# When is the Peace Avenue by Peace Homes handover date?

URL: https://www.dxbrealtor.ai/answers/peace-avenue-by-peace-homes-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

The Dubai Land Department (DLD) register holds a completion date of 31 January 2029 for Peace Avenue by Peace Homes in Downtown Jebel Ali. A DLD inspection on 3 September 2026 put construction at 3.52%. Peace Homes Development's project page and Property Finder still show Q4 2027, so the marketed date and the registered date are more than a year apart.

## Key figures

- Registered completion date (DLD): 31 Jan 2029 (DLD register via Continental Club and Mitchell's, Oct 2026)
- Latest construction progress: 3.52% (DLD inspection, 3 Sep 2026)
- Developer's stated date: Q4 2027 (Peace Homes Development project page, accessed 11 Oct 2026)
- Gap between marketed and registered date: About 13 months (Q4 2027 (Property Finder, Dec 2027) vs 31 Jan 2029 (DLD))

## Peace Avenue by Peace Homes handover date: the latest position

The Dubai Land Department (DLD) project register holds 31 January 2029 as the completion date for Peace Avenue, registered as "Peace Avenue By Peace Homes" (project number 4146). The latest DLD inspection, on 3 September 2026, recorded 3.52% construction progress. Project details, prices and the payment plan are on the [Peace Avenue by Peace Homes](/projects/peace-avenue-by-peace-homes/) page.

Peace Homes Development's own project page still says "Handover Q4 2027", and Property Finder lists December 2027. These dates are about 13 months earlier than the register. For a tower that was 3.52% built 15 months before Q4 2027, the registered January 2029 date is the more realistic of the two.

## Peace Avenue by Peace Homes handover date by building

Peace Avenue is a single tower with 266 registered units, 259 homes and 7 shops.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Peace Avenue By Peace Homes | 3.52%, 3 Sep 2026 | 31 Jan 2029 | Q4 2027 (Peace Homes); Dec 2027 (Property Finder); Q2 2028 (DXB Off Plan) |

## How the Peace Avenue by Peace Homes handover date has changed

| Date | Event | Source |
|---|---|---|
| 14 Oct 2025 | First DLD inspection, no progress recorded | DLD register via Continental Club |
| 1 Jan 2026 | Registered construction start; Property Finder lists bookings opening | DLD register; Property Finder |
| 16 Mar 2026 | Official launch event; launch report gives completion Q1 2029 | Peace Homes; Alnair |
| 3 Sep 2026 | DLD inspection records 3.52% complete | DLD register via Continental Club |
| Oct 2026 | Developer page still says Q4 2027; register holds 31 Jan 2029 | Peace Homes; Mitchell's |

The registered date has not moved since launch on the evidence available. What differs is the marketing date, which has stayed at Q4 2027 on the developer's page and on Property Finder.

## What the Peace Avenue by Peace Homes handover date means for payments

The payment plan is 20% on booking, 40% during construction and 40% on handover (Property Finder; Continental Club). The 40% handover payment is the largest single instalment. On a AED 695,000 launch price studio, it comes to AED 278,000. If handover follows the registered date rather than the marketed one, that payment falls in early 2029, not late 2027. The construction instalments are linked to progress, so their timing also depends on how quickly the tower rises from 3.52%.

## What to check before relying on the Peace Avenue by Peace Homes date

1. **The completion date written in the SPA**, and whether it says Q4 2027 or matches the registered 31 January 2029.
2. **The grace period** the SPA allows after that date before any compensation or cancellation right applies.
3. **The next DLD inspection figure**, through the Dubai REST app under project number 4146. Progress of 3.52% in September 2026 leaves about 96% of the work for the remaining 29 months.
4. **The developer's first deliveries.** Data Habibi records no completed Peace Homes project on DLD records and one project past its announced handover date (accessed 11 October 2026).

## Frequently asked

### When will Peace Avenue be completed?

The DLD registered completion date is 31 January 2029. At the 3 September 2026 inspection the tower was 3.52% complete, with construction registered as starting on 1 January 2026.

### Is the Peace Avenue handover date Q4 2027 or 2029?

Both appear. Peace Homes Development's project page says Q4 2027 and Property Finder says December 2027. The DLD register says 31 January 2029, and Alnair's launch report of 16 March 2026 gave Q1 2029. The SPA for each unit sets the binding date.

### Has the Peace Avenue handover date been delayed?

No change has been announced by the developer. The registered date of 31 January 2029 was already reported at launch in March 2026, so the gap is between marketing material and the register rather than a later delay.

### How far along is Peace Avenue construction?

3.52% at the DLD inspection of 3 September 2026, up from no recorded progress at the inspection of 14 October 2025 (Continental Club).

## Sources

- Continental Club, Peace Avenue By Peace Homes (DLD register), DLD inspection 3 Sep 2026, register updated 5 Oct 2026: https://continentalclub.ae/project/peace-avenue-by-peace-homes-downtown-jebel-ali/
- Mitchell's, Peace Avenue By Peace Homes, DLD registry, register as at 4 Oct 2026: https://www.mitchellscommercialrealty.com/off-plan/peace-avenue-by-peace-homes
- Continental Club, Dubai projects handing over in 2029, accessed 11 Oct 2026: https://continentalclub.ae/handover-2029/
- Peace Homes Development, Peace Avenue project page, accessed 11 Oct 2026: https://peacehomesdevelopment.com/project/peace-avenue
- Property Finder, Peace Avenue project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/peace-homes-group/peace-avenue
- Alnair, Peace Avenue launches in Jabal Ali Downtown, 16 Mar 2026: https://alnair.ae/en/news/peace-avenue-launches-in-jabal-ali-downtown-by-peace-homes-development
- DXB Off Plan, Peace Avenue, accessed 11 Oct 2026: https://dxboffplan.com/properties/peace-avenue-downtown-jebel-ali-dubai/
- Data Habibi, Peace Homes Development track record, accessed 11 Oct 2026: https://datahabibi.ae/dubai/developers/peace-homes-development