# When is the Samana Barari Avenue handover date?

URL: https://www.dxbrealtor.ai/answers/samana-barari-avenue-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Samana Barari Avenue is registered with the DLD for completion on 31 October 2028, while Samana Developers gives a Q2 2028 handover. The DLD inspection of 23 September 2026 recorded 6.01% complete, up from 4.57% in June. The two dates are four months apart, and the date in each buyer's SPA is the one that applies.

## Key figures

- Registered completion date (DLD): 31 Oct 2028 (DLD project register via Continental Club)
- Latest construction progress: 6.01% (DLD inspection, 23 Sep 2026)
- Developer's stated date: Q2 2028 (Samana Developers, accessed 11 Oct 2026)
- Date shown at launch: To be announced, then Q3 2028 (Broker listings, 4 and 20 Apr 2025)

## Samana Barari Avenue handover date: the latest position

The Dubai Land Department (DLD) project register lists Samana Barari Avenue with a completion date of 31 October 2028. Samana Developers' own page says Q2 2028, which ends four months earlier. Prices, sizes and the full plan are on the project page: [Samana Barari Avenue](/projects/samana-barari-avenue/).

Construction is in its early stages. The DLD inspection of 23 September 2026 put the tower at 6.01% complete, with about 25 months to the registered date.

## Samana Barari Avenue handover date by building

The project is one commercial tower of 349 offices and shops, over three basement levels and three parking levels.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Samana Barari Avenue (349 units) | 6.01% (23 Sep 2026) | 31 Oct 2028 | Q2 2028 (Samana); Q2 2028 (Data Habibi, Dubai Homes Online) |

Earlier DLD inspection: 4.57% on 18 June 2026 (via Continental Club).

## How the Samana Barari Avenue handover date has changed

| Date | Event | Source |
|---|---|---|
| Mar to Jun 2025 | Construction start: March 2025 per Data Habibi, 1 June 2025 per the DLD register | Data Habibi; DLD via Continental Club |
| 4 Apr 2025 | Expression of interest from AED 940,000; handover "to be announced" | Offplan Dubai |
| 20 Apr 2025 | Expected handover Q3 2028 | Remington Properties |
| 18 Jun 2026 | DLD inspection: 4.57% | DLD register via Continental Club |
| 10 Aug 2026 | Handover Q2 2028 | Dubai Homes Online |
| 23 Sep 2026 | DLD inspection: 6.01%; registered completion 31 Oct 2028 | DLD register via Continental Club |
| 11 Oct 2026 | Samana's page: Q2 2028 | Samana Developers |

The developer's quarter has moved earlier, not later, since the first listings. The register still holds October 2028.

## What the Samana Barari Avenue handover date means for payments

Samana's plans are spread over time rather than weighted on handover day. On the non-PDC plan, 20% is paid on booking, 1% a month for 36 months plus 10% in month 12 and 5% in months 18 and 24, then 24% at 0.5% a month for 48 months. The PDC plan starts at 15% and ends with 29% over 58 months. Dubai Homes Online describes the handover payment itself as 1%.

On a AED 2.17 million office, the 0.5% monthly stage is about AED 10,850 a month. When those instalments start depends on the plan wording in the SPA, so a later handover can shift the end of the payment schedule.

## What to check before relying on the Samana Barari Avenue date

1. **Which date the SPA uses**: Q2 2028, 31 October 2028, or another date with a grace period.
2. **Progress at the next DLD inspection**, since 1.44 points were added between June and September 2026 and over 90 points remain.
3. **Whether the 0.5% instalments are tied to handover or to calendar months** in the unit's plan.

## Frequently asked

### When will Samana Barari Avenue be completed?

The DLD register gives 31 October 2028 (project number 3829). Samana Developers' page says Q2 2028.

### Has the Samana Barari Avenue handover date been delayed?

No delay has been announced. Launch listings in April 2025 showed the date as to be announced and then Q3 2028; Samana has since shown Q2 2028, and the register date is 31 October 2028.

### How far along is Samana Barari Avenue?

6.01% at the DLD inspection of 23 September 2026, up 1.44 points from 4.57% on 18 June 2026 (DLD register via Continental Club).

### How much is paid after handover at Samana Barari Avenue?

On Samana's non-PDC plan, 24% is paid at 0.5% a month for 48 months. On the PDC plan, 29% is paid at 0.5% a month for 58 months.

## Sources

- Continental Club, Samana Barari Avenue (DLD project register), inspection 23 Sep 2026, register updated 4 Oct 2026: https://continentalclub.ae/project/samana-barari-avenue-majan/
- DLD project register via Continental Club, handover 2028 list, inspection 23 Sep 2026: https://continentalclub.ae/handover-2028/
- Samana Developers, Samana Barari Avenue, accessed 11 Oct 2026: https://www.samanadevelopers.com/projects/samana-barari-avenue
- Offplan Dubai, Samana Barari Avenue, 4 Apr 2025: https://www.offplan-dubai.com/samana-barari-avenue/
- Remington Properties, Samana Barari Avenue, 20 Apr 2025: https://remington.ae/samana-barari-avenue-commercial-excellence-in-majan-dubai/
- Propsearch, Samana Barari Avenue, updated 4 Feb 2026, accessed 11 Oct 2026: https://propsearch.ae/dubai/samana-barari-avenue
- Data Habibi, Samana Barari Avenue, accessed 11 Oct 2026: https://datahabibi.ae/dubai/new-projects/samana-barari-avenue
- Dubai Homes Online, Samana Barari Avenue, 10 Aug 2026: https://www.dubaihomesonline.com/project/1208-samana-barari-avenue-by-samana-at-majan