# When is the Sobha SeaHaven handover date?

URL: https://www.dxbrealtor.ai/answers/sobha-seahaven-handover-date/
Topic: Handover date
Updated: 2026-10-01

## Short answer

Sobha SeaHaven has two registered completion dates on the DLD register: 30 April 2028 for Tower A and 31 October 2028 for Towers B and C. At the latest DLD inspections, Towers B and C were 40.2% complete on 18 September 2026 and Tower A 37% complete on 6 August 2026. Earlier dates still circulate, including August 2027 on a Sobha listing and Q4 2026 to Q3 2027 from launch-era marketing, so the date in each tower's SPA is the one to rely on.

## Key figures

- Registered completion date (DLD): Tower A 30 Apr 2028; B and C 31 Oct 2028 (DLD register via Continental Club, Sep 2026)
- Latest construction progress, Towers B and C: 40.2% (DLD inspection, 18 Sep 2026)
- Latest construction progress, Tower A: 37% (DLD inspection, 6 Aug 2026)
- Portal date: Apr 2028 (Property Finder, accessed 28 Sep 2026. Matches Tower A only)

## Sobha SeaHaven handover date: the latest position

Sobha SeaHaven does not have one handover date. The Dubai Land Department (DLD) registers it as two projects: Tower A, with a registered completion date of 30 April 2028, and Towers B and C together, with 31 October 2028. Property Finder shows April 2028 for the whole development, which matches Tower A only. More on prices, sizes and the payment plan: [Sobha SeaHaven](/projects/sobha-seahaven/).

At the latest DLD inspections, Towers B and C were 40.2% complete on 18 September 2026 and Tower A was 37% complete on 6 August 2026. Earlier dates are still published elsewhere. A listing card on Sobha's own website showed August 2027 in September 2026, and Bayut shows Q3 2027 (Fahad Al Kuwari, 17 September 2026). Sobha's SeaHaven project pages give no date.

## Sobha SeaHaven handover date by building

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Tower A (66 storeys, 333 units, DLD project 2550) | 37% (6 Aug 2026) | 30 Apr 2028 | Property Finder: Apr 2028. Launch-era broker date: Q3 2027 |
| Tower B (47 storeys, DLD project 2762) | 40.2% (18 Sep 2026), shared with Tower C | 31 Oct 2028 | Launch-era broker date: Q4 2026 |
| Tower C (57 storeys, DLD project 2762) | 40.2% (18 Sep 2026), shared with Tower B | 31 Oct 2028 | No separate date published |

Towers B and C have 451 units between them and one progress figure, so there is no separate reading for Tower C. Tower heights are from Propsearch; broker dates are from Synergy Infracon.

## How the Sobha SeaHaven handover date has changed

| Date | Event | Source |
|---|---|---|
| 2022 | Tower A sales begin | DLD sales records via Continental Club |
| Feb 2023 | Tower A first DLD inspection: 0% | DLD via Fahad Al Kuwari |
| Jun 2023 | Sky Edition apartments launched in Tower A | Propsearch |
| 17 Jul 2023 | Tower B pre-launched | Sobha via Zawya |
| Oct 2023 | Towers B and C first DLD inspection: 0% | DLD via Fahad Al Kuwari |
| 2023 to 2024 | Marketing points to late 2026. Brokers quote Q4 2026 for Tower B and Q3 2027 for Tower A | Fahad Al Kuwari; Synergy Infracon |
| 27 Apr 2026 | Tower A: 30.92% | DLD via Continental Club |
| 11 Jun 2026 | Towers B and C: 32.23% | DLD via Continental Club |
| 6 Aug 2026 | Tower A: 37% | DLD via Continental Club |
| 18 Sep 2026 | Towers B and C: 40.2%. Register holds 30 Apr 2028 and 31 Oct 2028 | DLD via Continental Club |

Against the late 2026 date buyers heard at launch, Tower A's registered date is about 16 months later and Towers B and C about 22 months later. Towers B and C gained 7.97 points between June and September 2026, and Tower A 6.08 points between April and August 2026.

