# When is the Tria by Deyaar handover date?

URL: https://www.dxbrealtor.ai/answers/tria-by-deyaar-handover-date/
Topic: Handover date
Updated: 2026-10-12

## Short answer

Tria by Deyaar has been handed over. Deyaar announced on 6 October 2026 that it had handed over Tria in Dubai Silicon Oasis, 711 homes and 6 retail units, taking its 2026 deliveries above 2,100 units (Zawya press release). The registered completion date on the Dubai Land Department (DLD) register was 30 June 2025, so handover came about 16 months later. Deyaar had targeted 2025 at first, then 31 March 2026 and September 2026. The last published DLD site inspection, on 25 August 2026, recorded 94.11% complete.

## Key figures

- Registered completion date (DLD): 30 Jun 2025 (Passed. DLD register, project 2403, via fäm Properties)
- Handover: Oct 2026 (Deyaar announcement, 6 Oct 2026; 711 homes and 6 retail units)
- Last DLD construction progress: 94.11% (DLD site inspection, 25 Aug 2026)
- Date change since launch: 2025 to Oct 2026 (Deyaar, 7 Mar 2023 and 6 Oct 2026)

## Tria by Deyaar handover date: the latest position

Tria has been handed over. Deyaar announced on 6 October 2026 that it had handed over the tower's 711 homes and 6 retail units, taking its 2026 deliveries above 2,100 units (Zawya press release). The Dubai Land Department (DLD) register held 30 June 2025 as the registered completion date, and its last published site inspection, on 25 August 2026, recorded the tower 94.11% complete. Prices, sizes and the payment plan are on the [Tria by Deyaar](/projects/tria-by-deyaar/) page.

Before the announcement, Deyaar's construction update had given September 2026 as the expected completion date and said final building completion formalities had been initiated. The handover came about 16 months after the registered completion date.

## Tria by Deyaar handover date by building

Tria is a single tower, so one registered date and one progress figure cover all 717 units, which Deyaar's handover announcement gives as 711 homes and 6 retail units. The DLD register describes it as a ground floor, three podium levels and 28 residential and commercial floors.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Tria (DLD project 2403, 717 units) | 94.11%, 25 Aug 2026 (last published); handed over Oct 2026 (Deyaar) | 30 Jun 2025 (passed) | Handed over Oct 2026 (Deyaar, 6 Oct 2026); earlier Sep 2026 (Deyaar); Jun 2025 (Property Finder); Apr 2025 (Propsearch, 27 Aug 2026) |

The tower gained 0.74 points between the inspections of 3 August and 25 August 2026, from 93.37% to 94.11% (Continental Club, DLD data). The last few points usually cover finishing work, authority approvals and the building completion certificate, and Deyaar announced the handover about six weeks after the last published inspection.

## How the Tria by Deyaar handover date has changed

The date moved three times before the handover, which came more than a year after the original target.

| Date | What happened | Source |
|---|---|---|
| Jun 2022 | Tria launched for sale. | Deyaar |
| 1 Aug 2022 | DLD registered construction start, with a completion date of 30 June 2025. | DLD register, via Mitchells |
| 7 Mar 2023 | Deyaar gave 2025 as the completion target. | Deyaar project update |
| Not dated | Deyaar's Tria property page gave an end date of 31 March 2026, still shown on 1 October 2026. | Deyaar Tria page |
| 25 Aug 2026 | 94.11% complete at the DLD site inspection. | DLD register, via fäm Properties |
| Sep 2026 | Expected completion moved to September 2026. Completion formalities started. | Deyaar construction update |
| 1 Oct 2026 | September 2026 passed with no handover announced. | Deyaar; DLD register |
| 6 Oct 2026 | Deyaar announced the handover of Tria, 711 homes and 6 retail units. | Deyaar, via Zawya |

Other sources follow the same pattern: Data Habibi records a postponement from Q2 2025 to Q3 2026, while Property Finder and Propsearch still show the original 2025 dates.

## What the Tria by Deyaar handover date means for payments

Property Finder and Continental Club list a plan of 14% at launch, 35% during construction, 11% on handover and 40% after handover. On the studio launch price of AED 517,000, that is AED 56,870 at handover and AED 206,800 paid after it. Data Habibi lists a different split for some units: 12% deposit, 49% during construction, 9% at handover and 30% over 36 months after handover.

