# When is the Samana Resorts handover date?

URL: https://www.dxbrealtor.ai/answers/samana-resorts-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

The registered completion date for Samana Resorts is 30 May 2028, per the Dubai Land Department (DLD) project register, and Samana's project page now gives Q3 2028. The last DLD inspection, on 23 June 2026, put construction at 5.85% for both towers together. Data Habibi records an original promise of Q4 2026, and Property Finder still shows December 2026, so portal dates can be badly out of date.

## Key figures

- Registered completion date (DLD): 30 May 2028 (DLD project register via Continental Club)
- Latest construction progress: 5.85% (DLD inspection, 23 Jun 2026)
- Developer's stated date: Q3 2028 (Samana Developers, accessed 11 Oct 2026)
- Date change since launch: Q4 2026 to Q3 2028 (Data Habibi, 21 month postponement)

## Samana Resorts handover date: the latest position

The Dubai Land Department (DLD) register gives Samana Resorts a completion date of 30 May 2028, and Samana's own project page now says Q3 2028. Prices and payment plans are on the [Samana Resorts](/projects/samana-resorts/) project page.

The last DLD inspection, on 23 June 2026, recorded 5.85% complete, up from 4.42% on 3 April 2026. With about 23 months from that inspection to the register date, nearly all of the two towers remained to be built.

## Samana Resorts handover date by building

The register describes a shared base of three basements and a ground floor, with Tower A and Tower B each of 16 floors plus a roof. Progress and the completion date are recorded for the project as a whole.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Tower A | 5.85% for whole project (23 Jun 2026) | 30 May 2028 | Q3 2028 (Samana); Q2 2028 (Bayut) |
| Tower B | 5.85% for whole project (23 Jun 2026) | 30 May 2028 | Q3 2028 (Samana); Q2 2028 (Bayut) |

Registered sales are split almost evenly, 212 in Tower A and 224 in Tower B since 28 April 2025 (Mitchells). Samana Resorts Phase 2 is a separate listing with its own dates and is not part of this table.

## How the Samana Resorts handover date has changed

| Date | What was recorded | Source |
|---|---|---|
| Launch | Developer promise Q4 2026 | Data Habibi |
| 30 Dec 2024 | Brokers list completion in Q2 2028 | Off Plan Properties Dubai |
| 1 May 2025 | Construction start on the DLD register | DLD via Mitchells |
| 3 Apr 2026 | DLD inspection: 4.42% complete | DLD via Continental Club |
| 23 Jun 2026 | DLD inspection: 5.85% complete | DLD via Continental Club |
| Oct 2026 | Registered completion 30 May 2028; Samana says Q3 2028 | DLD register, Samana Developers |

Property Finder still shows December 2026, the launch era date. The current gap between the register and Samana's page is one quarter.

## What the Samana Resorts handover date means for payments

Property Finder lists four plans. The post-handover plan is 20% on booking, 57% during construction, 1% on handover and 22% after handover. The other three, 15/85, 20/80 and 20/79/1, are paid in full by handover. In December 2024, a broker listed 20%, 52%, 5% on handover and 23% over 44 months after handover. Under the post-handover plans, the instalments after the keys start only once handover happens, so a later date also pushes back the final payment.

## What to check before relying on the Samana Resorts date

1. **Whether the SPA says 30 May 2028 or Q3 2028**, and the grace period stated.
2. **That the unit is in Tower A or Tower B of Samana Resorts**, not Samana Resorts Phase 2.
3. **The next DLD inspection**, through the DLD project status service, for progress after 5.85%.

## Frequently asked

### What is the Samana Resorts completion date?

The DLD register gives 30 May 2028 for project number 2895. Samana's project page gives Q3 2028 and Bayut lists Q2 2028.

### Is Samana Resorts finished?

No. Construction started on 1 May 2025, and the DLD inspection of 23 June 2026 recorded 5.85% complete.

### Has the Samana Resorts handover date been delayed?

Yes. Data Habibi records an original developer promise of Q4 2026 and a current target of Q3 2028, a 21 month postponement.

### Do Tower A and Tower B hand over at different times?

The DLD register lists both towers under one project with one completion date, 30 May 2028, and one progress figure. No source gives separate dates for each tower.

## Sources

- Continental Club, Samana Resorts (DLD project register), inspection 23 Jun 2026, registry updated 9 Oct 2026: https://continentalclub.ae/project/samana-resorts-dubai-production-city/
- DLD project register via Continental Club, handover 2028 list, inspection 23 Jun 2026: https://continentalclub.ae/handover-2028/
- Mitchells, Samana Resorts DLD registry and registered sales, registry as at 4 Oct 2026: https://www.mitchellscommercialrealty.com/off-plan/samana-resorts
- Samana Developers, Samana Resorts, accessed 11 Oct 2026: https://www.samanadevelopers.com/projects/samana-resorts
- Data Habibi, Samana Resorts, accessed 11 Oct 2026: https://datahabibi.ae/dubai/new-projects/samana-resorts
- Bayut, Samana Resorts building guide, 16 Sep 2026: https://www.bayut.com/buildings/samana-resorts-dubai-production-city/
- Property Finder, Samana Resorts project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/samana-developers/samana-resorts
- Off Plan Properties Dubai, Samana Resorts, 30 Dec 2024: https://offplanpropertiesdubai.ae/projects/samana-resorts/
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status
