/plp/buy/apartment-for-sale-dubai-jumeirah-village-circle-district-14-golden-wood-views-5-92701296.html
- Property Finder, Golden Wood Views 5 listing (5 year post-handover plan), Jan 2026: https://www.propertyfinder.ae/en/plp/buy/apartment-for-sale-dubai-jumeirah-village-circle-district-14-golden-wood-views-5-136083143.html
- HomeSearch, Golden Wood Views JVT (DLD record), accessed 11 Oct 2026: https://www.homesearch.ae/for-sale/off-plan/golden-wood-real-estate-development-1201/golden-wood-views-2021
- Data Habibi, Golden Wood Views I, accessed 11 Oct 2026: https://datahabibi.ae/dubai/new-projects/golden-wood-views-i
- JRE, Golden Woods projects in Dubai, accessed 11 Oct 2026: https://jre.ae/developers/golden-woods