# When is the Sol Levante handover date?

URL: https://www.dxbrealtor.ai/answers/sol-levante-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Sol Levante has a registered completion date of 15 September 2028, and SOL Properties gives Q3 2028. The last Dubai Land Department inspection, on 6 July 2026, recorded the tower 7.19% complete. The date has not changed since launch, but progress of about 0.7 points a month will need to rise to about 3.5 points a month to meet it.

## Key figures

- Registered completion date: 15 Sep 2028 (DLD project register via Continental Club)
- Latest construction progress: 7.19% (DLD inspection, 6 Jul 2026)
- Developer's stated date: Q3 2028 (SOL Properties, via Zawya (Apr and Aug 2025) and project site)
- Change since launch: None (Q3 2028 given since April 2025)

## Sol Levante handover date: the latest position

Sol Levante is registered with the Dubai Land Department (DLD) for completion on 15 September 2028. At the last DLD inspection, on 6 July 2026, the tower was 7.19% complete. Prices, sizes and the payment plan are on the project page: [Sol Levante](/projects/sol-levante/).

SOL Properties gives Q3 2028, and its project site places the 50% handover payment in that quarter. Between September 2025 and July 2026 the tower gained 6.99 points, about 0.7 points a month. Finishing by 15 September 2028 would need about 3.5 points a month for the 26 months that remain.

## Sol Levante handover date by building

Sol Levante is one tower, registered as "Sol Levante" in JVT District 1 (DLD project 3642) by SOL Properties.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Sol Levante (674 units: homes, offices and shops) | 7.19% (6 Jul 2026) | 15 Sep 2028 | Q3 2028 (SOL Properties; Property Finder) |

The building combines four office podium levels, retail and 20 residential floors (Zawya, August 2025). One registered date covers all of them.

## How the Sol Levante handover date has changed

| Date | Event | Source |
|---|---|---|
| 17 Mar 2025 | Launch with 612 homes, offices and retail; AED 1 billion GDV | Zawya |
| 15 Apr 2025 | SOL Properties says handover slated for Q3 2028; contractor to be appointed in three to four months | Zawya Projects |
| 15 Jun 2025 | Construction starts; completion registered for 15 Sep 2028 | DLD via Continental Club |
| 5 Aug 2025 | Q3 2028 repeated; 600 homes, studios from AED 736,000 | Zawya |
| 3 Sep 2025 | DLD inspection: about 0.2% (implied by the later gain) | DLD via Continental Club |
| 6 Jul 2026 | DLD inspection: 7.19% | DLD via Continental Club |
| 25 Sep 2026 | Latest registered sale, a 1 bedroom at AED 1,372,400 | DLD via Continental Club |

The date has held since the first public statement. The schedule gives about 39 months from the start of construction to the registered date. Just over a year in, 7.19% is recorded, which leaves most of the work for the last 26 months.

## What the Sol Levante handover date means for payments

The project site lists 10% on booking, 10% plus the 4% DLD fee within 30 days, 30% during construction and 50% on handover. Offplans.com shows the 30% as four payments of 7.5% every six months, which are time-based rather than tied to progress. The 50% handover payment moves with completion. On the median 1 bedroom price of AED 1,361,000, that is about AED 680,500. On a studio at the median AED 788,000, it is AED 394,000.

## What to check before relying on the Sol Levante date

1. **The SPA completion date and grace period**, against the registered 15 September 2028.
2. **The instalment schedule in the SPA.** Brokers describe the construction payments as fixed six-monthly amounts.
3. **Mortgage timing for the 50% payment**, since a bank offer may need renewing if completion moves past Q3 2028.
4. **The next DLD inspection.** The last published reading is from 6 July 2026.

## Frequently asked

### Is Sol Levante finished?

No. The DLD inspection of 6 July 2026 recorded the tower 7.19% complete. Its registered completion date is 15 September 2028.

### What is the Sol Levante completion date?

15 September 2028 on the DLD register (via Continental Club). SOL Properties and Property Finder give Q3 2028.

### Has the Sol Levante handover date been delayed?

No. SOL Properties said in April 2025 that handover was slated for Q3 2028, repeated it in August 2025, and the register holds 15 September 2028.

### Do the Sol Levante offices and apartments hand over together?

The DLD register holds one completion date for all 674 units in the building, including the office and retail floors. No separate dates are published.

## Sources

- DLD project register via Continental Club, Sol Levante, inspection 6 Jul 2026; registry updated 4 Oct 2026: https://continentalclub.ae/project/sol-levante-jvt-district-1/
- DLD project register via Continental Club, handover 2028 list, accessed 11 Oct 2026: https://continentalclub.ae/handover-2028/
- Zawya, SOL Properties launches AED 1bln GDV mixed-use development SOL Levante in JVT, 17 Mar 2025: https://www.zawya.com/en/press-release/companies-news/sol-properties-launches-aed1bln-gdv-mixed-use-development-sol-levante-in-jvt-mgwco74q
- Zawya Projects, SOL Properties set to appoint main contractor for JVT project, 15 Apr 2025: https://www.zawya.com/en/projects/construction/dubais-sol-properties-set-to-appoint-main-contractor-for-jvt-project-soon-435479
- Zawya, SOL Properties unveils $272mln mixed-use development in JVT, 5 Aug 2025: https://www.zawya.com/en/business/real-estate/sol-properties-unveils-272mln-mixed-use-development-in-jvt-qy7nj3nf
- SOL Levante project site, residences and payment plan, accessed 11 Oct 2026: https://sollevantejvt.com/residences/
- Property Finder, Sol Levante project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/sol-properties/sol-levante
- offplans.com, Sol Levante, accessed 11 Oct 2026: https://offplans.com/project/sol-properties-sol-levante-by-sol-properties