# When is the Onda by Kasco handover date?

URL: https://www.dxbrealtor.ai/answers/onda-by-kasco-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Onda by Kasco has a registered completion date of 31 August 2027, and portals market it as Q3 2027. The last DLD inspection, on 19 August 2026, recorded the tower 61.1% complete. At launch in October 2024 Kasco promised Q2 2027, so the date has moved back about one quarter, but recent progress of about 3 points a month leaves the August 2027 date within reach.

## Key figures

- Registered completion date (DLD): 31 Aug 2027 (DLD register via Continental Club)
- Latest construction progress: 61.1% (DLD inspection, 19 Aug 2026)
- Developer's stated date: Q3 2027 (Kasco via MEP Middle East, 10 Jan 2025)
- Date promised at launch: Q2 2027 (Kasco, 23 Oct 2024)

## Onda by Kasco handover date: the latest position

Onda by Kasco is registered with the Dubai Land Department (DLD) for completion on 31 August 2027. Property Finder lists a delivery date of August 2027, in Q3 2027. Full project details are on the [Onda by Kasco](/projects/onda-by-kasco/) page.

The tower was 61.1% complete at the DLD inspection on 19 August 2026. Since May 2025 it has added about 3.2 points a month on average (Dubai Data), so the remaining work is roughly in line with the time left before the registered date.

## Onda by Kasco handover date by building

Onda is a single 23 storey building of 352 registered units in Business Bay, DLD project 3052.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Onda by Kasco | 61.1% (19 Aug 2026) | 31 Aug 2027 | Q3 2027 (Kasco, Jan 2025); August 2027 (Property Finder) |

| DLD inspection | Progress |
|---|---|
| 12 Feb 2025 | 8.6% |
| 28 May 2025 | 14.2% |
| 15 Sep 2025 | 20.5% |
| 29 Jan 2026 | 35.7% |
| 7 May 2026 | 51.5% |
| 19 Aug 2026 | 61.1% |

## How the Onda by Kasco handover date has changed

| Date | What happened | Source |
|---|---|---|
| 8 Aug 2024 | Registered with the DLD | DLD register via Dubai Data |
| 1 Sep 2024 | Registered construction start | DLD register |
| 23 Oct 2024 | Launch: completion and handover expected in Q2 2027 | Kasco via Construction Business News Middle East |
| 10 Jan 2025 | Kasco gives planned delivery in Q3 2027 | MEP Middle East |
| 19 Aug 2026 | 61.1% complete, date still 31 Aug 2027 | DLD register via Continental Club |

Since January 2025, Kasco's public date, the portals and the register's 31 August 2027 have all pointed to Q3 2027, one quarter after the launch promise.

## What the Onda by Kasco handover date means for payments

Onda is weighted towards handover. Most sources list 20% on booking, 10% during construction and 70% on handover, while Property Finder lists 20/20/60. One agent's schedule shows the construction instalments falling in December 2025, March 2026 and October 2026, with 60% on completion and no post-handover plan (Offplans.com). Under any version, the largest payment, 60% or 70% of the price, falls due when the building is handed over, so the handover date sets when that money is needed.

## What to check before relying on the Onda by Kasco date

1. **The completion date in the SPA.** Buyers from the October 2024 launch may hold contracts referring to Q2 2027 rather than 31 August 2027.
2. **The grace period in the SPA**, which sets how long after the contract date handover can slip before the buyer has any remedy.
3. **The bank's timeline for a handover mortgage**, since 60% to 70% of the price is due when the building completes.

## Frequently asked

### When will Onda by Kasco be completed?

The registered completion date is 31 August 2027. Property Finder lists August 2027, and Kasco gave Q3 2027 in January 2025.

### Has the Onda by Kasco handover date been delayed?

Slightly. Kasco said at launch in October 2024 that completion and handover were expected in Q2 2027. By January 2025 the planned delivery was Q3 2027, and the DLD register shows 31 August 2027.

### Is Onda by Kasco on track?

Progress rose from 35.7% on 29 January 2026 to 61.1% on 19 August 2026. At the average pace since May 2025, about 3.2 points a month (Dubai Data), the remaining 39 points would take roughly a year, close to the registered date.

### How much is paid at Onda by Kasco handover?

Between 60% and 70% of the price, depending on which plan the buyer signed. Most sources list 20/10/70; Property Finder lists 20/20/60.

## Sources

- DLD project register via Continental Club, Onda by Kasco, inspection 19 Aug 2026, registry updated 30 Sep 2026: https://continentalclub.ae/project/onda-by-kasco-business-bay/
- Continental Club, projects with handover in 2027, accessed 11 Oct 2026: https://continentalclub.ae/handover-2027/
- Dubai Data, Onda By Kasco, data through 7 Oct 2026: https://datadubai.ae/projects/onda-by-kasco/
- Construction Business News Middle East, KASCO Developments launches ONDA, 23 Oct 2024: https://www.cbnme.com/news/kasco-developments-launches-its-first-residential-project-onda-in-business-bay/
- MEP Middle East, KASCO Developments to self-fund VAL and ONDA, 10 Jan 2025: https://www.mepmiddleeast.com/projects/kasco-self-fund-val-and-onda-projects
- Property Finder, Onda by Kasco project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/kasco-properties/onda-by-kasco
- Offplans.com, Onda by Kasco payment schedule, accessed 11 Oct 2026: https://offplans.com/project/octa-properties-onda-by-kasco-by-kasco-developments
