# When is The Boulevard by Prestige One handover date?

URL: https://www.dxbrealtor.ai/answers/the-boulevard-by-prestige-one-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

The Boulevard by Prestige One has a registered completion date of 30 November 2027, and Prestige One's current date is Q1 2028. The DLD inspection on 23 September 2026 recorded 10.57% complete. The date has already moved from the Q3 2027 quoted in 2025, and at the pace seen in mid 2026 the tower would not be finished by Q1 2028 either.

## Key figures

- Registered completion date (DLD): 30 Nov 2027 (DLD project register via Continental Club)
- Latest construction progress: 10.57% (DLD inspection, 23 Sep 2026)
- Developer's stated date: Q1 2028 (Propsearch, 6 Mar 2026; Continental Club)
- Date quoted in 2025: Q3 2027 (Property Finder listing, 22 Nov 2025)

## The Boulevard by Prestige One handover date: the latest position

Prestige One's current handover date for The Boulevard is Q1 2028, and Property Finder lists January 2028. The DLD project register holds a registered completion date of 30 November 2027. Prices, sizes and the payment plans are on [The Boulevard by Prestige One](/projects/the-boulevard-by-prestige-one/) page.

The latest DLD inspection, on 23 September 2026, recorded 10.57% complete. With 14 months to the registered date and 18 months to the end of Q1 2028, almost nine tenths of the building remains to be built.

## The Boulevard by Prestige One handover date by building

The Boulevard is one tower, registered as DLD project 3428 with 387 units.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| The Boulevard by Prestige One | 10.57%, 23 Sep 2026 | 30 Nov 2027 | Q1 2028 (Propsearch; Continental Club); January 2028 (Property Finder); Q4 2027 (ezre.ae) |

## How The Boulevard by Prestige One handover date has changed

| Date | What happened | Source |
|---|---|---|
| 25 Dec 2024 | Prestige One publishes its project page | Prestige One |
| 1 Jul 2025 | Bookings and registered construction start | Property Finder; DLD register |
| 22 Nov 2025 | Agent listing quotes Q3 2027 handover | Property Finder |
| 6 Mar 2026 | Propsearch shows Q1 2028 | Propsearch |
| 23 Jun 2026 | Inspection records about 4.82% | DLD register |
| 23 Sep 2026 | Inspection records 10.57% | DLD register |

The marketed date has moved from Q3 2027 to Q1 2028, and the registered date of 30 November 2027 sits between them. Progress has picked up, from under 5% in the first year to 5.75 points in the three months to September 2026. Even so, at about 1.9 points a month the remaining 89% would take close to four years. To finish by 31 March 2028 the pace would need to reach about 5 points a month.

## What The Boulevard by Prestige One handover date means for payments

The amount due at handover depends on the plan. On the post-handover plan, buyers pay 20% on booking, 35% during construction and 10% on handover, then 35% over 35 months, so a later handover also delays the monthly payments that follow it. On the standard plan, 45% is paid in instalments every three months from booking and 35% is due on completion (offplans.com). Under that plan, the construction instalments run from 3 to 24 months after booking, on fixed dates, and fall due well before the tower is finished.

## What to check before relying on The Boulevard by Prestige One date

1. **The date in the SPA.** Buyers who booked in 2025 may hold contracts or marketing material quoting Q3 2027.
2. **The grace period** the SPA allows after the completion date, given the gap between progress and the registered date.
3. **The next DLD inspection.** A pace near 5 points a month is needed to reach Q1 2028.

## Frequently asked

### When will The Boulevard by Prestige One be completed?

The registered completion date is 30 November 2027. Prestige One's current date is Q1 2028, and Property Finder shows January 2028. The tower was 10.57% complete on 23 September 2026.

### Has The Boulevard by Prestige One handover been delayed?

Yes. Listings and portals in 2025 quoted Q3 2027. The current developer date is Q1 2028, about two quarters later, and the registered date is 30 November 2027.

### How fast is construction moving at The Boulevard?

Progress rose from about 4.82% on 23 June 2026 to 10.57% on 23 September 2026 (DLD project register via Continental Club), about 1.9 points a month. Construction started on 1 July 2025.

### Is The Boulevard by Prestige One finished?

No. It was 10.57% complete at the DLD inspection on 23 September 2026.

## Sources

- DLD project register via Continental Club, Dubai handover 2027 tracker (The Boulevard by Prestige One, inspection 23 Sep 2026), accessed 11 Oct 2026: https://continentalclub.ae/handover-2027/
- DLD project register via Continental Club, The Boulevard by Prestige One (project 3428), register updated 5 Oct 2026: https://continentalclub.ae/project/the-boulevard-by-prestige-one-dubailand-residence-complex/
- Propsearch, The Boulevard by Prestige One, updated 6 Mar 2026: https://propsearch.ae/dubai/the-boulevard-by-prestige-one
- Property Finder, The Boulevard project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/prestige-one-developments/the-boulevard-by-prestige-one
- Property Finder, agent listing in The Boulevard by Prestige One (Q3 2027 handover), 22 Nov 2025: https://www.propertyfinder.ae/en/plp/buy/apartment-for-sale-dubai-dubai-land-residence-complex-the-boulevard-by-prestige-one-117248560.html
- Everhomes, The Boulevard by Prestige One, accessed 11 Oct 2026: https://everhomes.ae/off-plan/the-boulevard/
- Prestige One Developments, The Boulevard project page, published 25 Dec 2024, accessed 11 Oct 2026: https://prestigeone.ae/projects/the-boulevard-by-prestige-one/
- offplans.com, The Boulevard payment plans, accessed 11 Oct 2026: https://offplans.com/project/prestige-one-the-boulevard-by-prestige-one
- ezre.ae, The Boulevard payment plan, accessed 11 Oct 2026: https://ezre.ae/projects/the-boulevard/payment-plan
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status
