# When is the Saria by Beyond handover date?

URL: https://www.dxbrealtor.ai/answers/saria-by-beyond-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Beyond gives Q1 2028 for the Saria by Beyond handover, while the DLD register holds a registered completion date of 1 October 2027. The DLD inspection on 1 October 2026 recorded 30.99% complete. With 69% of the work left, the registered date will not be met, and even Q1 2028 needs a faster pace than the tower has shown so far.

## Key figures

- Registered completion date (DLD): 1 Oct 2027 (DLD project register via Continental Club)
- Latest construction progress: 30.99% (DLD inspection, 1 Oct 2026)
- Developer's stated date: Q1 2028 (Beyond via Zawya, 24 Mar 2026)
- Date change since launch: Q4 2027 to Q1 2028 (Propsearch)

## Saria by Beyond handover date: the latest position

Beyond expects Saria to be completed in Q1 2028, and Property Finder lists expected completion on 31 March 2028. The DLD project register still holds a registered completion date of 1 October 2027. Prices, sizes and the payment plan are on the [Saria by Beyond](/projects/saria-by-beyond/) page.

The DLD inspection on 1 October 2026 recorded the tower 30.99% complete, a year before its registered date. Construction has sped up in 2026, but the registered date is out of reach, and Q1 2028 depends on keeping up the latest pace.

## Saria by Beyond handover date by building

Saria is one tower, registered as DLD project 3115 with 372 units.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Saria by Beyond | 30.99%, 1 Oct 2026 | 1 Oct 2027 | Q1 2028 (Beyond, Mar 2026); 31 Mar 2028 (Property Finder); Q3 2029 (Inside Realty) |

For the other towers in the district, see the [Dubai Maritime City handover date](/answers/dubai-maritime-city-handover-date/) page.

## How the Saria by Beyond handover date has changed

| Date | What happened | Source |
|---|---|---|
| 23 Sep 2024 | Launch; payment schedule anticipates completion in Q1 2028 | Metropolitan; Saria sales microsite |
| 1 Nov 2024 | Registered construction start | DLD register |
| 6 Dec 2024 | Beyond says Saria is sold out | Business Wire |
| 24 Oct 2025 | Inspection records 7.12% | DLD register |
| 28 Jan 2026 | Inspection records 10.32% | DLD register |
| 24 Mar 2026 | Beyond reports about 10% and Q1 2028 completion | Zawya |
| 7 May 2026 | Inspection records 16.88% | DLD register |
| 1 Oct 2026 | Inspection records 30.99% | DLD register |

Propsearch records an earlier estimate of Q4 2027, close to the registered date, later revised to Q1 2028. The payment schedule published at launch already pointed the final payment to Q1 2028, so the gap between the registered date and Beyond's date has existed since sales began.

Between 7 May and 1 October 2026 the tower gained about 2.9 points a month. At that pace the remaining 69% would take about two years, to around late 2028. Continental Club's longer-run average of 2.12 points a month points to mid 2029. Reaching completion by 31 March 2028 would need about 3.8 points a month for the next 18 months.

## What the Saria by Beyond handover date means for payments

Half the price is due on completion. The other 50% is paid on fixed dates: 10% on booking, 10% a month later and six 5% instalments every April and October from 2025 to 1 October 2027 (Saria sales microsite). Those dates do not move with construction, so buyers will have paid 50% by October 2027 whatever the progress. A later completion only delays the final 50%, giving more time to arrange a mortgage or sell before it falls due.

## What to check before relying on the Saria by Beyond date

1. **The completion date and grace period in the SPA**, since the registered date of 1 October 2027 will pass with the tower unfinished.
2. **The 1 April 2027 and 1 October 2027 instalments**, which fall due before completion on any of the published dates.
3. **The next DLD inspections.** A pace of about 3.8 points a month is needed to reach Q1 2028.

## Frequently asked

### When will Saria by Beyond be completed?

Beyond expects completion in Q1 2028, and Property Finder lists 31 March 2028. The DLD register still shows a registered completion date of 1 October 2027. The tower was 30.99% complete on 1 October 2026.

### Has the Saria by Beyond handover date been delayed?

Yes, by about one quarter so far. Propsearch records an original estimate of Q4 2027, later revised to Q1 2028. The DLD registered date of 1 October 2027 has not been updated.

### How fast is construction moving at Saria?

Progress went from 7.12% on 24 October 2025 to 10.32% on 28 January 2026, 16.88% on 7 May 2026 and 30.99% on 1 October 2026 (DLD project register via Continental Club).

### Is Saria by Beyond finished?

No. It was 30.99% complete at the DLD inspection on 1 October 2026.

## Sources

- DLD project register via Continental Club, Dubai handover 2027 tracker (Saria by Beyond, inspection 1 Oct 2026), accessed 11 Oct 2026: https://continentalclub.ae/handover-2027/
- DLD project register via Continental Club, Saria by Beyond (project 3115), register updated 8 Oct 2026: https://continentalclub.ae/project/saria-by-beyond-maritime-city/
- Zawya, BEYOND Developments confirms continued construction progress across Dubai Maritime City masterplan, 24 Mar 2026: https://www.zawya.com/en/press-release/companies-news/beyond-developments-confirms-continued-construction-progress-across-dubai-maritime-city-masterplan-354605
- Property Finder, Saria project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/beyond/saria
- Propsearch, Saria by Beyond, updated 11 Jul 2026: https://propsearch.ae/dubai/saria-by-beyond
- Saria by Beyond sales microsite, payment plan, 24 Sep 2024: https://sariabeyond.com/
- Metropolitan Premium Properties, SARIA new launch in Dubai Maritime City, 23 Sep 2024: https://metropolitan.realestate/media/news/saria-new-launch-in-dubai-maritime-city/
- Business Wire, BEYOND Developments launches Orise after sell-out of Saria, 6 Dec 2024: https://www.businesswire.com/news/home/20241206164506/en/Following-the-Phenomenal-Success-and-Sell-Out-of-Its-First-Project-Saria-BEYOND-Developments-Launches-Orise-Continuing-to-Set-New-Standards-in-Waterfront-Living-at-Dubai-Maritime-City
- Inside Realty, Saria by BEYOND, accessed 11 Oct 2026: https://insiderealty.ae/en/projects/saria-by-beyond-dubai-maritime-city
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status