Because 40% of the price falls after handover under the main plan, the October 2026 handover sets the start of those post-handover instalments. The handover payment itself falls due once Deyaar issues its handover notice.

## What to check after the Tria by Deyaar handover

1. **The handover notice for your unit.** For Regalia, owners were formally notified once completion certificates were issued, and handover followed in April 2026 (GDN, 21 Apr 2026).
2. **The completion date and grace period in your SPA.** Older SPAs may carry the 2025 date that matches the DLD register, which matters for any delay terms.
3. **Which payment plan your contract follows**, since sources list both 14/35/11/40 and 12/49/9/30 splits, with different amounts due at handover.
4. **The DLD status of project number 2403**, through DLD's project status enquiry service, which shows whether the register has recorded the project as complete.

## Frequently asked

### What is the Tria by Deyaar completion date?

Tria was handed over in October 2026, Deyaar announced on 6 October 2026. The DLD register held 30 June 2025 as the registered completion date for project number 2403. Deyaar's earlier dates were 2025, 31 March 2026 and September 2026.

### When will Tria by Deyaar be ready?

It is ready. Deyaar announced on 6 October 2026 that it had handed over Tria, 711 homes and 6 retail units (Zawya press release).

### Is Tria by Deyaar finished?

Yes, Deyaar announced the handover on 6 October 2026. The last published DLD inspection before that recorded 94.11% complete on 25 August 2026, up from 93.37% on 3 August 2026 (Continental Club, DLD registry updated 25 Sep 2026).

### Has the Tria by Deyaar handover date been delayed?

Yes. In March 2023 Deyaar gave a 2025 completion target, and the DLD registered completion date is 30 June 2025. Deyaar's date later moved to 31 March 2026 and then to September 2026, and the handover was announced on 6 October 2026, about 16 months after the registered date.

### How much is due at the Tria handover?

Under the plan listed by Property Finder and Continental Club, 11% of the price is due on handover and 40% after handover. On the studio launch price of AED 517,000, that is AED 56,870 at handover and AED 206,800 afterwards.

## Sources

- Deyaar, construction updates of Deyaar projects in Dubai, accessed 1 Oct 2026: https://www.deyaar.ae/en/construction-update/
- Deyaar, Tria property page, accessed 1 Oct 2026: https://www.deyaar.ae/en/properties/tria/
- Deyaar, Tria project update, 7 Mar 2023: https://www.deyaar.ae/en/tria-project-update/
- fäm Properties, Tria by Deyaar completion date (DLD data), inspection 25 Aug 2026, accessed 1 Oct 2026: https://famproperties.com/completion-date/tria-by-deyaar
- Continental Club, Tria by Deyaar (DLD project registry, project 2403), registry updated 25 Sep 2026: https://continentalclub.ae/project/tria-by-deyaar-dubai-silicon-oasis/
- Mitchells Commercial Realty, Tria by Deyaar DLD registry and registered sales, status as at 8 Sep 2026: https://www.mitchellscommercialrealty.com/off-plan/tria-by-deyaar
- Property Finder, Tria by Deyaar, accessed 28 Sep 2026: https://www.propertyfinder.ae/en/new-projects/deyaar-leasing/tria-by-deyaar
- Propsearch, Tria by Deyaar, updated 27 Aug 2026: https://propsearch.ae/dubai/tria-by-deyaar
- Data Habibi, Tria floor plans and delivery dates, accessed 1 Oct 2026: https://datahabibi.ae/dubai/new-projects/tria
- GDN, Deyaar completes handover of over 1,400 residential units in Dubai, 21 Apr 2026: https://www.gdnonline.com/Details/1392215/Deyaar-completes-handover-of-over-1,400-residential-units-in-Dubai
- Zawya (Deyaar press release), Deyaar builds on its 2026 handover momentum with 711 new homes at Tria in Dubai Silicon Oasis, 6 Oct 2026: https://www.zawya.com/en/press-release/companies-news/deyaar-builds-on-its-2026-handover-momentum-with-711-new-homes-at-tria-in-dubai-silicon-oasis-1510991
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status
