# When is the Samana Park Meadows handover date?

URL: https://www.dxbrealtor.ai/answers/samana-park-meadows-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Samana Park Meadows is registered with the DLD for completion on 31 August 2027, while Samana Developers announced a March 2028 handover at launch in October 2024. The DLD inspection of 1 October 2026 recorded 38.03% complete. At the pace of the past year, Continental Club projects completion around September 2028, later than both dates.

## Key figures

- Registered completion date (DLD): 31 Aug 2027 (DLD project register via Continental Club)
- Latest construction progress: 38.03% (DLD inspection, 1 Oct 2026)
- Developer's date at launch: March 2028 (Samana via Zawya, 3 Oct 2024)
- Projection at past year's pace: About Sep 2028 (Continental Club, 2.61 points a month)

## Samana Park Meadows handover date: the latest position

The Dubai Land Department (DLD) project register lists Samana Park Meadows with a completion date of 31 August 2027. At launch on 3 October 2024, Samana Developers announced completion and handover in March 2028. Prices, sizes and the full plan are on the project page: [Samana Park Meadows](/projects/samana-park-meadows/).

The DLD inspection of 1 October 2026 recorded 38.03% complete. Meeting the August 2027 register date would need about 5.6 points a month for the next 11 months, about double the pace of the past year.

## Samana Park Meadows handover date by building

The project is one building of two basements, a ground floor, 16 floors and a roof, with 221 apartments.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Samana Park Meadows (221 units) | 38.03% (1 Oct 2026) | 31 Aug 2027 | March 2028 (Samana at launch); Q3 2027 (Continental Club); August 2027 (Propsearch); Q1 2028 (Data Habibi) |

Earlier DLD inspections: 8.61% on 23 October 2025 and 27.27% on 18 June 2026 (via Continental Club).

## How the Samana Park Meadows handover date has changed

| Date | Event | Source |
|---|---|---|
| 1 Aug 2024 | Construction start on the DLD register | DLD via Continental Club |
| 28 Aug 2024 | Project registered with the DLD | Dubai Data |
| 3 Oct 2024 | Launch: AED 220 million, 221 units, from AED 694,000, handover March 2028 | Zawya, Arabian Business |
| 23 Oct 2025 | DLD inspection: 8.61% | DLD register via Continental Club |
| 3 Jan 2026 | Propsearch estimate: August 2027 | Propsearch |
| 18 Jun 2026 | DLD inspection: 27.27% | DLD register via Continental Club |
| 1 Oct 2026 | DLD inspection: 38.03% | DLD register via Continental Club |

The two dates have both stood since 2024. Progress picked up in 2026: 10.76 points between June and October, about 3.2 points a month. Continental Club's projection of about 22 September 2028 uses the slower 2.61 points a month average of the past year.

## What the Samana Park Meadows handover date means for payments

Samana's non-PDC plan takes 20% on booking, 1% a month for 42 months, 10% in month 12 and 5% in month 18, which is 77% in about three and a half years from booking. The last 23% is paid at 0.5% a month for 46 months; on the PDC plan it is 28% over 56 months. Data Habibi lists 5% due on handover itself.

For a buyer who booked in October 2024, the 42 monthly instalments end around April 2028, close to the launch handover date. On a AED 1.46 million two bedroom, the 0.5% stage is about AED 7,300 a month.

## What to check before relying on the Samana Park Meadows date

1. **Which date the SPA states**, 31 August 2027 or March 2028, and the grace period after it.
2. **Progress at the next DLD inspections**, to see whether the 2026 pace of about 3 points a month holds or rises.
3. **The plan wording**, including any handover payment and the start date of the 0.5% instalments.

## Frequently asked

### When will Samana Park Meadows be completed?

The DLD register gives 31 August 2027 (project number 2896). Samana announced March 2028 at launch, and Data Habibi shows Q1 2028.

### Has the Samana Park Meadows handover date been delayed?

No delay has been announced. The launch date was March 2028; the register date of 31 August 2027 is earlier. Progress of 38.03% in October 2026 makes the August 2027 date hard to reach.

### How far along is Samana Park Meadows?

38.03% at the DLD inspection of 1 October 2026, up from 27.27% on 18 June 2026 and 8.61% on 23 October 2025 (DLD register via Continental Club).

### When does the post-handover plan at Samana Park Meadows start?

Samana's plans end with 0.5% a month for 46 months (non-PDC) or 56 months (PDC). At launch, Samana's chief executive described these as payments after handover, so they start when the building is handed over.

## Sources

- Continental Club, Samana Park Meadows (DLD project register), inspection 1 Oct 2026, register updated 7 Oct 2026: https://continentalclub.ae/project/samana-park-meadows-dubailand-residence-complex/
- DLD project register via Continental Club, handover 2027 list, inspection 1 Oct 2026: https://continentalclub.ae/handover-2027/
- Zawya, Samana launches $60mln Samana Park Meadows in Dubailand, 3 Oct 2024: https://www.zawya.com/en/business/real-estate/samana-launches-60mln-samana-park-meadows-in-dubailand-ilq81utt
- Samana Developers, Samana Park Meadows, accessed 11 Oct 2026: https://www.samanadevelopers.com/projects/samana-park-meadows
- Dubai Data, Samana Park Meadows (DLD record), accessed 11 Oct 2026: https://datadubai.ae/projects/samana-park-meadows/
- Propsearch, Samana Park Meadows, updated 3 Jan 2026, accessed 11 Oct 2026: https://propsearch.ae/dubai/samana-park-meadows
- Data Habibi, Samana Park Meadows, accessed 11 Oct 2026: https://datahabibi.ae/dubai/new-projects/samana-park-meadows