# When is the Samana Imperial Garden handover date?

URL: https://www.dxbrealtor.ai/answers/samana-imperial-garden-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Samana Imperial Garden is registered with the DLD for completion on 31 December 2028, and Samana Developers gives Q1 2029, the March 2029 date announced at launch. The DLD inspection of 19 June 2026 recorded 3.76% complete. The register date is earlier than the developer's, so buyers will see different dates depending on the source.

## Key figures

- Registered completion date (DLD): 31 Dec 2028 (DLD project register via Continental Club)
- Latest construction progress: 3.76% (DLD inspection, 19 Jun 2026)
- Developer's stated date: Q1 2029 (Samana Developers, accessed 11 Oct 2026)
- Date announced at launch: March 2029 (Samana via Zawya, 14 Oct 2025)

## Samana Imperial Garden handover date: the latest position

The Dubai Land Department (DLD) project register lists Samana Imperial Garden with a completion date of 31 December 2028. Samana Developers gives an anticipated completion date of Q1 2029, the same March 2029 target it announced at launch. Prices, sizes and the full plan are on the project page: [Samana Imperial Garden](/projects/samana-imperial-garden/).

The building is at an early stage. The DLD inspection of 19 June 2026 recorded 3.76% complete, with about 30 months left to the registered date. The register sets the construction period from 1 July 2025 to 31 December 2028.

## Samana Imperial Garden handover date by building

The project is one building of two basements, a ground floor, six floors and a roof, with 344 apartments.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Samana Imperial Garden (344 units) | 3.76% (19 Jun 2026) | 31 Dec 2028 | Q1 2029 (Samana); December 2028 (Propsearch) |

Earlier DLD inspection: 2.34% on 30 April 2026 (via Continental Club).

## How the Samana Imperial Garden handover date has changed

| Date | Event | Source |
|---|---|---|
| 1 Jul 2025 | Construction start on the DLD register, with completion set for 31 Dec 2028 | DLD via Continental Club |
| 14 Oct 2025 | Launch: AED 398 million, 344 units, from AED 859,000, handover March 2029 | Samana via Zawya |
| 28 Feb 2026 | Propsearch estimate: December 2028 | Propsearch |
| 30 Apr 2026 | DLD inspection: 2.34% | DLD register via Continental Club |
| 19 Jun 2026 | DLD inspection: 3.76% | DLD register via Continental Club |
| 11 Oct 2026 | Samana's page: Q1 2029 | Samana Developers |

Neither date has moved since launch. The gap between them is one quarter, with the register ahead of the developer.

## What the Samana Imperial Garden handover date means for payments

Samana's plans are paid mostly by monthly instalments. On the non-PDC plan, buyers pay 20% on booking, 10% in month 12, then 1% a month for 70 months. On the PDC plan it is 15%, 10%, then 1% a month for 75 months. From an October 2025 booking, the last monthly instalment falls in about 2031, so close to 30% of the price is still being paid after a March 2029 handover.

On a AED 838,000 studio, the DLD median, the monthly instalment is about AED 8,380. Continental Club lists a different split with 75% due on handover, so the plan attached to each SPA needs checking.

## What to check before relying on the Samana Imperial Garden date

1. **Which date the SPA states**: 31 December 2028, Q1 2029 or March 2029, and the grace period after it.
2. **The plan in the SPA**, since the published plans run monthly past handover while one listing shows 75% on handover.
3. **The next DLD inspection**, since the last published figure is from June 2026.

## Frequently asked

### When will Samana Imperial Garden be completed?

The DLD register gives 31 December 2028 (project number 3797). Samana's page says Q1 2029, and Propsearch shows December 2028.

### Has the Samana Imperial Garden handover date been delayed?

No. Samana announced March 2029 at launch on 14 October 2025 and still gives Q1 2029. The DLD register date, 31 December 2028, is earlier.

### How far along is Samana Imperial Garden?

3.76% complete at the DLD inspection of 19 June 2026, up from 2.34% on 30 April 2026 (DLD register via Continental Club).

### How much is due at handover at Samana Imperial Garden?

Samana's published plans have no large handover payment. After 20% or 15% on booking and 10% in month 12, buyers pay 1% a month for 70 or 75 months, which runs past the Q1 2029 handover.

## Sources

- Continental Club, Samana Imperial Garden (DLD project register), inspection 19 Jun 2026, register updated 4 Oct 2026: https://continentalclub.ae/project/samana-imperial-garden-arjan/
- DLD project register via Continental Club, handover 2028 list, inspection 19 Jun 2026: https://continentalclub.ae/handover-2028/
- Samana Developers, Samana Imperial Garden, accessed 11 Oct 2026: https://www.samanadevelopers.com/projects/samana-imperial-garden
- Zawya (Samana press release), Samana redefines Arjan living with Flexible Homes at Imperial Garden, 14 Oct 2025: https://www.zawya.com/en/press-release/companies-news/samana-redefines-arjan-living-with-flexible-homes-and-private-pools-at-imperial-garden-397348
- Propsearch, Samana Imperial Garden, updated 28 Feb 2026, accessed 11 Oct 2026: https://propsearch.ae/dubai/samana-imperial-garden