# When is the Vista by Vision handover date?

URL: https://www.dxbrealtor.ai/answers/vista-by-vision-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Vista by Vision has a registered completion date of 1 September 2027, matching the Q3 2027 handover shown by the developer and Property Finder. The last DLD inspection, on 14 May 2026, recorded the building 3.38% complete. With almost all the work still to do and no newer inspection published by 8 October 2026, the date in each buyer's SPA and the next DLD figure are the ones to watch.

## Key figures

- Registered completion date (DLD): 1 Sep 2027 (DLD register via Continental Club)
- Latest construction progress: 3.38% (DLD inspection, 14 May 2026)
- Developer's stated date: Q3 2027 (Developer supplied, via Continental Club)
- Portal date: 1 Sep 2027 (Property Finder, accessed 11 Oct 2026)

## Vista by Vision handover date: the latest position

Vista by Vision is registered with the Dubai Land Department (DLD) for completion on 1 September 2027. Property Finder shows the same date with a Q3 2027 delivery, and Continental Club records Q3 2027 as the developer's date. Full project details are on the [Vista by Vision](/projects/vista-by-vision/) page.

The building was 3.38% complete at the DLD inspection on 14 May 2026. That was the latest figure when the register was updated on 8 October 2026, so the public record says little yet about how fast the tower is rising.

## Vista by Vision handover date by building

Vista by Vision is a single building with a basement, ground floor, 14 residential floors and a roof, registered as DLD project 4175 under the name Vista By Vision.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Vista by Vision (B+G+14+R, 328 units) | 3.38% (14 May 2026) | 1 Sep 2027 | Q3 2027 (developer); 1 Sep 2027 (Property Finder) |

## How the Vista by Vision handover date has changed

| Date | What happened | Source |
|---|---|---|
| 28 Oct 2025 | Vision announces Vista as its next project, B+G+14+R with 321 homes | Vision Developments |
| 28 Oct 2025 | First DLD inspection, 0% | DLD register via Dubai Data |
| 18 Nov 2025 | Registered with the DLD | DLD register via Dubai Data |
| Dec 2025 | Vision says the building sold out in seven hours | Vision Developments |
| 1 Jan 2026 | Registered construction start; Property Finder lists sales from the same day | DLD register; Property Finder |
| 14 May 2026 | 3.38% complete; registered completion 1 Sep 2027 | DLD register via Continental Club |
| 11 Oct 2026 | Property Finder still lists 1 Sep 2027 | Property Finder |

The date has held at Q3 2027, or 1 September 2027, in every source checked. What has not been tested yet is the pace. Continental Club calculates 0.52 percentage points a month from the two inspections so far, and notes that across 1,175 completed Dubai projects the median pace is 2.48 points a month, with a median build of 40 months. The registered schedule gives Vista about 20 months from its January 2026 start.

## What the Vista by Vision handover date means for payments

Property Finder lists the plan as 10% down payment, 10% during construction and 80% on handover. OffPlanIndex also shows a 20% down, 80% on handover version. In both, only 20% is paid before completion, so the handover date sets when buyers need the other 80%. For a 1 bedroom at the registered median of AED 1.11 million, that is about AED 888,000. If the date moves, that payment moves with it.

## What to check before relying on the Vista by Vision date

1. **The anticipated completion date in the SPA**, and whether it says 1 September 2027 or a quarter, plus the grace period allowed after it.
2. **The next DLD inspection.** A figure well above 3.38% would show the superstructure under way.
3. **A mortgage pre-approval timed to the handover date**, since 80% falls due then and the bank will value the finished unit.

## Frequently asked

### When will Vista by Vision be completed?

The DLD register gives 1 September 2027. Property Finder lists the same date, and Continental Club records Q3 2027 as the developer's date.

### Has the Vista by Vision handover date been delayed?

No change has been recorded. The registered completion date of 1 September 2027 matches the Q3 2027 date shown since sales began, and Vision Developments has not announced a new one.

### How far along is Vista by Vision?

3.38% at the DLD inspection on 14 May 2026, up from 0% on 28 October 2025 (Dubai Data). No later inspection had been published when the register was updated on 8 October 2026.

### Is Vista by Vision on track for September 2027?

Too early to tell. Only two inspections have been recorded, and the building would need to go from 3.38% to 100% in about 15 and a half months. Continental Club puts the pace so far at 0.52 percentage points a month.

## Sources

- Continental Club, projects with handover in 2027 (DLD project register), inspection 14 May 2026, accessed 11 Oct 2026: https://continentalclub.ae/handover-2027/
- DLD project register via Continental Club, Vista By Vision, registry updated 8 Oct 2026: https://continentalclub.ae/project/vista-by-vision-dubai-production-city/
- Dubai Data, Vista By Vision, data through 29 Sep 2026: https://datadubai.ae/projects/vista-by-vision/
- Vision Developments, VERDE by Vision sold out in 10 hours (Vista announcement), 28 Oct 2025: https://www.visiondevelopments.ae/blog/our-blog-1/verde-by-vision-sold-out-in-just-10-hours-vision-developments-achieves-a-new-milestone-2
- Vision Developments, VISTA by Vision sells out in just 7 hours, December 2025, posted 6 Apr 2026: https://www.visiondevelopments.ae/blog/our-blog-1/vista-by-vision-sells-out-in-just-7-hours-3
- Property Finder, Vista by Vision project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/vision-development/vista-by-vision
- OffPlanIndex, Vista by Vision, accessed 11 Oct 2026: https://offplanindex.com/projects/vision-development-vista-by-vision