# When is the Wynwood by Imtiaz handover date?

URL: https://www.dxbrealtor.ai/answers/wynwood-by-imtiaz-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Wynwood by Imtiaz has a registered completion date of 30 September 2027, matching the Q3 2027 handover on Imtiaz Developments' project page. The latest DLD inspection, on 6 October 2026, recorded the building 26.26% complete, up from 16% in July. About 74% of the work was left with a year to go, so the pace of the next few inspections decides whether the date holds.

## Key figures

- Registered completion date (DLD): 30 Sep 2027 (DLD register via Continental Club)
- Latest construction progress: 26.26% (DLD inspection, 6 Oct 2026)
- Developer's stated date: Q3 2027 (Imtiaz Developments, accessed 11 Oct 2026)
- Portal date: 30 Sep 2027 (Property Finder, accessed 11 Oct 2026)

## Wynwood by Imtiaz handover date: the latest position

Wynwood by Imtiaz is registered with the Dubai Land Department (DLD) for completion on 30 September 2027. Imtiaz Developments lists Q3 2027 on its project page, and Property Finder and Propsearch give the same quarter. Full project details are on the [Wynwood by Imtiaz](/projects/wynwood-by-imtiaz/) page.

The building was 26.26% complete at the DLD inspection on 6 October 2026. Progress has run at about 10 percentage points a quarter since April 2026.

## Wynwood by Imtiaz handover date by building

Wynwood is a single 18 floor building of 146 homes on Dubai Islands, registered as DLD project 3784. DLD project data on Dubricks shows registration on 1 July 2025 with an anticipated completion date of 30 September 2027.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Wynwood by Imtiaz (G+2P+14+R) | 26.26% (6 Oct 2026) | 30 Sep 2027 | Q3 2027 (Imtiaz); 30 Sep 2027 (Property Finder) |

## How the Wynwood by Imtiaz handover date has changed

| Date | What happened | Source |
|---|---|---|
| 1 May 2025 | Launch date in DLD project data | Dubricks |
| 24 May 2025 | Launch event at the Imtiaz sales gallery in Dubai Hills | Imtiaz Developments |
| 15 Jun 2025 | Sales open; registered construction start | Property Finder; DLD register |
| 1 Jul 2025 | Registered with the DLD, completion 30 Sep 2027 | Dubricks |
| 3 Apr 2026 | 8.45% complete | DLD register via Continental Club |
| 9 Jul 2026 | 16% complete | DLD register via Continental Club |
| 6 Oct 2026 | 26.26% complete | DLD register via Continental Club |

The date has not changed. What has changed is the pace: about 7.5 points from April to July, then about 10 points from July to October. To reach 100% by 30 September 2027, the building needs about 6 points a month, roughly double the rate of the last quarter. The next inspections will show whether the pace rises. Imtiaz's own project page showed a lower progress figure of 21 when accessed on 11 October 2026.

## What the Wynwood by Imtiaz handover date means for payments

The plan is 20% on booking, 40% during construction and 40% on handover (Propsearch; Continental Club). For a 1 bedroom at the registered median of about AED 2.25 million, the handover payment is about AED 900,000. If completion slips past 30 September 2027, that payment moves later, while construction instalments tied to milestones would also follow the slower schedule.

## What to check before relying on the Wynwood by Imtiaz date

1. **The completion date and grace period in the SPA**, given that about 74% of the work remained a year before the registered date.
2. **How the 40% construction instalments are linked**, to dates or to DLD progress milestones.
3. **The next DLD inspection.** If inspections stay roughly quarterly, the next falls around January 2027, and the building would need to be near 45% to stay on the registered schedule.

## Frequently asked

### When will Wynwood by Imtiaz be completed?

The DLD register gives 30 September 2027. Imtiaz lists Q3 2027 and Property Finder 30 September 2027, so the sources agree.

### Has the Wynwood by Imtiaz handover date been delayed?

No change has been recorded. DLD project data shows an anticipated completion date of 30 September 2027 from registration in July 2025, and Imtiaz still shows Q3 2027.

### How far along is Wynwood by Imtiaz?

26.26% at the DLD inspection on 6 October 2026, up from 8.45% on 3 April 2026 and 16% on 9 July 2026 (DLD register via Continental Club).

### When will Wynwood Residence on Dubai Islands be ready?

Wynwood Residence is Imtiaz's marketing name for Wynwood by Imtiaz. Its registered completion date is 30 September 2027, with Imtiaz giving Q3 2027.

## Sources

- Continental Club, projects with handover in 2027 (DLD project register), inspection 6 Oct 2026, accessed 11 Oct 2026: https://continentalclub.ae/handover-2027/
- DLD project register via Continental Club, Wynwood by Imtiaz, registry updated 4 Oct 2026: https://continentalclub.ae/project/wynwood-by-imtiaz-dubai-islands/
- Imtiaz Developments, Wynwood project page, accessed 11 Oct 2026: https://imtiaz.ae/property/wynwood-by-imtiaz
- Imtiaz Developments, Wynwood Residence launch event, 24 May 2025: https://imtiaz.ae/event/wynwood-residence-by-imtiaz-launch-event
- Dubricks, Wynwood by Imtiaz (DLD project data), accessed 11 Oct 2026: https://dubricks.com/project/wynwood-by-imtiaz
- Property Finder, Wynwood by Imtiaz project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/imtiaz-developments/wynwood-by-imtiaz
- Propsearch, Wynwood by Imtiaz, updated 5 Jun 2026: https://propsearch.ae/dubai/wynwood-by-imtiaz