# When is the Reem by Vision handover date?

URL: https://www.dxbrealtor.ai/answers/reem-by-vision-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Reem by Vision has a registered completion date of 31 December 2026, matching the Q4 2026 handover date Vision Developments gave at launch in May 2025. The DLD inspection on 23 July 2026 recorded 53.14% complete. At the pace recorded between April and July 2026 the building would reach only about 80% by the end of the year, so a move into 2027 is likely unless work speeds up.

## Key figures

- Registered completion date (DLD): 31 Dec 2026 (DLD project register via Continental Club, updated 4 Oct 2026)
- Latest construction progress: 53.14% (DLD inspection, 23 Jul 2026)
- Developer's stated date: Q4 2026 (Vision Developments, 13 May 2025)
- Progress, April to July 2026: +13.71 points (DLD inspections, 28 Apr and 23 Jul 2026)

## Reem by Vision handover date: the latest position

Reem by Vision has a registered completion date of 31 December 2026, the same as the Q4 2026 date Vision Developments announced at launch. Prices, sizes and the payment plan are on the [Reem by Vision](/projects/reem-by-vision/) page.

The DLD inspection on 23 July 2026 recorded 53.14% complete. Vision has not announced a new date, but the pace of work since April 2026 points to completion in 2027 rather than by 31 December 2026.

## Reem by Vision handover date by building

Reem is one building, DLD project 3612, registered in Wadi Al Safa 2 (Liwan) with 200 units.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Reem by Vision (G+P+8+roof, 200 units) | 53.14%, 23 Jul 2026 | 31 Dec 2026 | Q4 2026 (Vision Developments); Dec 2026 (Property Finder) |

Vision lists 198 apartments over ground floor retail; the DLD register counts 200 units, including two larger units, and describes residential and clinic use. All units share one progress figure and one completion date. The register had recorded 192 sales by 4 October 2026, only one of them a resale (Continental Club), so almost every owner bought directly from Vision on the same date terms.

## How the Reem by Vision handover date has changed

| Date | What happened | Source |
|---|---|---|
| 17 Mar 2025 | First DLD inspection, 0% | DLD via Dubai Handover |
| 13 May 2025 | Vision launches Reem and Soul, handover Q4 2026 | Vision Developments |
| 31 May 2025 | Construction start recorded | DLD register |
| 28 Apr 2026 | Inspection records about 39.4% | DLD register via Continental Club |
| 23 Jul 2026 | Inspection records 53.14% | DLD register via Continental Club |
| 4 Oct 2026 | Registered completion date still 31 Dec 2026 | DLD register via Continental Club |

The date has not changed. The schedule from construction start to registered completion is 19 months, short for a 200 unit building. Between the April and July 2026 inspections the building added about 4.8 points a month. At that rate it would stand near 79% on 31 December 2026 and reach 100% around mid 2027. This is an estimate from the published inspections, not a DLD or Vision figure.

## What the Reem by Vision handover date means for payments

Under the 10/20/70 plan, 70% of the price is due on handover. On a 1 bedroom at the DLD median of AED 840,200, that is about AED 588,000; on a studio at AED 560,900, about AED 392,600. Buyers have paid only 30% before that point, so a later handover delays the largest payment, and any mortgage for it, by the same amount of time.

## What to check before relying on the Reem by Vision date

1. **The completion date and grace period in the SPA**, since the registered date is 31 December 2026 and progress was 53% in July.
2. **A mortgage approval timed for the 70% payment**, as approvals usually carry an expiry date.
3. **DLD's project status service for project 3612**, for an inspection after July 2026.

## Frequently asked

### When will Reem by Vision be completed?

The registered completion date in the DLD project register is 31 December 2026. Vision Developments gave Q4 2026 at launch, and Property Finder shows December 2026.

### Is Reem by Vision finished?

No. It was 53.14% complete at the DLD inspection on 23 July 2026, the latest published by 11 October 2026.

### Has the Reem by Vision handover date been delayed?

Not officially. The Q4 2026 date from the May 2025 launch still stands in the DLD register. The July 2026 progress figure suggests the building will need longer than that.

### Is Soul by Vision due at the same time?

Vision Developments launched Reem and Soul on the same day, 13 May 2025, and gave both a Q4 2026 handover. Soul is in Dubai Production City and is registered as a separate DLD project.

## Sources

- DLD project register via Continental Club, Reem By Vision, inspection 23 Jul 2026, register updated 4 Oct 2026: https://continentalclub.ae/project/reem-by-vision-liwan/
- DLD project register via Continental Club, Dubai handover 2026 tracker, accessed 11 Oct 2026: https://continentalclub.ae/handover-2026/
- Dubai Handover, Reem by Vision (DLD inspection history), accessed 11 Oct 2026: https://dubaihandover.com/projects/3612-reem-by-vision
- Vision Developments, launch of REEM and SOUL, 13 May 2025: https://www.visiondevelopments.ae/blog/our-blog-1/vision-developments-launches-two-new-residential-projects-in-dubai-reem-and-soul-1
- Property Finder, Reem by Vision project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/vision-development/reem-by-vision
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status
