# When is The Chedi Private Residences handover date?

URL: https://www.dxbrealtor.ai/answers/the-chedi-private-residences-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

The Chedi Private Residences has a registered completion date of 28 February 2029, and Al Seeb gives Q1 2029. The latest DLD inspection, on 8 September 2026, recorded 2.61% complete, up from 1.42% on 12 May 2026. Main construction only began with the contractor award in August 2026, so the pace of the next inspections will show whether the date holds.

## Key figures

- Registered completion date (DLD): 28 Feb 2029 (DLD project register via Continental Club)
- Latest construction progress: 2.61% (DLD inspection, 8 Sep 2026)
- Developer's stated date: Q1 2029 (Al Seeb via Middle East Construction News, 3 Aug 2026)
- Date given at launch: 2029 (The Chedi Hotels, 12 Feb 2025)

## The Chedi Private Residences handover date: the latest position

The DLD project register holds a registered completion date of 28 February 2029 for The Chedi Private Residences, and Al Seeb's own target is the first quarter of 2029. Prices, sizes and the payment plan are on [The Chedi Private Residences](/projects/the-chedi-private-residences/) page.

The latest DLD inspection, on 8 September 2026, recorded 2.61% complete. The tower only moved into main construction when Ancient Builders Constructions was appointed in August 2026. At that point, piling, shoring and excavation were under way (Middle East Construction News, 3 August 2026).

## The Chedi Private Residences handover date by building

The project is one tower, registered as DLD project 3323 with 118 units.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| The Chedi Private Residences tower | 2.61%, 8 Sep 2026 | 28 Feb 2029 | Q1 2029 (Al Seeb, Aug 2026); Feb 2029 (Propsearch, 26 Sep 2026) |

The tower rises about 240 metres on Sheikh Zayed Road, with homes from 2 bedroom sky villas of about 3,556 sq ft up to multi-level mansions. All of them share the one registered date. The contract award report counted 117 residences, one fewer than the register.

## How The Chedi Private Residences handover date has changed

| Date | What happened | Source |
|---|---|---|
| 6 to 12 Feb 2025 | Launch showcase in Downtown Dubai; completion given as 2029 | The Chedi Hotels |
| 1 Mar 2025 | Construction start registered | DLD register |
| 12 May 2026 | DLD inspection records 1.42% | DLD register |
| 3 Aug 2026 | Main contract awarded to ABC; completion due Q1 2029 | Middle East Construction News |
| 8 Sep 2026 | DLD inspection records 2.61% | DLD register |

The date has not moved since launch. The concern is pace rather than a revision. Progress rose 1.19 points between May and September 2026. To reach completion by 28 February 2029, the remaining 97.39 points must be built in under 30 months, which is over 3 points a month.

## What The Chedi Private Residences handover date means for payments

Under the plan published by Tanami Properties, 55% is paid before handover, 10% on handover and 35% in instalments over the 30 months after handover. Three of the construction instalments are tied to progress (50%, 60% and 70% complete), so they fall due only as the tower rises. On a 2 bedroom at the DLD median of AED 6,499,076, the handover payment is about AED 650,000 and the post-handover share about AED 2.27 million (Continental Club, register updated 5 October 2026). A later handover also pushes the post-handover instalments into 2031 or beyond.

## What to check before relying on The Chedi Private Residences date

1. **The completion date and grace period in the SPA**, compared with 28 February 2029 in the register.
2. **The next two DLD inspections**, which will show whether main construction under ABC has lifted the pace above 3 points a month.
3. **How the post-handover instalments are dated in the SPA**, whether from the handover date or fixed calendar dates.

## Frequently asked

### When will The Chedi Private Residences be completed?

The registered completion date in the DLD project register is 28 February 2029. Al Seeb said in August 2026 that the tower is scheduled for completion in the first quarter of 2029.

### How far along is construction at The Chedi Private Residences?

2.61% complete at the DLD inspection on 8 September 2026, up from 1.42% on 12 May 2026. Piling, shoring and excavation were under way when the main contract was awarded in August 2026.

### Has The Chedi Private Residences handover date been delayed?

No. The launch release in February 2025 gave 2029, and the developer, the register and Propsearch all still point to February or Q1 2029.

### Who is building The Chedi Private Residences?

Ancient Builders Constructions (ABC) is the main contractor, appointed in August 2026, with MBM Gulf Electromechanical on MEP and Model Engineering Consultants as lead consultant (Middle East Construction News, 3 Aug 2026).

## Sources

- DLD project register via Continental Club, The Chedi Private Residences, inspection 8 Sep 2026, register updated 5 Oct 2026: https://continentalclub.ae/project/the-chedi-private-residences-barsha-heights/
- DLD project register via Continental Club, Dubai handover 2029 tracker, accessed 11 Oct 2026: https://continentalclub.ae/handover-2029/
- Middle East Construction News, Al Seeb awards main contract for Chedi Private Residences, 3 Aug 2026: https://meconstructionnews.com/?p=68578
- The Chedi Hotels, Al Seeb partners with Devmark to launch The Chedi Private Residences, 12 Feb 2025: https://www.chedihotels.com/news/al-seeb-partners-with-devmark-to-launch-the-chedi-private-residences/
- Propsearch, The Chedi Private Residences, updated 26 Sep 2026: https://propsearch.ae/dubai/the-chedi-private-residences
- Tanami Properties, The Chedi Private Residences payment plan, accessed 11 Oct 2026: https://www.tanamiproperties.com/Projects/The-Chedi-Private-Residences-PaymentPlan
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status