# When is the Palm Jebel Ali Frond M handover date?

URL: https://www.dxbrealtor.ai/answers/palm-jebel-ali-frond-m-handover-date/
Topic: Handover date
Updated: 2026-10-06

## Short answer

The Palm Jebel Ali Frond M handover date is 8 October 2027, the registered completion date on the Dubai Land Department (DLD) register for project 2594. At the latest DLD inspection, on 5 August 2026, Frond M was 40.29% complete, up from 28.52% on 30 April 2026 (Continental Club, registry updated 4 Oct 2026). Nakheel says the first Palm Jebel Ali villas hand over in phases from late 2026 through 2027 but has not named Frond M, and the frond still needs about 60 points of progress to finish.

## Key figures

- Registered completion date (DLD): 8 Oct 2027 (Project 2594. Continental Club; Property Finder)
- Latest construction progress: 40.29% (DLD inspection, 5 Aug 2026)
- Nakheel's stated date: Late 2026 to 2027 (First villas on the island, fronds not named. Nakheel via WAM, 20 Aug 2026)
- Progress needed to meet the date: About 4.3 points a month (Against about 3.7 a month between Apr and Aug 2026 inspections)

## Palm Jebel Ali Frond M handover date: the latest position

The Frond M handover date is 8 October 2027. That is the registered completion date the Dubai Land Department (DLD) holds for Palm Jebel Ali Frond M, project 2594, a group of 146 villas. Property Finder shows the same date and fäm Properties lists October 2027. Prices, villa sizes and the payment plan are on the [Palm Jebel Ali Frond M](/projects/palm-jebel-ali-frond-m/) page, and the wider island is covered at [Palm Jebel Ali](/projects/palm-jebel-ali/).

Frond M was 40.29% complete at the DLD inspection on 5 August 2026. Nakheel said on 20 August 2026 that the first villas on Palm Jebel Ali would be handed over in phases from late 2026 through 2027, and that the villas on Fronds K to P had entered internal and external finishing. It did not name Frond M, and no Frond M handover had been announced by 6 October 2026.

## Palm Jebel Ali Frond M handover date by frond

Frond M is one DLD project. The table sets it beside the other fronds in the same villa group.

| Frond | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| M (146 villas) | 40.29% (5 Aug 2026) | 8 Oct 2027 | Property Finder: Q4 2027. Nakheel: phased from late 2026 through 2027 |
| N | 47.10% (5 Aug 2026) | 8 Oct 2027 | Nakheel: phased from late 2026 through 2027 |
| O | 55.70% (4 Aug 2026) | 29 Sep 2027 | Nakheel: phased from late 2026 through 2027 |
| P | 34.65% (4 Aug 2026) | 29 Sep 2027 | Property Finder: Q3 2027 |
| K | 47.91% (5 Aug 2026) | 1 Dec 2027 | Nakheel: phased from late 2026 through 2027 |

Source: DLD register via Continental Club (2027 tracker, accessed 6 October 2026). Frond P has its own page: [Palm Jebel Ali Frond P handover date](/answers/palm-jebel-ali-frond-p-handover-date/). All fronds: [Palm Jebel Ali handover date](/answers/palm-jebel-ali-handover-date/).

## How the Palm Jebel Ali Frond M handover date has changed

| Date | What happened | Source |
|---|---|---|
| 27 Sep 2023 | Frond M goes on sale and construction is registered as starting | Property Finder; DLD register |
| 23 Oct 2025 | 9.57% complete | Property Finder |
| 12 Jan 2026 | DLD register puts all tracked Palm Jebel Ali projects between Oct 2027 and Oct 2028 | AGBI |
| 27 Jan 2026 | 19.73% at RERA inspection; fäm Properties shows October 2027 | Nakheel progress page; fäm Properties |
| 10 Mar 2026 | 22.10% at Nakheel internal inspection | Nakheel progress page |
| 30 Apr 2026 | 28.52% at DLD inspection | Continental Club |
| 16 Jun 2026 | Nakheel says first Palm Jebel Ali handovers start later in 2026 | Nakheel |
| 5 Aug 2026 | 40.29% at DLD inspection; registered date still 8 Oct 2027 | Continental Club |
| 20 Aug 2026 | Nakheel repeats late 2026 start, continuing through 2027 | Nakheel via WAM |

The registered date has stayed at October 2027 since at least January 2026. Frond M gained 11.77 points in the 97 days between the April and August 2026 inspections, about 3.7 points a month. Finishing the remaining 59.71 points by 8 October 2027 would need about 4.3 points a month, so the frond is close to the pace its date requires but not yet on it.