## What the Sobha SeaHaven handover date means for payments

Sources disagree on the plan. Property Finder lists two structures, 20% at launch, 40% during construction and 40% at handover, and 20/20/60 with 60% at handover. Real Estate Club Dubai cites 20/60/20 (17 June 2026). On any of these, 20% to 60% of the price falls due at handover, and that payment moves with the handover date of the buyer's tower. On a 1 bedroom bought at the AED 3.3 million launch price on the 20/40/40 plan, AED 1.32 million is due at handover. Many SeaHaven units are priced above AED 5 million, where mortgage loan-to-value limits are lower (Real Estate Club Dubai).

## What to check before relying on the Sobha SeaHaven date

1. **Which tower your unit is in.** Tower A and Towers B and C have registered dates six months apart, and portals often show only the Tower A date.
2. **The anticipated completion date in your SPA**, which may be an earlier launch-era date, and the grace period that applies to it.
3. **For resales, the balance still owed to Sobha**, since 40% or 60% at handover may still be outstanding.
4. **The next DLD inspection for your tower**, especially for Tower C, which has no separate progress figure.

## Frequently asked

### What is the Sobha SeaHaven handover date?

On the DLD register, 30 April 2028 for Tower A and 31 October 2028 for Towers B and C (Continental Club, Sep 2026). Property Finder shows April 2028 for the whole project, which matches Tower A only.

### What is the Sobha SeaHaven completion date for Tower B and Tower C?

31 October 2028. Towers B and C are one project on the DLD register, number 2762, so they share one date and one progress figure: 40.2% at the inspection of 18 September 2026.

### Is Sobha SeaHaven finished?

No. Tower A was 37% complete on 6 August 2026 and Towers B and C 40.2% complete on 18 September 2026 (DLD register).

### Has the Sobha SeaHaven handover date been delayed?

Against launch-era marketing, yes. Brokers quoted Q4 2026 for Tower B and Q3 2027 for Tower A, and a Property Finder page for the Sky Edition still shows 1 December 2026. The registered dates are now 30 April 2028 and 31 October 2028 (Fahad Al Kuwari, 17 Sep 2026; Synergy Infracon; Continental Club).

### Why do websites show August 2027 for Sobha SeaHaven?

A listing card on Sobha's website showed August 2027 in September 2026, while its project pages gave no date (Fahad Al Kuwari, 17 Sep 2026). Bayut shows Q3 2027. Both are earlier than either DLD registered date.

## Sources

- Continental Club, Sobha Seahaven Tower A (DLD registry, project 2550), 30 Sep 2026: https://continentalclub.ae/project/sobha-seahaven-tower-a-dubai-marina/
- Continental Club, Sobha Seahaven Tower B and C (DLD registry, project 2762), 25 Sep 2026: https://continentalclub.ae/project/sobha-seahaven-tower-b-c-dubai-marina/
- fäm Properties, Sobha Seahaven Tower A completion date, accessed 1 Oct 2026: https://famproperties.com/completion-date/sobha-seahaven-tower-a
- Homesearch, Sobha Seahaven Tower A (DLD project data), accessed 1 Oct 2026: https://www.homesearch.ae/for-sale/off-plan/sobha/sobha-seahaven-tower-a-2550
- Fahad Al Kuwari, Sobha Seahaven handover date: August 2027 or late 2028?, 17 Sep 2026: https://fahadalkuwari.com/sobha-seahaven-handover-date/
- Synergy Infracon, Sobha Seahaven Dubai Harbour, accessed 1 Oct 2026: https://synergyinfracon.com/projects/sobha-seahaven
- Zawya, Sobha pre-launches Sobha SeaHaven Tower B at Dubai Harbour, 17 Jul 2023: https://www.zawya.com/en/business/real-estate/sobha-pre-launches-sobha-seahaven-tower-b-at-dubai-harbour-wiay06vl
- Propsearch, Sobha Seahaven, updated 11 Jul 2026: https://propsearch.ae/dubai/sobha-seahaven
- Property Finder, Sobha Seahaven project page, accessed 28 Sep 2026: https://www.propertyfinder.ae/en/new-projects/sobha-real-estate-llc/sobha-seahaven
- Real Estate Club Dubai, Sobha Seahaven handover, financing your final payment, 17 Jun 2026: https://realestateclubdubai.com/handover/sobha-seahaven-handover-2026-final-payment-mortgage-financing
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status