# When is the Solanki One handover date?

URL: https://www.dxbrealtor.ai/answers/solanki-one-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Solanki One has a registered completion date of 30 May 2028 on the Dubai Land Department (DLD) register, and the developer gives Q2 2028. The building was 35.17% complete at the last DLD inspection on 14 September 2026, up from 21.68% on 19 May 2026. At that pace it would finish around April 2028, but this is a single building at an early stage and the next inspections will show whether the pace holds.

## Key figures

- Registered completion date (DLD): 30 May 2028 (DLD register via Continental Club)
- Latest construction progress: 35.17% (DLD inspection, 14 Sep 2026)
- Developer's stated date: Q2 2028 (Developer supplied, via Continental Club)
- Portal estimate: 30 May 2028 (Property Finder, accessed 11 Oct 2026)

## Solanki One handover date: the latest position

The DLD register gives Solanki One a registered completion date of 30 May 2028, and the developer, Solanki Realty, gives Q2 2028. At the last DLD inspection, on 14 September 2026, the building was 35.17% complete. Prices, sizes and the plan are on the [Solanki One](/projects/solanki-one/) page.

The date has not changed since launch. Between May and September 2026 the building gained 13.49 points, about 3.4 points a month. Finishing by 30 May 2028 needs about 3.2 points a month from September 2026, so the recent pace is slightly ahead of schedule.

## Solanki One handover date by building

Solanki One is a single building with a basement, ground floor, 12 residential floors and a roof, listed on the register as "Solanki One" (project 3776).

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Solanki One (133 units) | 35.17% (14 Sep 2026) | 30 May 2028 | Q2 2028 (developer); 30 May 2028 (Property Finder) |

The previous inspection, on 19 May 2026, recorded 21.68% (Continental Club). At the recorded pace, the remaining 64.83 points would take about 19 months from September 2026, to around April 2028. This is a calculation from DLD figures, not a developer forecast. The 133 units are 24 studios, 84 one bedroom, 23 two bedroom and 2 three bedroom apartments. All 66 sales registered since 2025 were from the developer (Continental Club).

## How the Solanki One handover date has changed

- **2024:** first trace of the project in public records (Propsearch).
- **30 May 2025:** sales start, with expected completion on 30 May 2028 (Property Finder). DLD registers construction from the same day.
- **19 May 2026:** DLD inspection records 21.68%.
- **14 September 2026:** DLD inspection records 35.17%.
- **October 2026:** the registered date is unchanged at 30 May 2028.

## What the Solanki One handover date means for payments

Under the main plan, buyers pay 10% on booking, 60% during construction and 30% on handover (Continental Club; Property Finder). A second option on Property Finder moves most of the final share past completion: 10% on booking, 50% during construction, 10% on handover and 30% after handover. For a 1 bedroom at the DLD median of AED 786,240, the handover payment is AED 235,872 under the first plan or AED 78,624 under the second. For a studio at the median of AED 542,520, it is AED 162,756 under the first plan.

## What to check before relying on the Solanki One date

1. **Which of the two plans the SPA uses**, since the handover payment differs by a factor of three.
2. **The completion date and grace period in the SPA**, compared with the registered 30 May 2028.
3. **Whether construction instalments follow DLD progress or fixed dates**, given the 60% or 50% share during construction.
4. **The next DLD inspection for project 3776**, to confirm the pace above 3 points a month has held.

## Frequently asked

### Is Solanki One finished?

No. It was 35.17% complete at the DLD inspection on 14 September 2026, with a registered completion date of 30 May 2028.

### What is the Solanki One completion date?

30 May 2028 is the registered completion date (project 3776). The developer gives Q2 2028, and Property Finder and Propsearch give the same timing.

### Has the Solanki One handover date been delayed?

No. The date has been 30 May 2028 since sales and construction started on 30 May 2025, and progress between May and September 2026 ran slightly ahead of the pace the date needs.

### How much is due at the Solanki One handover?

Under the main plan, 30% is due on handover. Property Finder also lists a plan with 10% on handover and 30% after it.

## Sources

- Continental Club, Solanki One (DLD project register, project 3776), inspection 14 Sep 2026, accessed 11 Oct 2026: https://continentalclub.ae/project/solanki-one-dubailand-residence-complex/
- Continental Club, Dubai handovers in 2028 (DLD project register), accessed 11 Oct 2026: https://continentalclub.ae/handover-2028/
- Property Finder, Solanki One by Solanki Realty, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/solanki-realty/solanki-one
- Propsearch, Solanki One, accessed 11 Oct 2026: https://propsearch.ae/dubai/solanki-one
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status