# When is the Terra Golf Collection handover date?

URL: https://www.dxbrealtor.ai/answers/terra-golf-collection-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Terra Golf Collection has a registered completion date of 31 December 2027 at the Dubai Land Department (DLD), and current listings give Q4 2027. The DLD inspection on 1 September 2026 recorded 20.05% complete. Earlier listings gave June 2027 and Q2 2027, so the expected handover has moved back by about six months.

## Key figures

- Registered completion date (DLD): 31 Dec 2027 (DLD project 2877, via Continental Club)
- Latest construction progress: 20.05% (DLD inspection, 1 Sep 2026)
- Current listing date: Q4 2027 (JRE Dubai; Projects Scout)
- Earlier date: Q2 2027 (Propsearch, at contractor appointment, Jul 2025; June 2027 on Kredium)

## Terra Golf Collection handover date: the latest position

Terra Golf Collection, Taraf's gated group of 6 bedroom villas and townhouses in Jumeirah Golf Estates, has a registered completion date of 31 December 2027 at the Dubai Land Department (DLD). Current listings give Q4 2027. Full project details are on the [Terra Golf Collection](/projects/terra-golf-collection/) page.

The DLD inspection on 1 September 2026 recorded 20.05% complete (DLD project register via Continental Club, inspection 1 September 2026). Earlier dates were sooner: June 2027 on a launch-era listing and Q2 2027 when the main contractor was appointed in July 2025.

## Terra Golf Collection handover date by building

DLD files the whole collection as one project, number 2877, with 66 registered homes on 18 plots.

| Release | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Terra Golf Collection (DLD project 2877) | 20.05%, 1 Sep 2026 | 31 Dec 2027 | Q4 2027 (Projects Scout); June 2027 on earlier listing (Kredium) |
| Phase 2 release, 20 furnished villas | 6.64% on JRE Dubai, undated | Not filed separately in the DLD extract | Q4 2027 (JRE Dubai) |

## How the Terra Golf Collection handover date has changed

| Date | Event | Source |
|---|---|---|
| 14 Dec 2023 | Launch of 84 homes in Jumeirah Golf Estates | Taraf |
| Launch period | Listed handover June 2027; townhouses from AED 7.24 million | Kredium |
| 31 Mar 2024 | Construction start on the DLD register; completion date 31 Dec 2027 | Mitchells (DLD) |
| Jul 2025 | Al Firas General Contracting appointed main contractor; handover Q2 2027 | Propsearch |
| 21 Aug 2025 | Taraf guide gives 77 units and a 60/40 plan | Taraf |
| 1 Sep 2026 | DLD inspection: 20.05% | DLD via Continental Club |
| Oct 2026 | Listings give Q4 2027 | JRE Dubai; Projects Scout |

The registered date sits about six months after the mid 2027 date in early marketing. With 20.05% done 29 months after the registered start, about 80% of the work falls in the final 16 months.

## What the Terra Golf Collection handover date means for payments

On the launch plan, 40% of the price is due on handover, after 10% down, two further 10% payments in the first six months, and 10% each at 30%, 40% and 50% construction (Kredium). With DLD at 20.05% in September 2026, the 30% milestone had not yet been reached on DLD's figure. The phase 2 release puts 50% on handover (JRE Dubai). On a home of about AED 15 million, 40% at handover is about AED 6 million.

## What to check before relying on the Terra Golf Collection date

1. **The date written in the SPA.** Early marketing gave mid 2027, so the date in an SPA can differ from the 31 December 2027 on the register.
2. **The construction milestones.** Three instalments on the launch plan are tied to 30%, 40% and 50% progress, so the DLD inspection figure sets their timing.
3. **The release and plot.** Phase 2 villas have a different payment split, and DLD records the plot rather than the built-up area.

## Frequently asked

### Is Terra Golf Collection finished?

No. The DLD inspection on 1 September 2026 recorded 20.05% complete, and the register listed it as under construction on 4 October 2026 (Mitchells).

### What is the Terra Golf Collection completion date?

31 December 2027, the completion date on file at DLD for project 2877. Construction started on 31 March 2024 on the register.

### Has the Terra Golf Collection handover date been delayed?

The expected date has moved. A launch-era listing gave June 2027 (Kredium) and Propsearch recorded Q2 2027 in July 2025. Current listings give Q4 2027 and the register holds 31 December 2027.

### When will Terra Golf Collection phase 2 be ready?

JRE Dubai lists the phase 2 release of 20 furnished villas with a Q4 2027 handover and 6.64% progress, without a date for that reading. The DLD extract for Terra Golf Collection shows one project with one completion date, 31 December 2027.

## Sources

- DLD project register via Continental Club, Dubai handovers 2027 (CC BY 4.0), inspection 1 Sep 2026: https://continentalclub.ae/handover-2027/
- Mitchells Commercial Realty, Terra Golf Collection DLD registry, registry as at 4 Oct 2026: https://www.mitchellscommercialrealty.com/off-plan/terra-golf-collection
- Taraf Holding, Taraf unveils Terra Golf Collection, 14 Dec 2023: https://www.tarafholding.com/en/en-news/taraf-unveils-terra-golf-collection-luxury-villas-in-jumeirah-golf-estates
- Taraf Holding, Investing in Jumeirah Golf Estates villas, 21 Aug 2025: https://www.tarafholding.com/en/en-news/investing-in-jumeirah-golf-estates-villas
- Propsearch, Terra Golf Collection, updated 26 Mar 2026: https://propsearch.ae/dubai/terra-golf-collection
- Kredium, Terra Golf Collection, accessed 11 Oct 2026: https://www.kredium.ae/off-plan-properties/view/project/terra-golf-collection
- JRE Dubai, Terra Golf Collection Phase 2, accessed 11 Oct 2026: https://jre.ae/projects/terra-golf-collection-phase-2
- Projects Scout, Terra Golf Collection, accessed 11 Oct 2026: https://www.projectsscout.com/ae/en/project/taraf-properties/terra-golf-collection