# When is the Taraf 3 Residence handover date?

URL: https://www.dxbrealtor.ai/answers/taraf-3-residence-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Taraf 3 Residence has a registered completion date of 31 March 2028 at the Dubai Land Department (DLD), and Property Finder lists Q1 2028. The DLD inspection on 5 May 2026 recorded 5.88% complete, up from no recorded progress on 9 November 2025. Some brokers quote Q3 2028, so the date in the SPA is the one that applies.

## Key figures

- Registered completion date (DLD): 31 Mar 2028 (DLD project 4192, via Continental Club)
- Latest construction progress: 5.88% (DLD inspection, 5 May 2026)
- Portal date: Q1 2028 (Property Finder, accessed 11 Oct 2026)
- Other broker date: Q3 2028 (Driven Properties; Grand Reve Realty)

## Taraf 3 Residence handover date: the latest position

Taraf 3 Residence, a 151 unit apartment building in Jumeirah Village Circle (JVC) District 10, has a registered completion date of 31 March 2028 at the Dubai Land Department (DLD). Property Finder lists the same date and a Q1 2028 handover. Full project details are on the [Taraf 3 Residence](/projects/taraf-3-residence/) page.

The DLD inspection on 5 May 2026 recorded 5.88% complete (DLD project register via Continental Club, inspection 5 May 2026). An earlier inspection on 9 November 2025 had recorded no progress. Some brokers quote Q3 2028, later than the register.

## Taraf 3 Residence handover date by building

Taraf 3 Residence is a single building, filed with DLD as one project.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Taraf 3 Residence (DLD project 4192, 151 units) | 5.88%, 5 May 2026 | 31 Mar 2028 | Q1 2028 (Property Finder); Q3 2028 (Driven Properties, Grand Reve) |

## How the Taraf 3 Residence handover date has changed

| Date | Event | Source |
|---|---|---|
| 18 Nov 2019 | Land purchase registered against the project | Continental Club (DLD) |
| 1 Nov 2025 | Booking opens from AED 760,400; construction start on the DLD register; completion date 31 Mar 2028 | Property Finder; Mitchells (DLD) |
| 9 Nov 2025 | DLD inspection: no progress recorded | Continental Club |
| 20 Nov 2025 | Launch date recorded by fäm Properties, handover 31 Mar 2028 | fäm Properties |
| 5 May 2026 | DLD inspection: 5.88% | DLD via Continental Club |
| Oct 2026 | Register unchanged at 31 Mar 2028; brokers quote Q1 or Q3 2028 | Mitchells; Property Finder; Driven Properties |

The registered date has not changed since construction started. The register allows about 29 months from start to completion for a building of a basement, ground floor, four podium parking levels and 13 residential floors (CVTEC). The May 2026 reading came six months in, leaving about 94% of the work for the remaining 23 months.

## What the Taraf 3 Residence handover date means for payments

Brokers list a 40/60 plan, with 60% of the price due on handover (Driven Properties; Grand Reve Realty). The dates of the 40% paid before handover are not published. Because most of the price is tied to completion, a later handover also delays the largest payment. On a launch-price studio of AED 760,400, the 60% handover payment is about AED 456,000; on a 2 bedroom registered at AED 1.82 million in December 2025, it is about AED 1.09 million. Payments go into the project escrow account at First Abu Dhabi Bank (Mitchells).

## What to check before relying on the Taraf 3 Residence date

1. **Which date the SPA states.** The register holds 31 March 2028; Q3 2028 on some broker pages would be six months later.
2. **The grace period.** With 5.88% recorded in May 2026, any delay would run into the SPA's grace period.
3. **The latest DLD inspection.** No reading after 5 May 2026 appeared in the register extract of 4 October 2026.

## Frequently asked

### Is Taraf 3 Residence finished?

No. The DLD inspection on 5 May 2026 recorded 5.88% complete, and the register still listed it as under construction on 4 October 2026 (Mitchells).

### What is the Taraf 3 Residence completion date?

31 March 2028, the completion date on file at DLD for project 4192. Property Finder gives the same date as its expected completion.

### Has the Taraf 3 Residence handover date been delayed?

Not on the register. The 31 March 2028 date has been on file since construction started on 1 November 2025. Broker pages quoting Q3 2028 differ from the register rather than reflecting a change.

### How long is left until Taraf 3 Residence is completed?

From the May 2026 inspection, about 23 months remained to the registered date, with about 94% of the work still to do on DLD's figure.

## Sources

- DLD project register via Continental Club, Dubai handovers 2028 (CC BY 4.0), inspection 5 May 2026: https://continentalclub.ae/handover-2028/
- Continental Club, Taraf 3 Residence (DLD inspections), accessed 11 Oct 2026: https://continentalclub.ae/project/taraf-3-residence-jumeirah-village-circle/
- Mitchells Commercial Realty, Taraf 3 Residence DLD registry, registry as at 4 Oct 2026: https://www.mitchellscommercialrealty.com/off-plan/taraf-3-residence
- Property Finder, Taraf 3 Residence project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/taraf-properties/taraf-3-residence
- Driven Properties, Taraf 3 Residence, accessed 11 Oct 2026: https://www.drivenproperties.com/dubai/off-plan-projects/taraf-3-residence-jvc
- Grand Reve Realty, Taraf 3 Residence, accessed 11 Oct 2026: https://grandreverealty.com/projects/taraf-3-residence-at-jvc/
- CVTEC Engineering Consultants, Taraf 3, accessed 11 Oct 2026: http://www.cvtec.ae/projects/taraf-3/
- fäm Properties, Taraf 3 Residence, accessed 11 Oct 2026: https://famproperties.com/jumeirah-village-circle-dubai/taraf-3-residence