# When is the Myra Onyx handover date?

URL: https://www.dxbrealtor.ai/answers/myra-onyx-handover-date/
Topic: Handover date
Updated: 2026-10-11

## Short answer

Myra Onyx had a registered completion date of 12 September 2026, and Property Finder also lists September 2026, but that date has passed. The building was 66.77% complete at the last Dubai Land Department (DLD) inspection on 2 July 2026. Agent listings now show Q4 2026, and at the recorded pace the building would reach 100% around March 2027.

## Key figures

- Registered completion date (DLD): 12 Sep 2026 (DLD register via Continental Club; date passed)
- Latest construction progress: 66.77% (DLD inspection, 2 Jul 2026)
- Developer's date at launch: Sep 2026 (Property Finder, sales started 13 Sep 2024)
- Listing date now: Q4 2026 (Bayut and Property Finder listings, 2026)

## Myra Onyx handover date: the latest position

The DLD register gave Myra Onyx a registered completion date of 12 September 2026, and that date has passed. At the last DLD inspection, on 2 July 2026, the building was 66.77% complete. Prices, sizes and the plan are on the [Myra Onyx](/projects/myra-onyx/) page.

Listings for the building now give Q4 2026, while Property Finder's project page still shows September 2026. Myra Properties has not published a revised date. Based on the pace between December 2025 and July 2026, Continental Club estimates 100% around 18 March 2027, which is a calculation rather than a developer date.

## Myra Onyx handover date by building

Myra Onyx is one G+12 building with 60 apartments, listed on the register as "Myra Onyx" (project 4308).

| Building | Construction progress (DLD, date) | Registered completion date | Developer or portal date |
|---|---|---|---|
| Myra Onyx (60 units) | 66.77% (2 Jul 2026) | 12 Sep 2026 | Sep 2026 on Property Finder; Q4 2026 in listings |

The previous inspection, on 25 December 2025, recorded 42.58%. The gain of 24.19 points in just over six months works out at about 3.9 points a month (Continental Club), well above the 2.48 points a month Continental Club gives as the median pace across Dubai projects. The 60 units are 20 one bedroom and 40 two bedroom apartments, and the project's escrow account is with First Abu Dhabi Bank (Continental Club). All 27 sales registered in 2026 were from the developer, with no resales recorded.

## How the Myra Onyx handover date has changed

- **13 September 2024:** sales and construction start, with expected completion on 12 September 2026 (Property Finder; DLD register).
- **25 December 2025:** DLD inspection records 42.58%.
- **6 February 2026:** a Bayut listing gives Q3 2026 in its details and "expected completion by December 2026" in its text.
- **2 July 2026:** DLD inspection records 66.77%.
- **July 2026:** listings show Q3 or Q4 2026 (Bayut, 29 July 2026; Property Finder).
- **12 September 2026:** the registered completion date passes without completion.

## What the Myra Onyx handover date means for payments

Under the 20/80 plan in listings, buyers pay 10% on booking and 10% within 30 days, then 80% on handover (Bayut, February and July 2026). Nothing is tied to construction stages. That means the delay leaves most of the price unpaid until the building is complete. For a 1 bedroom at the 2026 DLD median of AED 934,000, the handover payment would be AED 747,200. For a 2 bedroom at the median of AED 1,461,000, it would be AED 1,168,800.

## What to check before relying on the Myra Onyx date

1. **The completion date and grace period in the SPA**, since the registered date has already passed.
2. **Whether the developer has applied to DLD for an extension**, which would show as a new registered date for project 4308.
3. **Financing for the 80% handover payment**, including a mortgage offer that will still be valid when the building is completed.
4. **The next DLD inspection figure**, as the last public one dates from July 2026.

## Frequently asked

### Is Myra Onyx finished?

No. It was 66.77% complete at the DLD inspection on 2 July 2026, against a registered completion date of 12 September 2026 (DLD register via Continental Club).

### What is the Myra Onyx completion date?

The registered completion date is 12 September 2026, which has passed. Listings show Q4 2026, and one February 2026 listing said December 2026. Continental Club's pace estimate puts 100% at around 18 March 2027.

### Has the Myra Onyx handover date been delayed?

In practice, yes. The two year schedule set at launch in September 2024 ended on 12 September 2026, and the building was about two thirds built two months before that. Myra Properties has not published a new date.

### How much is due at the Myra Onyx handover?

Listings give a 20/80 plan, so 80% of the price is due on handover (Bayut, Feb and Jul 2026).

## Sources

- Continental Club, Myra Onyx (DLD project register, project 4308), inspection 2 Jul 2026, accessed 11 Oct 2026: https://continentalclub.ae/project/myra-onyx-nadd-al-hamar/
- Continental Club, Dubai handovers in 2026 (DLD project register), accessed 11 Oct 2026: https://continentalclub.ae/handover-2026/
- Property Finder, Myra Onyx project page, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/new-projects/myra-real-estate-deveiopment-l-l-c/myra-onyx
- Bayut, Myra Onyx 1 bedroom listing (20% payment plan, handover 2026), added 6 Feb 2026: https://www.bayut.com/property/details-14223089.html
- Bayut, Myra Onyx 2 bedroom listing, listed 29 Jul 2026: https://www.bayut.com/property/details-16001140.html
- Property Finder, Myra Onyx 1 bedroom listing, accessed 11 Oct 2026: https://www.propertyfinder.ae/en/plp/buy/apartment-for-sale-dubai-nadd-al-hammar-myra-onyx-126098327.html
- DLD, real estate project status enquiry: https://backoffice.dubailand.gov.ae/en/eservices/real-estate-project-status-landing/real-estate-project-status