# When is the Treppan Living Prive handover date?

URL: https://www.dxbrealtor.ai/answers/treppan-living-prive-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Treppan Living Prive has a registered completion date of 15 December 2028, and Fakhruddin Properties markets a Q4 2028 handover. The only DLD inspection on record, on 28 January 2026, recorded 0% complete, before the registered construction start of 1 July 2026. The date has not changed since launch, but no progress figure from after the start of works had been published by 11 October 2026.

## Key figures

- Registered completion date (DLD): 15 Dec 2028 (DLD project register via Continental Club)
- Latest construction progress: 0% (DLD inspection, 28 Jan 2026)
- Developer's stated date: Q4 2028 (Fakhruddin via Continental Club; Mira International)
- Registered construction start: 1 Jul 2026 (DLD project register via Continental Club)

## Treppan Living Prive handover date: the latest position

Treppan Living Prive has a registered completion date of 15 December 2028 in the DLD project register, and Fakhruddin Properties markets a Q4 2028 handover. Prices, sizes and payment plans are on the [Treppan Living Prive](/projects/treppan-living-prive/) page.

The only DLD inspection on record, on 28 January 2026, recorded 0% complete. It took place before the sales launch on 10 February 2026 and before the registered construction start of 1 July 2026. Until the next inspection is published, there is no official figure for how much work has been done.

## Treppan Living Prive handover date by building

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Treppan Living Prive (DLD project 4345, 65 units) | 0%, 28 Jan 2026 | 15 Dec 2028 | Q4 2028 (Continental Club, Mira International); December 2028 (Starview Niche); to be confirmed (JRE) |

The project is a single G+2P+12+R tower, so all 65 homes share one date. The register lists 1 bedroom Executive Suites of 1,029 to 1,103 sq ft, 2 bedroom Family Suites of 1,609 to 2,137 sq ft and two 4 bedroom Signature Penthouses of 3,714 to 3,769 sq ft, all sold fully furnished. Fit-out of furniture and the wellness facilities, such as the hyperbaric chamber and cryotherapy rooms, is part of what must be finished before handover. Fakhruddin's earlier Dubai Islands project, [Treppan Serenique Residences](/projects/treppan-serenique-residences/), is a separate registration with a completion date of 15 October 2027.

## How the Treppan Living Prive handover date has changed

| Date | What happened | Source |
|---|---|---|
| 28 Jan 2026 | DLD inspection records 0% | DLD register |
| 10 Feb 2026 | Fakhruddin launches Treppan Living Prive | Fakhruddin Properties |
| 1 Jul 2026 | Registered construction start | DLD register |
| Sep 2026 | Register shows completion on 15 Dec 2028 | Continental Club |
| Oct 2026 | Listings show Q4 2028 | Mira International; Starview Niche |

The date has not moved since launch. Other Dubai Islands projects carry a range of dates; the [Dubai Islands](/projects/dubai-islands/) page sets out the wider island's progress. With a registered build period of about 29 months for a 15 storey tower, the first inspection after July 2026 will show whether work started on schedule.

## What the Treppan Living Prive handover date means for payments

Most of the price is due at handover. Continental Club and Mira International show 40% on handover, and JRE, Starview Niche and Saveraah show 60%. On a 1 bedroom at AED 3,243,000, that is about AED 1.30 million or AED 1.95 million due around December 2028. No post-handover plan appears in the published sources.

## What to check before relying on the Treppan Living Prive date

1. **The completion date and grace period in the SPA** against 15 December 2028.
2. **The next DLD inspection**, the first after the registered start of works.
3. **Which payment plan the SPA uses**, since the handover share is 40% or 60%.

## Frequently asked

### When will Treppan Living Prive be completed?

The DLD register gives 15 December 2028, and Fakhruddin markets Q4 2028.

### Has construction started at Treppan Living Prive?

The register dates the construction start to 1 July 2026. The only inspection on record, on 28 January 2026, recorded 0%, and no later inspection had been published by 11 October 2026.

### Has the Treppan Living Prive handover date changed?

No change has been recorded. The project launched on 10 February 2026 and has carried a Q4 2028 date and a registered completion of 15 December 2028 since. One broker page, JRE, shows the handover as to be confirmed.

## Sources

- DLD project register via Continental Club, Treppan Living Prive, inspection 28 Jan 2026, register updated 25 Sep 2026: https://continentalclub.ae/project/treppan-living-prive-dubai-islands/
- DLD project register via Continental Club, Dubai handover 2028 tracker, accessed 11 Oct 2026: https://continentalclub.ae/handover-2028/
- Fakhruddin Properties, launch of Treppan Living Prive, 10 Feb 2026: https://www.fakhruddinproperties.com/press-release/fakhruddin-properties-introduces-john-abraham-as-global-brand-ambassador-for-treppan-living-at-launch-of-treppan-living-prive
- Mira International, Treppan Living Prive, accessed 11 Oct 2026: https://mira-international.com/properties/treppan-living-prive
- Starview Niche, Treppan Living Prive, accessed 11 Oct 2026: https://starviewniche.com/project/treppan-living-prive/
- JRE Dubai, Treppan Living Prive, accessed 11 Oct 2026: https://jre.ae/fa/projects/treppan-living-prive
- Saveraah Properties, Treppan Living Prive, accessed 11 Oct 2026: https://saveraahproperties.ae/dubai-projects/treppan-living-prive/
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status