# When is the Sobha Solis handover date?

URL: https://www.dxbrealtor.ai/answers/sobha-solis-handover-date/
Topic: Handover date
Updated: 2026-10-01

## Short answer

Sobha's own website gives December 2027 as the Sobha Solis handover date, but the DLD registered completion date is 31 December 2028, a year later. The latest DLD inspection, on 5 May 2026, recorded the project at 13.22% complete, and no newer inspection had been filed by 25 September 2026. The two dates have not been reconciled, so the date in each buyer's SPA is the one that applies.

## Key figures

- Registered completion date (DLD): 31 Dec 2028 (DLD register via Mitchell's and Continental Club, Sep 2026)
- Latest construction progress: 13.22% (DLD inspection, 5 May 2026)
- Developer's stated date: Dec 2027 (Sobha Realty, accessed 1 Oct 2026)
- Progress at previous inspection: 9.37% (DLD inspection, 29 Jan 2026)

## Sobha Solis handover date: the latest position

Sobha Solis has two published handover dates a year apart. Sobha's own website shows December 2027. The Dubai Land Department (DLD) register holds a registered completion date of 31 December 2028, and Property Finder shows the same December 2028. More on prices and the payment plan: [Sobha Solis](/projects/sobha-solis/).

Construction was at an early stage at the last inspection. The DLD recorded Sobha Solis at 13.22% complete on 5 May 2026, and Continental Club's register data of 25 September 2026 showed no newer inspection. Neither date has passed, but they do not agree, and Sobha has not explained the difference.

## Sobha Solis handover date by building

The DLD register lists Sobha Solis as one project, number 3334, with 2,341 units in six buildings and one completion date. Propsearch describes four towers, A to D. No source gives a separate date or progress figure for each tower, so every unit carries the same registered date.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Sobha Solis, all towers (DLD project 3334) | 13.22% (5 May 2026) | 31 Dec 2028 | Sobha: Dec 2027. Propsearch: Dec 2027. Property Finder: Dec 2028 |

## How the Sobha Solis handover date has changed

| Date | Event | Source |
|---|---|---|
| 3 Oct 2024 | Registered construction start. Bookings open from October 2024 | DLD via Continental Club; Property Finder |
| Jan 2025 | Official launch of about 2,316 furnished homes | Propsearch |
| 29 Jan 2026 | DLD inspection: 9.37% | DLD via Continental Club |
| 5 May 2026 | DLD inspection: 13.22%, up 3.85 points in three months | DLD via Continental Club |
| Sep 2026 | Register holds 31 Dec 2028. Sobha's site shows Dec 2027 | Mitchell's; Sobha Realty |

Sobha's site and Propsearch (updated 28 July 2026) show December 2027, while the DLD date on file is a year later. Between January and May 2026 the recorded pace was about 1.2 points a month. From 13.22% in May 2026, finishing by December 2027 needs about 4.4 points a month, and finishing by 31 December 2028 about 2.7.

## What the Sobha Solis handover date means for payments

The plan is 60% during construction and 40% on handover. The 40% is a single large payment tied to the actual handover, so whether that comes in December 2027, December 2028 or later decides when buyers need the funds, or a mortgage, in place.

| Price point | 40% due on handover |
|---|---|
| AED 1.55 million (Sobha starting price, Sep 2026) | AED 620,000 |
| AED 1.12 million (median registered sale, Apr 2025 to Sep 2026) | AED 448,000 |
| AED 4.04 million (top of Sobha's current range) | AED 1,616,000 |

Sources: Sobha Realty; DLD registered sales via Mitchell's.

## What to check before relying on the Sobha Solis date

1. **Which date your SPA uses.** December 2027 and 31 December 2028 are both published, and only the SPA date and its grace period are binding.
2. **How the 40% handover payment will be funded**, since it is due on the actual handover date, not the brochure date.
3. **The next DLD inspection.** The 13.22% figure dates from 5 May 2026, and a newer reading on the DLD project status service would show whether the pace has picked up.
4. **Which tower your unit is in**, in case Sobha later hands the towers over at different times. The register currently gives one date for all of them.

## Frequently asked

### What is the Sobha Solis handover date?

Sobha's website lists December 2027. The DLD registered completion date is 31 December 2028, and Property Finder also lists December 2028 (Sobha Realty, accessed 1 Oct 2026; Mitchell's, Sep 2026).

### What is the Sobha Solis completion date on the DLD register?

31 December 2028, for DLD project 3334, which covers all 2,341 units. The registered construction start was 3 October 2024.

### Is Sobha Solis due in 2027 or 2028?

Sources split. Sobha and Propsearch give December 2027. The DLD register and Property Finder give December 2028. At 13.22% complete in May 2026, the project had about 87 points of construction left.

### How much is due at handover at Sobha Solis?

40%. The plan is 60% during construction and 40% on handover. On a unit at Sobha's current AED 1.55 million starting price, that is AED 620,000.

## Sources

- Sobha Realty, Sobha Solis apartments, accessed 1 Oct 2026: https://sobharealty.com/sobha-communities/sobha-solis/apartments
- Mitchells Commercial Realty, Sobha Solis DLD registry and registered sales (project 3334), 8 Sep 2026: https://www.mitchellscommercialrealty.com/off-plan/sobha-solis
- Continental Club, Sobha Solis (DLD project registry), 25 Sep 2026: https://continentalclub.ae/project/sobha-solis-motor-city/
- Continental Club, Dubai handover 2028 projects and progress (DLD register), 15 Sep 2026: https://continentalclub.ae/handover-2028/
- fäm Properties, Sobha Solis completion date, accessed 1 Oct 2026: https://famproperties.com/completion-date/sobha-solis
- Property Finder, Sobha Solis project page, accessed 28 Sep 2026: https://www.propertyfinder.ae/en/new-projects/sobha-real-estate-llc/sobha-solis
- Propsearch, Sobha Solis, updated 28 Jul 2026: https://propsearch.ae/dubai/sobha-solis
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status