# When is The Orchard Place handover date?

URL: https://www.dxbrealtor.ai/answers/the-orchard-place-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Towers A and B at The Orchard Place had a registered completion date of 31 July 2026, which has passed, and Tower C is registered for 31 March 2027. The latest DLD inspections recorded Towers A and B at 42.68% on 11 March 2026 and Tower C at 13% on 7 May 2026. No revised date for Towers A and B had been published by 11 October 2026, and broker listings already show Q4 2027 for Tower C.

## Key figures

- Towers A and B, registered completion (DLD): 31 Jul 2026 (passed) (DLD project register via Continental Club)
- Towers A and B, latest progress: 42.68% (DLD inspection, 11 Mar 2026)
- Tower C, registered completion (DLD): 31 Mar 2027 (13% built at the 7 May 2026 DLD inspection)
- Tower C, broker date: Q4 2027 (Dubainary; Lucretia gives 1 Dec 2027)

## The Orchard Place handover date: the latest position

The Orchard Place has two registered completion dates. Towers A and B were registered for 31 July 2026, and that date has passed with the towers unfinished. Tower C is registered for 31 March 2027. Prices, sizes and payment plans are on [The Orchard Place](/projects/the-orchard-place/) page.

The last DLD inspection of Towers A and B, on 11 March 2026, recorded 42.68% complete. Dubai Handover's daily copy of the register still showed 31 July 2026 on 9 October 2026, so no new date has been filed. A passed registered date does not mean the towers were handed over. It means the record has not yet been changed.

## The Orchard Place handover date by building

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Towers A and B (DLD project 2629, 418 units) | 42.68%, 11 Mar 2026 | 31 Jul 2026 (passed) | Q3 2026 (Property Finder; Continental Club) |
| Tower C (196 units) | 13%, 7 May 2026 | 31 Mar 2027 | Q4 2027 (Dubainary); 1 Dec 2027 (Lucretia) |

Towers A and B share one registration, so their DLD progress figure covers both. Peak Summit's own update reported the structure 96% complete in each tower by September 2025, with MEP works 90% done to the 25th floor in Tower B. Tower C is a separate registration with its own escrow and date. Data Habibi gives Tower C 191 units and Khaleej Times 193; the register lists 196.

## How The Orchard Place handover date has changed

| Date | What happened | Source |
|---|---|---|
| 31 Jul 2023 | Towers A and B sales open; construction start registered; completion registered for 31 Jul 2026 | Property Finder; DLD register |
| 9 Jun 2024 | Tower C launched with a Q4 2026 handover target, from AED 687,000 | Khaleej Times |
| Jun 2024 | Tower C construction starts | Data Habibi |
| 12 Nov 2025 | Developer reports structure 96% complete in Towers A and B | Peak Summit |
| 11 Mar 2026 | DLD inspection records Towers A and B at 42.68% | DLD register |
| 7 May 2026 | DLD inspection records Tower C at 13%; registered date 31 Mar 2027 | DLD register |
| 31 Jul 2026 | Registered date for Towers A and B passes | DLD register |
| Oct 2026 | Tower C marketed for Q4 2027 | Dubainary; Lucretia |

Tower C's date has moved from Q4 2026 at launch to 31 March 2027 in the register and Q4 2027 in current listings, a slip of about a year. Towers A and B have not yet been given a public replacement for July 2026.

## What The Orchard Place handover date means for payments

On Towers A and B, 40% of the price is due on handover under the 60/40 plan, so that payment has not yet fallen due. On a 1 bedroom sold at AED 1,247,634 in May 2026, 40% is about AED 499,000. Tower C's main plan puts 10% on handover and 30% over 30 months after it (Data Habibi), so a later handover also delays the end of the post-handover instalments.

## What to check before relying on The Orchard Place date

1. **Whether the unit is in Towers A and B or Tower C**, since the registered dates are eight months apart.
2. **The SPA's completion date and grace period for Towers A and B**, now that 31 July 2026 has passed, and any written revised date from Peak Summit.
3. **The next DLD inspection of Towers A and B**, the first since March 2026.
4. **Tower C's SPA date** against the March 2027 register date and the Q4 2027 broker date.

## Frequently asked

### Is The Orchard Place finished?

No. Towers A and B were 42.68% complete at the DLD inspection of 11 March 2026, and Tower C was 13% complete on 7 May 2026.

### Has The Orchard Place handover date been delayed?

Towers A and B passed their registered completion date of 31 July 2026 without being finished, and no new date had been registered by 11 October 2026. Tower C launched with a Q4 2026 target (Khaleej Times, June 2024), is registered for 31 March 2027 and is now marketed for Q4 2027.

### When will The Orchard Place Tower C be completed?

The DLD register gives 31 March 2027. Broker listings give Q4 2027, and Lucretia gives 1 December 2027. Tower C was 13% built on 7 May 2026.

### What is The Orchard Place completion date for Tower A and Tower B?

Both towers sit under one DLD registration with a completion date of 31 July 2026, now passed. Peak Summit reported the structure 96% complete in both towers in its September 2025 update.

## Sources

- DLD project register via Continental Club, The Orchard Place, inspection 11 Mar 2026, accessed 11 Oct 2026: https://continentalclub.ae/project/the-orchard-place-jvc-district-12/
- DLD project register via Continental Club, Dubai handover 2026 tracker, accessed 11 Oct 2026: https://continentalclub.ae/handover-2026/
- DLD project register via Continental Club, Dubai handover 2027 tracker (Tower C, inspection 7 May 2026), accessed 11 Oct 2026: https://continentalclub.ae/handover-2027/
- Dubai Handover, The Orchard Place, snapshot 9 Oct 2026: https://dubaihandover.com/projects/2629-the-orchard-place
- Property Finder, The Orchard Place project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/peak-summit-real-estate-development-l-l-c/the-orchard-place
- The Orchard Place, construction update September 2025 (Tower A and B), 12 Nov 2025: https://theorchardplace.ae/en/news/construction-update-september-2025-tower-a-and-b
- Khaleej Times, Peak Summit Development launches Tower C at The Orchard Place, 9 Jun 2024: https://www.khaleejtimes.com/business/property/peak-summit-development-launches-tower-c-at-the-orchard-place-in-dubais-jvc
- Data Habibi, The Orchard Place Tower C, accessed 11 Oct 2026: https://datahabibi.ae/dubai/new-projects/the-orchard-place-tower-c
- Dubainary, The Orchard Place Tower C, accessed 11 Oct 2026: https://dubainary.com/off-plan/peak-summit-real-estate-development-the-orchard-place-tower-c
- Lucretia International, The Orchard Place Tower C, accessed 11 Oct 2026: https://www.lucretia-international.com/en/projects/orchard-the-orchard-place-tower-c
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status