# When is the Oasiz by Danube handover date?

URL: https://www.dxbrealtor.ai/answers/oasiz-by-danube-handover-date/
Topic: Handover date
Updated: 2026-10-01

## Short answer

The Oasiz by Danube handover date is 30 November 2027, the registered completion date on the Dubai Land Department (DLD) register, and Danube and Property Finder give the same November 2027. The DLD inspection of 29 July 2026 put the tower at 30.36% complete, and Danube's own inspection on 31 August 2026 reported 33%. Danube said on 30 July 2026 that Oasiz 1 and 2 were among 11 projects it would hand over within 12 months, earlier than the registered date, but no earlier date has been registered.

## Key figures

- Registered completion date (DLD): 30 Nov 2027 (DLD register, via Mitchells, accessed 1 Oct 2026)
- Latest construction progress: 30.36% (DLD site inspection, 29 Jul 2026. Danube reported 33% on 31 Aug 2026)
- Developer's stated date: Nov 2027 (Danube Properties, accessed 28 Sep 2026)
- Date change since launch: Dec 2027 to Nov 2027 (One month earlier. Launch date via Khaleej Times, 13 Sep 2024)

## Oasiz by Danube handover date: the latest position

Oasiz by Danube is due for completion on 30 November 2027. That is the registered completion date the Dubai Land Department holds for the tower, registered as Oasiz 1 by Danube, and Danube and Property Finder give the same November 2027. The DLD site inspection of 29 July 2026 recorded 30.36% complete, 20 months after the registered construction start of 1 December 2024. More on prices and sizes is on the [Oasiz by Danube](/projects/oasiz-by-danube/) page.

Danube's own inspection on 31 August 2026 put the tower at 33%, with the substructure finished, the 17th floor slab cast, blockwork up to the 12th floor and plastering up to the 6th. On 30 July 2026 Danube named Oasiz 1 and 2 among 11 projects it would hand over within 12 months, which would mean before the registered date. No earlier date has been registered.

## Oasiz by Danube handover date by building

Danube launched Oasiz as two towers. They are separate projects on the DLD register, with the same registered date.

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Oasiz 1 (this tower, 410 homes) | 30.36%, 29 Jul 2026 (Danube: 33%, 31 Aug 2026) | 30 Nov 2027 | Nov 2027 (Danube; Property Finder) |
| Oasiz 2 (separate project) | 31%, 29 Jul 2026 | 30 Nov 2027 | Nov 2027 (Property Finder) |

The DLD register describes Oasiz 1 as a basement, ground floor, four podium levels, 32 floors and a roof.

## How the Oasiz by Danube handover date has changed

The date has moved one month earlier since launch.

| Date | What happened | Source |
|---|---|---|
| 13 Sep 2024 | Danube unveils Oasiz 1 and 2, about 900 homes in all, for completion within 36 months, by December 2027. | Khaleej Times; Construction Week |
| 1 Dec 2024 | Booking opens and the DLD registers the construction start. Registered completion date 30 November 2027. | Property Finder; DLD register |
| 8 Dec 2025 | Property Finder marks Oasiz sold out. | Property Finder |
| 29 Jul 2026 | 30.36% complete at the DLD site inspection. | DLD register, via Mitchells |
| 30 Jul 2026 | Danube names Oasiz 1 and 2 among 11 projects to hand over within 12 months. | Danube, via GoDubai |
| 31 Aug 2026 | Danube reports 33%. | Danube Properties |

## What the Oasiz by Danube handover date means for payments

Oasiz launched on Danube's 1% monthly plan. Property Finder lists the plan as 10% down, 55% during construction and 35% on handover. A broker listing from the launch describes the same 35% as spread over 35 months after handover, so sources disagree on whether it falls due at once. On Property Finder's starting price of AED 769,000, 35% is AED 269,150. If Danube hands over before 30 November 2027, as its July 2026 statement suggests, any lump sum due on handover would fall due earlier too.

## What to check before relying on the Oasiz by Danube date

1. **Whether your unit is in Oasiz 1 or Oasiz 2.** They share a name, a site and a registered date, but are separate DLD projects with separate progress figures.
2. **How your SPA treats the 35%.** It is listed both as a handover payment and as a 35 month post-handover plan.
3. **What triggers the handover payment.** If handover comes early, check the notice period the SPA gives before that payment is due.
4. **Which progress figure you are reading.** Danube's 33% and the DLD's 30.36% are from inspections a month apart; the DLD figure for project 3259 is the official one.

## Frequently asked

### What is the Oasiz by Danube completion date?

30 November 2027. This is the registered completion date on the DLD register for Oasiz 1 by Danube, project number 3259, and Danube and Property Finder give November 2027 (accessed 28 Sep and 1 Oct 2026).

### Is Oasiz by Danube finished?

No. The DLD inspection of 29 July 2026 put it at 30.36% complete. Danube's inspection on 31 August 2026 reported 33%, with the 17th floor slab cast, blockwork up to the 12th floor and plastering up to the 6th floor.

### Has the Oasiz by Danube handover date been delayed?

No. At the launch in September 2024, Danube said Oasiz would be completed within 36 months, by December 2027. The registered date is 30 November 2027, one month earlier, and Danube said in July 2026 it expected to hand over Oasiz 1 and 2 within 12 months.

### When will Oasiz 2 be handed over?

Oasiz 2 is a separate DLD project next to Oasiz 1 with the same registered completion date, 30 November 2027. It was 31% complete at its DLD inspection on 29 July 2026 (Continental Club, DLD data).

### How much is due at the Oasiz by Danube handover?

Property Finder lists 10% down, 55% during construction and 35% on handover. A broker listing from the launch describes the 35% as paid over 35 months after handover instead, so the split in each buyer's SPA is the one that applies.

## Sources

- Mitchells Commercial Realty, Oasiz 1 by Danube DLD registry (project 3259), accessed 1 Oct 2026: https://www.mitchellscommercialrealty.com/off-plan/oasiz-1-by-danube
- Danube Properties, Oasiz construction updates, 31 Aug 2026: https://danubeproperties.com/construction/oasiz/
- Danube Properties, Oasiz, accessed 28 Sep 2026: https://danubeproperties.com/portfolio/oasiz/
- Continental Club, Dubai handover 2027 tracker (DLD project registry), accessed 1 Oct 2026: https://continentalclub.ae/handover-2027/
- Property Finder, Danube Oasiz project page, accessed 1 Oct 2026: https://www.propertyfinder.ae/en/new-projects/danube-properties/danube-oasiz
- Khaleej Times, Danube Properties unveils two mega projects set for launch soon, 13 Sep 2024: https://www.khaleejtimes.com/kt-network/danube-properties-unveils-two-mega-projects-set-for-launch-soon
- Construction Week Online, Danube launches two new projects, 13 Sep 2024: https://www.constructionweekonline.com/news/dubai-real-estate-danube-launches-two-new-projects
- GoDubai, Danube Properties announces handover of 11 projects in Dubai over next 12 months, 30 Jul 2026: https://www.godubai.com/citylife/press_release_page.asp?pr=193241
- Dubai Master Plan Real Estate, Danube Oasiz payment plan, 13 Sep 2024: https://dubaimasterplan.com/properties/danube-oasiz-in-dubai-silicon-oasis/
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status