## What the Palm Jebel Ali Frond M handover date means for payments

Frond M was sold on a 20/60/20 plan: 20% on booking, 60% during construction and 20% on handover (Property Finder; Continental Club). The handover payment is 20% of the villa's price, for example AED 4.2 million on a villa bought at AED 21 million. It falls due when Nakheel issues the handover notice, so it moves if the frond finishes after 8 October 2027. The DLD register names Emirates NBD as the escrow bank. No post-handover plan has been published for Frond M.

## What to check before relying on the Palm Jebel Ali Frond M date

1. **The completion date in the SPA and its grace period**, which may differ from the register's 8 October 2027.
2. **The next DLD inspection for project 2594.** At the April to August 2026 pace, Frond M would reach 100% around December 2027, about two months after its registered date.
3. **Whether Nakheel names Frond M in its first handover phase.** Its late 2026 start has so far been stated for the island, not for any frond.
4. **On a resale, the Nakheel NOC and how much of the construction share is paid**, since the last 20% falls due at handover.

## Frequently asked

### What is the Frond M handover date?

8 October 2027, the registered completion date on the DLD register (Continental Club, registry updated 4 Oct 2026). Property Finder shows the same date and fäm Properties lists October 2027. Nakheel has only said that the first villas on Palm Jebel Ali hand over from late 2026 through 2027.

### Is Palm Jebel Ali Frond M finished?

No. It was 40.29% complete at the DLD inspection on 5 August 2026. Palm Observer found the same figure on the register on 3 September 2026.

### Has the Frond M handover date been delayed?

Not on the register. fäm Properties showed October 2027 when Frond M was 19.73% complete in January 2026, and the register still showed 8 October 2027 in October 2026. Progress has sped up: 9.57% in October 2025, 28.52% in April 2026 and 40.29% in August 2026.

### Do Frond M and Frond N hand over at the same time?

They share a registered completion date of 8 October 2027. Frond N was further along, at 47.10% on 5 August 2026, against 40.29% for Frond M (Continental Club).

## Sources

- Continental Club, Palm Jebel Ali Frond M (DLD registry and transactions), registry updated 4 Oct 2026: https://continentalclub.ae/project/palm-jebel-ali-frond-m-palm-jebel-ali/
- Continental Club, Dubai handover 2027 projects and progress (DLD register), accessed 6 Oct 2026: https://continentalclub.ae/handover-2027/
- Property Finder, Palm Jebel Ali Frond M project page, accessed 6 Oct 2026: https://www.propertyfinder.ae/en/new-projects/nakheel/palm-jebel-ali-frond-m
- fäm Properties, Palm Jebel Ali Frond M completion date, accessed 6 Oct 2026: https://famproperties.com/completion-date/palm-jebel-ali-frond-m
- Nakheel, Palm Jebel Ali construction progress page, 17 Jun 2026: https://www.nakheel.com/en/construction-progress/palm-jebel-ali
- Palm Observer, Palm Jebel Ali current status (DLD project status recheck), 3 Sep 2026: https://www.palmobserver.com/palm-jebel-ali-current-status/
- WAM, Nakheel unveils limited collection of 44 beachfront villas on Palm Jebel Ali, 20 Aug 2026: https://www.wam.ae/en/article/c1tv9cp-nakheel-unveils-limited-collection-beachfront
- Nakheel, Dubai's Palm Jebel Ali villas head for first handovers this year, 16 Jun 2026: https://www.nakheel.com/en/media-centre/press-releases/news-detail/2026/06/16/dubai-s-palm-jebel-ali-villas-head-for-first-handovers-this-year
- AGBI, Palm Jebel Ali homes ready from 2027, inspection reports say, 12 Jan 2026: https://www.agbi.com/analysis/real-estate/2026/01/palm-jebel-ali-assets-ready-from-2027-say-inspection-reports/
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status