# When is the Timez by Danube handover date?

URL: https://www.dxbrealtor.ai/answers/timez-by-danube-handover-date/
Topic: Handover date
Updated: 2026-10-01

## Short answer

The Timez by Danube handover date is 31 July 2028, the registered completion date on the Dubai Land Department (DLD) register, which matches the Q3 2028 Danube gave at the February 2025 launch. The DLD site inspection of 9 September 2026 put construction at 21.45% complete, up from 17.06% on 12 May 2026, and Danube reported 25% on 31 August 2026. Danube's own project page and Property Finder now show Q2 2028, one quarter earlier than the registered date.

## Key figures

- Registered completion date (DLD): 31 Jul 2028 (DLD register, project 3559, via Mitchells, accessed 1 Oct 2026)
- Latest construction progress: 21.45% (DLD site inspection, 9 Sep 2026. Danube reported 25% on 31 Aug 2026)
- Developer's stated date: Q2 2028 (Danube project page, accessed 1 Oct 2026. Q3 2028 at launch)
- Date change since launch: Q3 2028 to Q2 2028 (Launch release, 14 Feb 2025, to Danube's current page)

## Timez by Danube handover date: the latest position

Timez by Danube is due for completion on 31 July 2028. That is the registered completion date on the Dubai Land Department (DLD) register, and it matches the Q3 2028 Danube gave when it launched the tower on 14 February 2025. Danube's own project page and Property Finder now show Q2 2028, one quarter earlier, but Danube has not filed an earlier date with the DLD. Prices and sales figures are on the [Timez by Danube](/projects/timez-by-danube/) page.

The DLD site inspection of 9 September 2026 recorded 21.45% complete, up from 17.06% on 12 May 2026. Danube's own update of 31 August 2026 gave 25%, with shoring, piling and foundation concreting finished, the level 2 slab cast and finishing works started, and said the superstructure was ahead of schedule. To reach 31 July 2028, the remaining 78.55% would need to be built in about 23 months, a faster pace than the 4.39 points recorded between May and September 2026, which covered mostly below ground work.

## Timez by Danube handover date by building

Timez is a single 43 storey tower with two basement levels, so one date covers every unit. The DLD register lists 1,142 homes; Danube's page gives 1,000 apartments.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Timez by Danube (one tower, 1,142 homes) | 21.45%, 9 Sep 2026 | 31 Jul 2028 | Danube: Q2 2028. Property Finder: Q2 2028. Bayut and Goldpillars: Q3 2028 |

## How the Timez by Danube handover date has changed

The registered date has held. The developer's marketed date has moved one quarter earlier, while Propsearch records the change the other way round.

| Date | What happened | Source |
|---|---|---|
| 14 Feb 2025 | Danube launches Timez with handover in Q3 2028. | Danube, via Middle East Construction News |
| 1 Apr 2025 | DLD registered construction start. Registered completion 31 July 2028. | DLD register, via Mitchells |
| 12 May 2026 | 17.06% at the DLD site inspection. | DLD register, via Mitchells |
| 31 Aug 2026 | Danube reports 25% and says the project will finish well ahead of schedule. | Danube construction page |
| 9 Sep 2026 | 21.45% at the DLD site inspection. | DLD register, via Mitchells |
| 23 Sep 2026 | Propsearch shows an original Q2 2028, revised to Q3 2028. | Propsearch |
| 1 Oct 2026 | Danube's project page shows Q2 2028; registered date unchanged. | Danube; DLD register |

## What the Timez by Danube handover date means for payments

Bayut and Goldpillars describe 70% during construction and 30% on handover. Propsearch describes the 30% as paid over a set period after handover, and Danube's own page advertises instalments of 0.5% a month. On a studio at the AED 800,000 launch price, 30% is AED 240,000, due either on the handover date or spread across the months after it, depending on the plan signed. Under the first version, an earlier handover in Q2 2028 would bring that payment forward.

## What to check before relying on the Timez by Danube date

1. **Whether your SPA says Q2 2028 or 31 July 2028**, since Danube's marketing and the DLD register now differ by about a quarter.
2. **Whether the final 30% is due on handover or after it**, since sources describe both.
3. **The DLD progress for project 3559**, through DLD's project status enquiry service, to see whether the pace picks up as the superstructure rises.
4. **How an early handover affects you**, since Danube says it will finish ahead of schedule and a completion notice brings the handover payment and service charges forward.

## Frequently asked

### What is the Timez by Danube completion date?

31 July 2028 is the registered completion date on the DLD register (project 3559). Danube's launch release of 14 February 2025 gave Q3 2028, and Bayut shows the same. Danube's own project page and Property Finder now show Q2 2028.

### Is Timez by Danube finished?

No. The DLD site inspection of 9 September 2026 recorded 21.45% complete. Danube's update of 31 August 2026 gave 25%, with shoring, piling and foundations finished and the level 2 slab cast.

### When will Timez by Danube be ready?

On the registered date, by 31 July 2028. Danube says the project will be completed well ahead of schedule and its own page shows Q2 2028, but it has not filed an earlier date with the DLD.

### Has the Timez by Danube handover date been delayed?

No. The registered date of 31 July 2028 matches the Q3 2028 given at launch. Sources differ on direction: Danube's page now shows the earlier Q2 2028, while Propsearch records Q2 2028 as the original date, revised to Q3 2028 (updated 23 Sep 2026).

### How much is due at the Timez by Danube handover?

Portals describe 70% during construction and 30% on handover. Propsearch describes the 30% as paid over a period after handover instead, and Danube's own page advertises 0.5% a month, so the plan in your SPA decides how much falls due on the day.

## Sources

- Mitchell's, Timez by Danube, DLD registry and registered sales (DLD project 3559), accessed 1 Oct 2026: https://www.mitchellscommercialrealty.com/off-plan/timez-by-danube
- Danube Properties, Timez portfolio page, accessed 1 Oct 2026: https://danubeproperties.com/portfolio/timez/
- Danube Properties, Timez construction updates, 31 Aug 2026: https://danubeproperties.com/construction/timez/
- Middle East Construction News, Danube Properties unveils TIMEZ in Dubai Silicon Oasis, 14 Feb 2025: https://meconstructionnews.com/62487/danube-properties-unveils-timez-in-dubai-silicon-oasis
- Propsearch, Timez by Danube, updated 23 Sep 2026: https://propsearch.ae/dubai/timez-by-danube
- Property Finder, Timez by Danube, accessed 28 Sep 2026: https://www.propertyfinder.ae/en/new-projects/danube-properties/timez
- Bayut, Timez by Danube, accessed 28 Sep 2026: https://www.bayut.com/buildings/timez-by-danube/
- Goldpillars, Danube Timez payment plan, accessed 28 Sep 2026: https://www.goldpillars.ae/project/danube-timez-payment-plan
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status