# When is the Samana Mykonos Signature handover date?

URL: https://www.dxbrealtor.ai/answers/samana-mykonos-signature-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Samana Developers now gives Q1 2027 as the anticipated completion date for Samana Mykonos Signature, while the Dubai Land Department (DLD) register still shows 30 April 2026, a date that has passed. The last DLD inspection, on 14 May 2026, put construction at 80.48%. The date has moved from Q4 2025 at launch, and Property Finder's ready label does not match the register, which lists the building as under construction.

## Key figures

- Registered completion date (DLD): 30 Apr 2026 (passed) (DLD project register via Continental Club)
- Latest construction progress: 80.48% (DLD inspection, 14 May 2026)
- Developer's stated date: Q1 2027 (Samana Developers, accessed 11 Oct 2026)
- Date change since launch: Q4 2025 to Q2 2027 (Data Habibi, 20 month postponement)

## Samana Mykonos Signature handover date: the latest position

Samana Developers now gives Q1 2027 as the anticipated completion date for Samana Mykonos Signature. The Dubai Land Department (DLD) register still shows 30 April 2026, which passed with the building unfinished. Prices and the payment plan are on the [Samana Mykonos Signature](/projects/samana-mykonos-signature/) project page.

The last DLD inspection, on 14 May 2026, recorded 80.48% complete. Data Habibi lists Q2 2027, one quarter later than Samana, so sources disagree on the exact quarter.

A passed registered date does not mean the building is finished. It means the developer has not yet filed a new date with the DLD. Between the inspections of 22 January and 14 May 2026, the building gained about two points a month, which would take the remaining 19.5% into early 2027 if that pace held.

## Samana Mykonos Signature handover date by building

The project is one building of a basement, ground floor, mezzanine and eight floors, with 300 units.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Samana Mykonos Signature (project 2587) | 80.48% (14 May 2026) | 30 Apr 2026 (passed) | Q1 2027 (Samana); Q2 2027 (Data Habibi); Q4 2026 (Dubainary, OffplanIndex) |

Samana Mykonos Signature is a separate project from Samana Mykonos in Dubai Studio City, which has its own register entry and dates.

## How the Samana Mykonos Signature handover date has changed

| Date | What was recorded | Source |
|---|---|---|
| 1 Oct 2023 | Bookings open and construction starts; developer target Q4 2025 | Property Finder, Data Habibi, DLD register |
| 22 Jan 2026 | DLD inspection: about 72.7% complete | DLD via Continental Club |
| 30 Apr 2026 | Registered completion date passes | DLD register |
| 14 May 2026 | DLD inspection: 80.48% complete | DLD via Continental Club |
| Oct 2026 | Samana's page shows Q1 2027; Data Habibi shows Q2 2027 | Samana Developers, Data Habibi |

From Q4 2025 at launch to Q1 2027 now is a move of about five quarters. All 18 sales registered between 16 July 2025 and 3 September 2026 were off-plan, which confirms no units had completed by then (Mitchells).

## What the Samana Mykonos Signature handover date means for payments

The launch plan was 15% on booking, 25% during construction and 60% on handover (Property Finder, Data Habibi). Later listings show 20/20/60 (OffplanIndex). Under either plan, 60% of the price falls due at handover, so the move to 2027 also delays the largest payment. On a studio bought for AED 850,000, that is AED 510,000.

## What to check before relying on the Samana Mykonos Signature date

1. **The completion date and grace period in the SPA**, since the register date has already passed.
2. **Any written notice from Samana of the new date**, as the project page says Q1 2027 but the register has not been updated.
3. **The next DLD inspection**, through the DLD project status service, for progress beyond 80.48%.

## Frequently asked

### What is the Samana Mykonos Signature completion date?

Samana's project page gives Q1 2027 (accessed 11 October 2026). The DLD register shows 30 April 2026 for project number 2587, which has passed without completion.

### Is Samana Mykonos Signature finished?

No. The DLD inspection of 14 May 2026 recorded 80.48% complete, and the register lists the project as under construction. Property Finder's ready label does not match that record.

### Has the Samana Mykonos Signature handover date been delayed?

Yes. Data Habibi records an original promise of Q4 2025 and a current target of Q2 2027. The register date of 30 April 2026 has passed, and Samana now gives Q1 2027.

### How fast is Samana Mykonos Signature being built?

Progress rose 7.81 points between the DLD inspections of 22 January 2026 and 14 May 2026, to 80.48% (DLD project register via Continental Club).

## Sources

- Continental Club, Samana Mykonos Signature (DLD project register), inspection 14 May 2026: https://continentalclub.ae/project/samana-mykonos-signature-arjan/
- DLD project register via Continental Club, handover 2026 list, inspection 14 May 2026: https://continentalclub.ae/handover-2026/
- Mitchells, Samana Mykonos Signature DLD registry and registered sales, registry as at 15 Jun 2026, sales to 23 Sep 2026: https://www.mitchellscommercialrealty.com/off-plan/samana-mykonos-signature
- Samana Developers, Samana Mykonos Signature, accessed 11 Oct 2026: https://www.samanadevelopers.com/projects/samana-mykonos-signature
- Property Finder, Samana Mykonos Signature project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/samana-developers/samana-mykonos-signature
- Data Habibi, Samana Mykonos Signature, accessed 11 Oct 2026: https://datahabibi.ae/dubai/new-projects/samana-mykonos-signature
- OffplanIndex, Samana Mykonos Signature, accessed 11 Oct 2026: https://offplanindex.com/projects/samana-developers-samana-mykonos-signature
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status